Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 2,116.85 1,792.2 84.66  
1 DARJEELING Jorebunglow Sukiapokhri Neorakhola W/S & Mtc.Div. GRAVITY BASED WATER SUPPLY SCHEME FOR KALEJ VALLEY PWSS, BLOCK : JORE BUNGALOW-SUKHIAPOKHRI - I, DISTRICT : DARJEELING , SM/18820 New Material Requisition To Resource Division RTOR000117/2023-2024 1174/NKWSMD 05/10/2023 0 Resource Division 3.20 0.00 0 0
2 DARJEELING Jorebunglow Sukiapokhri Neorakhola W/S & Mtc.Div. GRAVITY BASED WATER SUPPLY SCHEME FOR KALEJ VALLEY PWSS, BLOCK : JORE BUNGALOW-SUKHIAPOKHRI - I, DISTRICT : DARJEELING , SM/18820 New Continuation Engagement of 02 (Two) numbers Computer Operator (Graduate with Certificate in Computer Application) for the works related to Jal Jeevan Mission /Jal Swapno at the Office of the Executive Engineer, Neorakhola Water Supply & Maintenance Division, Public Health Engineering Directorate, Kalimpong for 01.08.2024 to 31.08.2024. Assistant Engineer II Junior Engineer I ORD/000096/2024-2025 1346/NKWSMD 31/07/2024 31 YAMA CONSTRUCTIONS LLP 0.39 0.00 0 100
3 DARJEELING Jorebunglow Sukiapokhri Neorakhola W/S & Mtc.Div. GRAVITY BASED WATER SUPPLY SCHEME FOR KALEJ VALLEY PWSS, BLOCK : JORE BUNGALOW-SUKHIAPOKHRI - I, DISTRICT : DARJEELING , SM/18820 New WATER SUPPLY SCHEME FOR KALEJ VALLEY PIPED WATER SUPPLY SCHEME IN JOREBUNGLOW SUKIAPOKHRI BLOCK UNDER DARJEELING DISTRICT. ORD/000202/2023-2024 1100/NKWSMD 21/09/2023 365 VINAYAK CONSTRUCTION 1,970.49 1,792.20 90.95 50
4 DARJEELING Jorebunglow Sukiapokhri Neorakhola W/S & Mtc.Div. GRAVITY BASED WATER SUPPLY SCHEME FOR KALEJ VALLEY PWSS, BLOCK : JORE BUNGALOW-SUKHIAPOKHRI - I, DISTRICT : DARJEELING , SM/18820 New ADDITIONAL WORK FOR KALEJ VALLEY PIPED WATER SUPPLY SCHEME UNDER BLOCK-JOREBUNGLOW SUKIAPOKRI DISTRICT-DARJEELING KURSEONG DIVISION PHED/GTA. ORD/000039/2025-2026 654/NKWSMD 05/05/2025 180 VINAYAK CONSTRUCTION 142.77 0.00 0 0
Total 2,116.86 1,792.20 84.66