Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 76.68 31.11 40.57  
1 COOCHBEHAR Coochbehar Division Rejuvenation of KALAPANI Water Supply Scheme , SM/10359 Augmentation FHTC VCH/001648/2021-2022 BP-2021_22_472 23/03/2022 SANKAR BANIK 4.93 0.00 0 0
2 COOCHBEHAR Coochbehar Division Rejuvenation of KALAPANI Water Supply Scheme , SM/10359 Augmentation Sinking of 250mm x 200 mm Big dia. Tube well with UPVC Pipes & Strainer at 3rd Site of Kalpani PWSS under Cooch Behar Division PHE Dte ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000027/2022-2023 43/CD 07/04/2022 45 SWAPAN KUMAR ROY 12.01 0.00 0 1
3 COOCHBEHAR Coochbehar Division Rejuvenation of KALAPANI Water Supply Scheme , SM/10359 Augmentation FHTC AT KALAPANI VCH/000765/2022-2023 271 21/09/2022 SWAPAN KUMAR ROY 11.98 0.00 0 0
4 COOCHBEHAR Coochbehar Division Rejuvenation of KALAPANI Water Supply Scheme , SM/10359 Augmentation Providing FHTC Works, Laying of pipe line Constructions of 3rd site Pump House, Boundary Wall at KALAPANI W.S.S under Cooch Behar Division P.H.E.Dte. ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000532/2021-2022 1632/CD 29/03/2022 60 SIDHARTHA ROY 35.55 20.28 57.05 1
5 COOCHBEHAR Northern Mechanical Division II Rejuvenation of KALAPANI Water Supply Scheme , SM/10359 Augmentation Quotation for new service connection at Kalapani W/SS TW No-III BILL/00248/2022-2023 BP-137/22-23 31/01/2023 WBSEDCL 0.92 0.00 0 0
6 COOCHBEHAR Coochbehar Division Rejuvenation of KALAPANI Water Supply Scheme , SM/10359 Augmentation fhtc at pwss VCH/000352/2022-2023 341 p 25/10/2022 NARAYAN CHANDRA BANIK 0.00 0.00 NAN 0
7 COOCHBEHAR Northern Mechanical Division II Rejuvenation of KALAPANI Water Supply Scheme , SM/10359 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Rejuvenation of Kalapani PWSS, TW no III in the district of CoochBehar under Northern Mechanical Division-II,PHE Dte,Alipurduar. Assistant Engineer, Cooch-Behar Mechanical Sub-Division Junior Engineer 2, Cooch-Behar Mechanical Sub-Division, ORD/000734/2022-2023 73/NMD-II 09/01/2023 30 B.B CONCERNED 11.29 10.83 95.93 100
Total 76.68 31.11 40.57