Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 322.45 0 0  
1 COOCHBEHAR Northern Mechanical Division II AUGMENTATION OF GURIAHATI PIPED WATER SUPPLY SCHEME , SM/09298 Augmentation Renovation of complete electrical arrangement at Guriahati W/S/S, T.W. No. II in the dist. of Cooch Behar , P.H.E Dte. Assistant Engineer, Cooch-Behar Mechanical Sub-Division Junior Engineer 2, Cooch-Behar Mechanical Sub-Division, ORD/000686/2021-2022 572/CMSD 27/08/2021 7 DIPA CHHETRI 0.52 0.00 0 0
2 COOCHBEHAR Coochbehar Division AUGMENTATION OF GURIAHATI PIPED WATER SUPPLY SCHEME , SM/09298 Augmentation Material Requisition To Resource Division RTOR000001/2023-2024 108/CD 26/04/2023 0 Resource Division 9.74 0.00 0 0
3 COOCHBEHAR Coochbehar Division AUGMENTATION OF GURIAHATI PIPED WATER SUPPLY SCHEME , SM/09298 Augmentation Execution of different works related to GURIAHATI PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000168/2023-2024 945/CD 04/09/2023 90 CHAKRABORTY ENTERPRISE 32.83 0.00 0 92
4 COOCHBEHAR Coochbehar Division AUGMENTATION OF GURIAHATI PIPED WATER SUPPLY SCHEME , SM/09298 Augmentation Supply and delivery of 200 mm dia UPVC pipe(CD) for Guriahati 3rd Site Tubewell under Cooch Behar Division , P.H.E Dte. ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000521/2021-2022 1569/CD 23/03/2022 15 DAFFODIL 2.95 0.00 0 1
5 COOCHBEHAR Coochbehar Division AUGMENTATION OF GURIAHATI PIPED WATER SUPPLY SCHEME , SM/09298 Augmentation Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Sitai Water Supply Scheme under Cooch Behar Division, PHED. ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000827/2022-2023 2047/CD 31/03/2023 61 BIPASHA MAHANTA BANIK 0.98 0.00 0 0
6 COOCHBEHAR Coochbehar Division AUGMENTATION OF GURIAHATI PIPED WATER SUPPLY SCHEME , SM/09298 Augmentation Execution of different works related to AUG. of GURIAHATIZ1 & 2 PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000407/2023-2024 1374/CD 05/12/2023 60 CHAKRABORTY ENTERPRISE 5.27 0.00 0 97
7 COOCHBEHAR Coochbehar Division AUGMENTATION OF GURIAHATI PIPED WATER SUPPLY SCHEME , SM/09298 Augmentation Material Requisition To Resource Division RTOR000015/2024-2025 1892/CD 06/11/2024 0 Resource Division 49.28 0.00 0 0
8 COOCHBEHAR Coochbehar Division AUGMENTATION OF GURIAHATI PIPED WATER SUPPLY SCHEME , SM/09298 Augmentation Construction of 150 cum OHR Providing FHTC Sinking 250mm X 200mm Big dia Tubewell & New UPVC/DI Pipe line & other allied works (PART ¿A) at GURIAHATI PWSS under Cooch Behar Division, PHED ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION,CONTRACTUAL ASSISTANT ENGINEER, COOCHBEHAR DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION,JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION ORD/000274/2021-2022 953/CD 31/12/2021 1324 S & P ENTERPRISE 143.02 0.00 0 78
9 COOCHBEHAR Northern Mechanical Division II AUGMENTATION OF GURIAHATI PIPED WATER SUPPLY SCHEME , SM/09298 Augmentation Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of Guriahati Water Supply Scheme TW No.- III and IV under NMD-II,PHE.Dte,APD. Assistant Engineer, Cooch-Behar Mechanical Sub-Division Junior Engineer 2, Cooch-Behar Mechanical Sub-Division, ORD/001246/2023-2024 2973/NMD-II 22/11/2023 30 WILFUL UNEMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 20.23 0.00 0 70
10 COOCHBEHAR Coochbehar Division AUGMENTATION OF GURIAHATI PIPED WATER SUPPLY SCHEME , SM/09298 Augmentation Execution of different works related to GURIAHATI PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION,JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION ORD/000351/2023-2024 1335/CD 24/11/2023 481 RAHAMAN ENTERPRISE 57.63 0.00 0 30
Total 322.44 0.00 0