| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 14 | 990.99 | 152.3 | 15.37 | ||||||||||||||
| 1 | JALPAIGURI | Maynaguri | Jalpaiguri Division | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Material Requisition To Resource Division | RTOR000043/2023-2024 | 1112/JD | 24/08/2023 | 0 | Resource Division | 122.36 | 0.00 | 0 | 0 | ||
| 2 | JALPAIGURI | Maynaguri | Jalpaiguri Division | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Material Requisition To Resource Division | RTOR000112/2023-2024 | 1506/JD | 13/10/2023 | 0 | Resource Division | 15.68 | 0.00 | 0 | 0 | ||
| 3 | JALPAIGURI | Maynaguri | Jalpaiguri Division | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Construction of Boundary Wall at 3rd Pump House site of Brahmapur PWSS in connection with Jal Jeevan Mission at Block - Maynaguri under Jalpaiguri Division PHE, DTE. | Assistant Engineer | Junior Engineer | ORD/000098/2024-2025 | 1299/JD | 05/09/2024 | 60 | M/S KARMAKAR CONSTRUCTION | 10.93 | 0.00 | 0 | 0 |
| 4 | JALPAIGURI | Maynaguri | Jalpaiguri Division | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Balance Laying Distribution System and Providing Functional House Hold Tap Connection at Brahmapur PWSS in Maynaguri Block under Jalpaiguri Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/000458/2024-2025 | 2335./JD | 12/12/2024 | 60 | SANDIP BANIK | 61.25 | 0.00 | 0 | 0 |
| 5 | JALPAIGURI | Maynaguri | Jalpaiguri Division | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Construction of Boundary Wall at 2nd Pump House site of Brahmapur PWSS in connection with Jal Jeevan Mission at Block - Maynaguri under Jalpaiguri Division, P.H.E.Dte. | Assistant Engineer | ORD/000083/2024-2025 | 802/RWS | 20/08/2024 | 30 | TECHNO CRACY | 7.49 | 0.00 | 0 | 0 | |
| 6 | JALPAIGURI | Maynaguri | Jalpaiguri Division | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Execution of Wall writing for creating awareness program in connection with Jal Jeevan Mission for Part-B of Maynaguri Block under Jalpaiguri Division P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/000034/2024-2025 | 941/JD | 07/08/2024 | 15 | PRITAM DUTTA | 4.83 | 4.83 | 100 | 100 |
| 7 | JALPAIGURI | Maynaguri | Jalpaiguri Division | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Material Requisition To Resource Division | RTOR000192/2023-2024 | 2053/JD | 09/01/2024 | 0 | Resource Division | 15.68 | 0.00 | 0 | 0 | ||
| 8 | JALPAIGURI | Maynaguri | Northern Mechanical | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | New Service Connection Charge for Brahmapur, T/W-III under BHOTPATTY CCC APPLICATION NO. 4003377837 Reference ID : 403192843 | BILL/00288/2024-2025 | BP/24-25/43 | 28/05/2024 | 0 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED | 4.64 | 0.00 | 0 | 0 | ||
| 9 | JALPAIGURI | Maynaguri | Northern Mechanical | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | New Service Connection Charge for Brahmapur, T/W-II under BHOTPATTY CCC APPLICATION NO. 4003375994 Reference ID : 403191703 | BILL/00208/2024-2025 | BP/24-25/14 | 23/04/2024 | 0 | WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED | 7.64 | 0.00 | 0 | 0 | ||
| 10 | JALPAIGURI | Maynaguri | Northern Mechanical | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for BRAHAMPURI PWSS, TW no I, II and III in the district of Jalpaiguri under Northern Mechanical Division, PHE Dte. | Assistant Engineer , Head Quarters , NMD | Junior Engineer | ORD/000825/2022-2023 | 267/NMD | 21/03/2023 | 895 | DAS ENTERPRISE | 32.59 | 0.00 | 0 | 65 |
| 11 | JALPAIGURI | Maynaguri | Jalpaiguri Division | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Construction of different components of Brahmapur PWSS i.e. TW, Pump Houses, Water distribution Network, OHR, RISING MAIN, FHTC etc. i.c.w. Jal Jeevan Mission at Block- Maynaguri under Jalpaiguri Division, P.H.E.Dte. | Assistant Engineer | Junior Engineer | ORD/000436/2023-2024 | 1670/JD | 24/11/2023 | 495 | NARAYAN CHANDRA SAHA | 597.49 | 147.47 | 24.68 | 50 |
| 12 | JALPAIGURI | Maynaguri | Northern Mechanical | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Installation of two tank chlorination system at different water supply scheme of JJM under Maynaguri Block in the district of Jalpaiguri under Northern Mechanical Division, P.H.E. Dte. | Assistant Engineer , Head Quarters , NMD | Junior Engineer | ORD/000776/2024-2025 | 290/HQ/NMD | 24/01/2025 | 30 | S.P. ENTERPRISE | 2.00 | 0.00 | 0 | 0 |
| 13 | JALPAIGURI | Maynaguri | Northern Mechanical | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Yard lighting arrangement at Head Work Site for Different PWSS under JJM in the BLOCK: MAYNAGURI, DISTRICT: JALPAIGURI under Northern Mechanical Division, P.H.E. Dte. | Assistant Engineer , Head Quarters , NMD | Junior Engineer | ORD/001006/2024-2025 | 26/NMD | 06/01/2025 | 30 | M/S SWAPAN BANERJEE | 15.35 | 0.00 | 0 | 0 |
| 14 | JALPAIGURI | Maynaguri | Northern Mechanical | BRAHMAPUR PIPED WATER SUPPLY SCHEME , SM/13705 | New | Solarisation of WBSEDCL Energised Electrical Installation at different piped water supply schemes in connection with Jal Jeevan Mission in the Jalpaiguri District( Maynaguri Block) under Northern Mechanical Division, P.H.E. Dte. | Assistant Engineer , Head Quarters , NMD | Junior Engineer | ORD/000002/2025-2026 | 961/NMD | 03/04/2025 | 120 | SILIGURI VYAPAR PRIVATE LIMITED | 93.06 | 0.00 | 0 | 0 |
| Total | 990.97 | 152.30 | 15.37 | ||||||||||||||