Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 19,829.63 8.78 0.04  
1 COOCHBEHAR Coochbehar Division Rejuvination of Takoamari water supply scheme , SM/09294 Augmentation FHTC TAKOMARI VCH/000391/2022-2023 BP-22-23-124 11/07/2022 ORIENTAL CO OP LABOUR CONTRACT CONSTRUCTION SO 19.43 0.00 0 0
2 COOCHBEHAR Coochbehar Division Rejuvination of Takoamari water supply scheme , SM/09294 Augmentation Sinking of 250mm x 200 mm Big dia. Tube well with UPVC Pipes & Strainer at 3rd Site of TAKOAMARI PWSS under Cooch Behar Division PHE Dte ASSISTANT ENGINEER, TUFANGANJ SUB-DIVISION JUNIOR ENGINEER, TUFANGANJ SUB-DIVISION ORD/000511/2021-2022 1459/CD 10/03/2022 30 AUXILIARY TUBEWELL DRILLERS 10.70 8.78 82.06 1
3 COOCHBEHAR Northern Mechanical Division II Rejuvination of Takoamari water supply scheme , SM/09294 Augmentation QUOTATION FOR NEW SERVICE CONNECTION AT TAKOAMARI TW NO III BILL/00543/2022-2023 BP-169/22-23 29/03/2023 WBSEDCL 1.06 0.00 0 0
4 COOCHBEHAR Northern Mechanical Division II Rejuvination of Takoamari water supply scheme , SM/09294 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Rejuvenation of Takoamari water supply scheme, TW no III under Northern Mechanical Division-II, PHE Dte.Alipurduar. Assistant Engineer, Cooch-Behar Mechanical Sub-Division Junior Engineer 3, Cooch-Behar Mechanical Sub-Division, ORD/000029/2023-2024 955/NMD-II 12/05/2023 30 MADHAB SAHA 9.15 0.00 0 0
5 COOCHBEHAR Coochbehar Division Rejuvination of Takoamari water supply scheme , SM/09294 Augmentation Laying of DI line along both the flanks of Roads in Cooch Behar District under Cooch Behar Division PHE Dte. CONTRACTUAL ASSISTANT ENGINEER, COOCHBEHAR DIVISION JUNIOR ENGINEER, RWS COOCH BEHAR SUB-DIVISION ORD/000339/2024-2025 1264/CD 02/07/2024 300 MACKINTOSH BURN LIMITED 19,789.29 0.00 0 0
Total 19,829.63 8.78 0.04