Sl. No. | Division
Working Divisions
|
System Order No
System generated Order No. for the Work Order as per PHED-MIS
|
Order Date
Date of Issuance of the Work Order as per PHED-MIS
|
Memo Number
Memo no. for Work Order Provided by the Divisions as per PHED-MIS
|
Vendor Name
Vendor Appointed Against this Work Order as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Order Value
Value of Work as mentioned in the Work Order
|
---|---|---|---|---|---|---|---|
2 | 23.94 | ||||||
1 | Central Mechanical Division | ORD/001644/2023-2024 | 15/03/2024 | 1526/CMD | D.K. ELECTRIC | Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.- 2 at Augumentation of Srikhanda Water Supply Scheme [ BLOCK- Katwa-I ]under CMD, PHE Dte., Dist.- Purba-Bardhama | 11.62 |
2 | Central Mechanical Division | ORD/001643/2023-2024 | 15/03/2024 | 1625/CMD | JOYGURU ENTERPRISE | Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.- 3 at Augumentation of Radhanagar Baghnapara Water Supply Scheme [ BLOCK- Kalna-I ]under CMD, PHE Dte., Dist.- Pur | 12.31 |
Total | 23.94 |