Sl. No. | Division
Working Divisions
|
System Order No
System generated Order No. for the Work Order as per PHED-MIS
|
Order Date
Date of Issuance of the Work Order as per PHED-MIS
|
Memo Number
Memo no. for Work Order Provided by the Divisions as per PHED-MIS
|
Vendor Name
Vendor Appointed Against this Work Order as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Order Value
Value of Work as mentioned in the Work Order
|
---|---|---|---|---|---|---|---|
13 | 289.21 | ||||||
1 | Alipurduar Division | ORD/000383/2021-2022 | 31/01/2022 | 2383/ALD | GOUTAM KUMAR DAS | Construction of Pump House ,Boundary Wall and laying distribution system for Uttar Kamkhyaguri Piped Water Supply Scheme Under Alipurduar Division PHE DTE. | 90.80 |
2 | Alipurduar Division | ORD/000449/2021-2022 | 21/02/2022 | 2656/ALD | G.TECH INDIA. | Soil investigation work at 3 different places of Kalchini & Totpara within Alipurduar District under Alipurduar Division PHE Dte. | 3.67 |
3 | Alipurduar Division | ORD/000496/2021-2022 | 14/03/2022 | 71/PHE-Brp | MITHUN DAS | Supply of different Office Furniture & Articles for the office of the Assistant Engineer, Birpara Sub-Division, PHE Dte. | 1.06 |
4 | Alipurduar Division | ORD/000151/2022-2023 | 15/07/2022 | 985/ALD | S.G ENTERPRISE | Construction of OHR 200cum for KUMARGRAM ZONE-II Water Supply Scheme under Alipurduar Division, PHE Dte. | 55.09 |
5 | Alipurduar Division | ORD/000160/2022-2023 | 15/07/2022 | 990/ALD | UNIVERSAL ENTERPRISES | Construction of OHR 200cum for KUMARGRAM ZONE-III Water Supply Scheme under Alipurduar Division, PHE Dte. | 55.33 |
6 | Alipurduar Division | ORD/000162/2022-2023 | 15/07/2022 | 992/ALD | GOUTAM KUMAR DAS | Construction of 250cum OHR for KUMARGRAM ZONE-I Water Supply Scheme under Alipurduar Division, PHE Dte. | 57.30 |
7 | Alipurduar Division | ORD/000223/2022-2023 | 29/07/2022 | 1113/ALD | DAS CONSTRUCTION | Laying distribution of pipeline & Culvert crossing with DI pipe under Narathali WSS Alipurduar Division, PHE Dte. | 3.67 |
8 | Alipurduar Division | ORD/000317/2022-2023 | 21/11/2022 | 2226/ALD | MADHAB SAHA | Gap filling in laying distribution system by making culvert crossing and laying of DI and UPVC pipes under Narathali Water Supply Scheme under Alipurduar Division, PHE Dte. (Part-A) | 4.65 |
9 | Alipurduar Division | ORD/000318/2022-2023 | 21/11/2022 | 2227/ALD | HARI CONSTRUCTION | Gap filling in laying distribution system by making culvert crossing and laying of DI and UPVC pipes under Narathali Water Supply Scheme under Alipurduar Division, PHE Dte. (Part-B) | 3.45 |
10 | Alipurduar Division | ORD/000297/2022-2023 | 20/09/2022 | 1688/ALD | DILIP MAHATO | Laying of CIDF, Rising Main, Delivery line, Hydraulic Testing, disinfection of UPVC pipeline and other allied works at Bhutnirghat WSS under Alipurduar Division, PHE Dte. | 5.82 |
11 | Alipurduar Division | ORD/000413/2022-2023 | 30/12/2022 | 2728/ALD | APSARI BHOWMICK | Hiring of Diesel Vehicle Maxi Cab (At least 7 seater ) for Executive Engineer, Alipurduar Division, P.H.E. Dte.(from 01.01.2023 to 31.12.2023) | 4.80 |
12 | Alipurduar Division | ORD/000541/2022-2023 | 27/02/2023 | 288/RWS | DIPAK DAS | Tiffin Allowances for plumbing, fitting and Electrician Training at different ITI colleges under Alipurduar District | 0.79 |
13 | Alipurduar Division | ORD/000305/2022-2023 | 17/10/2022 | 1943/ALD | HARIDAS GHOSH | Drilling Rigbore tube well (ODEX-115 method) at Modakpara, Paschim Bholardabri under Alipurduar Division, PHE Dte. | 2.77 |
Total | 289.21 |