No. of unauthorized work order
Exception Report Showing the Status of Major Pending Works for the Divisions

Update Data
Rs. in Lakh
Sl. No. Division
Working Divisions
System Order No
System generated Order No. for the Work Order as per PHED-MIS
Order Date
Date of Issuance of the Work Order as per PHED-MIS
Memo Number
Memo no. for Work Order Provided by the Divisions as per PHED-MIS
Vendor Name
Vendor Appointed Against this Work Order as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Order Value
Value of Work as mentioned in the Work Order
3 50.83
1 RCFA Division I ORD/000055/2024-2025 18/07/2024 1745/RCD-I M/S MONDAL ENTERPRISE Acceptance cum Work Order for Additional work for laying Rising Main of Augmentation of Jamuria Rural (Zone-I and Zone-II) under RCFA Division-I PHE Dte. 28.19
2 RCFA Division I ORD/000062/2024-2025 27/06/2024 1590/RCD-I SAMIR KUMAR ROY CHOWDHURY Acceptance cum Work Order for Balance work of construction of CWR at Runakuraghat for Augmentation of Panuria Piped Water Supply Scheme under RCFA Division-I PHE Dte. 9.92
3 RCFA Division I ORD/000054/2024-2025 18/07/2024 1744/RCD-I NATIONAL CONSTRUCTION Acceptance cum Work Order for Additional work along with Construction of Guard room with Toilet for Construction of 150 cum capacity RCC OHR with 20 Mtr staging height RCC Over Head Reservoir Piped connection and cost of pipes, specials at Augmentation of 12.73
Total 50.83