Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
3 | 1,097.22 | 648.09 | 59.07 | ||||||||||||||
1 | DARJEELING | Kurseong | Neorakhola W/S & Mtc.Div. | Piped Water Supply Scheme for Mahanadi tea Garden in Kurseong block under Darjeeling District , SM/16535 | New | Material Requisition To Resource Division | RTOR000007/2023-2024 | 154/NKWSMD | 03/05/2023 | Resource Division | 6.37 | 0.00 | 0 | 0 | |||
2 | DARJEELING | Kurseong | Neorakhola W/S & Mtc.Div. | Piped Water Supply Scheme for Mahanadi tea Garden in Kurseong block under Darjeeling District , SM/16535 | New | forest clearance of JJM schemes under kurseong Division PHED GTA. | BILL/00448/2023-2024 | BP-2023-24-289 | 01/11/2023 | DIVISIONAL FOREST OFFICER | 49.25 | 0.00 | 0 | 0 | |||
3 | DARJEELING | Kurseong | Neorakhola W/S & Mtc.Div. | Piped Water Supply Scheme for Mahanadi tea Garden in Kurseong block under Darjeeling District , SM/16535 | New | WATER SUPPLY SCHEME FOR MAHANADI TEA GARDEN PIPED WATER SUPPLY SCHEME IN KURSEONG BLOCK UNDER DARJEELING DISTRICT. | ORD/000005/2023-2024 | 92/NKWSMD | 27/04/2023 | 365 | VINAYAK CONSTRUCTION | 1,041.60 | 648.09 | 62.22 | 70 | ||
Total | 1,097.21 | 648.09 | 59.07 |