Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
3 926.15 0 0  
1 DARJEELING Mirik Neorakhola W/S & Mtc.Div. PIPED WATER SUPPLY SCHEME FOR SOURINI BASTY PWSS IN MIRIK BLOCK UNDER DARJEELING DISTRICT , SM/16627 New Material Requisition To Resource Division RTOR000035/2023-2024 278/NKWSMD 17/05/2023 Resource Division 4.55 0.00 0 0
2 DARJEELING Mirik Neorakhola W/S & Mtc.Div. PIPED WATER SUPPLY SCHEME FOR SOURINI BASTY PWSS IN MIRIK BLOCK UNDER DARJEELING DISTRICT , SM/16627 New Material Requisition To Resource Division RTOR000005/2024-2025 736/NKWSMD 02/04/2024 Resource Division 4.55 0.00 0 0
3 DARJEELING Mirik Neorakhola W/S & Mtc.Div. PIPED WATER SUPPLY SCHEME FOR SOURINI BASTY PWSS IN MIRIK BLOCK UNDER DARJEELING DISTRICT , SM/16627 New WATER SUPPLY SCHEME FOR SAURINI BASTI PIPED WATER SUPPLY SCHEME IN MIRIK BLOCK UNDER DARJEELING DISTRICT. ORD/000041/2023-2024 224/NKWSMD 10/05/2023 240 GARGO TRADERS 917.05 0.00 0 50
Total 926.14 0.00 0