Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 340.17 88.2 25.93  
1 COOCHBEHAR Cooch Behar - I Coochbehar Division BRAHMOTTAR KASAL DANGA PIPED WATER SUPPLY SCHEME. , SM/13214 New Execution of different works related to BRAHMOTTAR KASAL DANGA Z1 PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 999/1-5/NBC-1; Dt.: 24-01-23 ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION ORD/000486/2022-2023 1551/CD 24/01/2023 150 SWAPAN KUMAR ROY 317.38 88.20 27.79 60
2 COOCHBEHAR Cooch Behar - I Coochbehar Division BRAHMOTTAR KASAL DANGA PIPED WATER SUPPLY SCHEME. , SM/13214 New Execution of different works related to BRAHMATTAR KASALDANGA PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000345/2023-2024 1329/CD 24/11/2023 60 GOUTAM KUMAR DAS 22.79 0.00 0 98
Total 340.17 88.20 25.93