Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
9 | 440.52 | 183.81 | 41.73 | ||||||||||||||
1 | COOCHBEHAR | Mathabhanga - I | Coochbehar Division | BARA GOPALPUR PIPED WATER SUPPLY SCHEME. , SM/13161 | New | Material Requisition To Resource Division | RTOR000081/2023-2024 | 188/CD | 27/04/2023 | Resource Division | 19.93 | 0.00 | 0 | 0 | |||
2 | COOCHBEHAR | Mathabhanga - I | Northern Mechanical Division II | BARA GOPALPUR PIPED WATER SUPPLY SCHEME. , SM/13161 | New | Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Bara Gopalpur water supply scheme, TW no I and II under NMD-II, PHE Dte.APD | Assistant Engineer, Cooch-Behar Mechanical Sub-Division | Junior Engineer 4, Cooch-Behar Mechanical Sub-Division, | ORD/001128/2023-2024 | 2871/NMD-II | 17/10/2023 | 30 | RMD TRADING | 22.08 | 0.00 | 0 | 0 |
3 | COOCHBEHAR | Mathabhanga - I | Northern Mechanical Division II | BARA GOPALPUR PIPED WATER SUPPLY SCHEME. , SM/13161 | New | ELECTRIC QUOTATION BILL FOR NSC AT BARA GOPALPUR TW I | BILL/02047/2023-2024 | BP-2023-24-424 | 05/12/2023 | WBSEDCL | 4.31 | 0.00 | 0 | 0 | |||
4 | COOCHBEHAR | Mathabhanga - I | Coochbehar Division | BARA GOPALPUR PIPED WATER SUPPLY SCHEME. , SM/13161 | New | EXECUTION OF DIFFERENT WORKS AT KHAGRABARI PWSS | BILL/01320/2023-2024 | BP-816 | 22/12/2023 | BIJOY ROY | 7.78 | 0.00 | 0 | 0 | |||
5 | COOCHBEHAR | Mathabhanga - I | Coochbehar Division | BARA GOPALPUR PIPED WATER SUPPLY SCHEME. , SM/13161 | New | FHTC AT KHAGRABARI PWSS | BILL/01392/2023-2024 | BP-830-P2 | 30/12/2023 | AASHIRBAD ENTERPRISE | 0.50 | 0.00 | 0 | 0 | |||
6 | COOCHBEHAR | Mathabhanga - I | Coochbehar Division | BARA GOPALPUR PIPED WATER SUPPLY SCHEME. , SM/13161 | New | EXECUTION OF DIFFERENT WORK AT JAIGIRI CHILAKHANA PWSS | BILL/02053/2023-2024 | BP-1400 | 31/03/2024 | GHOSH AND SAHA CONSTRUCTION | 4.98 | 0.00 | 0 | 0 | |||
7 | COOCHBEHAR | Mathabhanga - I | Coochbehar Division | BARA GOPALPUR PIPED WATER SUPPLY SCHEME. , SM/13161 | New | Execution of different works related to BARO GOPALPUR PWSS under JAL JEEVAN MISSION | ASSISTANT ENGINEER, MATHABHANGA SUB-DIVISION | JUNIOR ENGINEER, MATHABHANGA SUB-DIVISION | ORD/000361/2023-2024 | 1396/CD | 05/12/2023 | 60 | SUBHAS CHANDRA ROY | 52.75 | 0.00 | 0 | 70 |
8 | COOCHBEHAR | Mathabhanga - I | Coochbehar Division | BARA GOPALPUR PIPED WATER SUPPLY SCHEME. , SM/13161 | New | Execution of different works related to BARA GOPALPUR PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1109/1-5/NBC-1; Dt.: 13-02-23 | ASSISTANT ENGINEER, MATHABHANGA SUB-DIVISION | JUNIOR ENGINEER, MATHABHANGA SUB-DIVISION | ORD/000586/2022-2023 | 1671/CD | 13/02/2023 | 150 | SUBHAS CHANDRA ROY | 324.18 | 183.81 | 56.7 | 10 |
9 | COOCHBEHAR | Mathabhanga - I | Northern Mechanical Division II | BARA GOPALPUR PIPED WATER SUPPLY SCHEME. , SM/13161 | New | ELECTRIC QUOTATION BILL FOR NEW SERVICE CONNECTION AT BARAGOPALPUR TW II. | BILL/00518/2024-2025 | BP-121/24-25 | 24/05/2024 | WBSEDCL | 4.01 | 0.00 | 0 | null | |||
Total | 440.52 | 183.81 | 41.73 |