| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 3 | 19.93 | 16.93 | 84.95 | ||||||||||||||
| 1 | DARJEELING | Neorakhola W/S & Mtc.Div. | Providing Functional Household Tap Connection with pipeline retrofitting for PWS scheme at Barbotia (Lower and Upper) , SM/10773 | Retrofitting | Material Requisition To Resource Division | RTOR000125/2022-2023 | 1901/NKWSMD | 15/12/2022 | 0 | Resource Division | 0.86 | 0.00 | 0 | 0 | |||
| 2 | DARJEELING | Neorakhola W/S & Mtc.Div. | Providing Functional Household Tap Connection with pipeline retrofitting for PWS scheme at Barbotia (Lower and Upper) , SM/10773 | Retrofitting | Providing Functional household tap connection under JJM & JSP Programme including extension work for PWS Scheme for Upper & Lower Barbotia, Gram Panchyat -Rishihat Bloomfield, Block Bijanbari -PullBazar. TSM No. 009473 SM Code-SM/08932 | ORD/000035/2022-2023 | 498/NKWSMD | 24/05/2022 | 60 | PROSENJIT BASAK | 18.21 | 16.93 | 92.97 | 100 | |||
| 3 | DARJEELING | Neorakhola W/S & Mtc.Div. | Providing Functional Household Tap Connection with pipeline retrofitting for PWS scheme at Barbotia (Lower and Upper) , SM/10773 | Retrofitting | Material Requisition To Resource Division | RTOR000185/2022-2023 | 2580/NKWSMD | 17/02/2023 | 0 | Resource Division | 0.86 | 0.00 | 0 | 0 | |||
| Total | 19.92 | 16.93 | 84.98 | ||||||||||||||