Sl. No. | Division
Working Divisions
|
Bill Number | Bill Date
Date of Issuance of the Work Order as per PHED-MIS
|
Vendor Name
Vendor Appointed Against this Work Order as per PHED-MIS
|
System Order Number
System generated Order No. for the Work Order as per PHED-MIS
|
Memo Number
Memo no. for Work Order Provided by the Divisions as per PHED-MIS
|
Order Date
Date of Issuance of the Work Order as per PHED-MIS
|
work_name
Name of the Work as per the Issued Work Order
|
Bill Gross Amount | Voucher Number | Voucher Date | System Voucher Number |
---|---|---|---|---|---|---|---|---|---|---|---|---|
0 | 18,123.99 | |||||||||||
1 | Coochbehar Division | BILL/00008/2024-2025 | 09/05/2024 | NO 1 GURIAHATI CO OP LABOUR CONTRACT AND CONSTRUCT SOCY LTD | ORD/000363/2023-2024 | 1394/CD | 05/12/2023 | Execution of different works related to SITALKUCHI Z2 PWSS under JAL JEEVAN MISSION | 12.95 | BP-14 | 15/05/2024 | VCH/000008/2024-2025 |
2 | Coochbehar Division | BILL/00018/2023-2024 | 16/08/2023 | SUSHANTA SAHA | ORD/000060/2021-2022 | 264/CD | 06/08/2021 | Pipe Line in the Command area incl. Providing House connection at CHARALJANI PWSS under Cooch Behar Division. PHE Dte. PART - B | 19.16 | wr-110 | 25/10/2024 | VCH/001867/2023-2024 |
3 | Coochbehar Division | BILL/00044/2024-2025 | 16/05/2024 | M/S. DUTTA AND CO | ORD/000096/2023-2024 | 631/CD | 12/07/2023 | Execution of different works related to PESTARJHAR Zone - II & III PWSS under JAL JEEVAN MISSION | 130.39 | BP-20 | 20/05/2024 | VCH/000010/2024-2025 |
4 | Coochbehar Division | BILL/00050/2024-2025 | 16/05/2024 | M/S. NITYAGOPAL BANIK | ORD/000108/2023-2024 | 661/CD | 14/07/2023 | Execution of different works related to SHIKARPUR PIPED WATER SUPPLY SCHEME. | 122.10 | BP-36 | 29/05/2024 | VCH/000019/2024-2025 |
5 | Coochbehar Division | BILL/00055/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000525/2023-2024 | 362/CD | 22/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Cooch Behar-I, Augmentation of Naharhat Bandar Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-44 | 29/05/2024 | VCH/000046/2024-2025 |
6 | Coochbehar Division | BILL/00111/2024-2025 | 11/06/2024 | PALLAB BHAWAL | ORD/000422/2021-2022 | 1520/CD | 15/03/2022 | Constructions of 250 Cum OHR as per Departmental Design & drawing, Providing F.H.T.C New laying of UPVC/DI Pipe Line & other allied work at BANESWAR Zone-II PWSS under Cooch Behar Division , P.H.E Dte. (PART-A) | 26.56 | BP-93 | 15/06/2024 | VCH/000034/2024-2025 |
7 | Coochbehar Division | BILL/00122/2024-2025 | 13/06/2024 | LIMRA SOCIAL WELFARE SOCIETY | ORD/000582/2023-2024 | 599/CD | 11/03/2024 | Designing, Making & erecting of DB using logo tagline for Cooch Behar districts under Jal Jeevan Mission (JJM) Support Activities Part E | 25.91 | BP-99 | 20/06/2024 | VCH/000085/2024-2025 |
8 | Coochbehar Division | BILL/00206/2024-2025 | 01/07/2024 | HARIDAS GHOSH | ORD/000463/2022-2023 | 1514/CD | 19/01/2023 | Execution of different works related to KOCHABARI PWSS under JAL JEEVAN MISSION SE NBC1/PHED A. O.: 983/1-5/NBC-1; DT: 19-01-23 | 72.63 | BP-147 | 15/07/2024 | VCH/000144/2024-2025 |
9 | Coochbehar Division | BILL/00209/2024-2025 | 01/07/2024 | SHRI ANNAPURNA DISTRIBUTORS | ORD/000485/2023-2024 | 287/CD | 09/02/2024 | Execution of different works related to PRAN MAJUMDER PWSS under JAL JEEVAN MISSION PART C | 23.48 | BP-159 | 15/07/2024 | VCH/000102/2024-2025 |
10 | Coochbehar Division | BILL/00218/2024-2025 | 08/07/2024 | SHRI ANNAPURNA DISTRIBUTORS | ORD/000519/2022-2023 | 1606/CD | 03/02/2023 | Execution of different works related to PURBA DHULIA BALDIHATI PWSS under JAL JEEVAN MISSION | 46.94 | BP-164 | 15/07/2024 | VCH/000176/2024-2025 |
11 | Coochbehar Division | BILL/00226/2023-2024 | 30/06/2023 | MS SSB CONSTRUCTION CO | ORD/000592/2022-2023 | 1672/CD | 13/02/2023 | Execution of different works related to KHARIJA DURGANAGAR DWITIA KHANDA PWSS under JAL JEEVAN MISSION | 1.99 | wr-110 | 25/10/2024 | VCH/001857/2023-2024 |
12 | Coochbehar Division | BILL/00291/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000328/2024-2025 | 846/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Cooch Behar-II, DUDDER KUTHIDEWANBAS PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-268 | 09/08/2024 | VCH/000137/2024-2025 |
13 | Coochbehar Division | BILL/00295/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000333/2024-2025 | 851/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Sitai, UTTAR SINGIMARI PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-280 | 14/08/2024 | VCH/000262/2024-2025 |
14 | Coochbehar Division | BILL/00296/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000337/2024-2025 | 855/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Mekhliganj, UTTAR SINGIMARI PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-275 | 14/08/2024 | VCH/000258/2024-2025 |
15 | Coochbehar Division | BILL/00300/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000338/2024-2025 | 856/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Haldibari, UTTAR SINGIMARI PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-274 | 14/08/2024 | VCH/000257/2024-2025 |
16 | Coochbehar Division | BILL/00305/2024-2025 | 08/08/2024 | SWAPAN KR.SARKAR | ORD/000095/2023-2024 | 630/CD | 12/07/2023 | Execution of different works related to PESTARJHAR Zone - I PWSS under JAL JEEVAN MISSION | 112.95 | BP-283 | 14/08/2024 | VCH/000264/2024-2025 |
17 | Coochbehar Division | BILL/00307/2024-2025 | 08/08/2024 | M/S KAMAK ENGINEERS AND CO | ORD/000551/2022-2023 | 1787/CD | 02/03/2023 | Execution of different works related to UNISH BASA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1235/1-5/NBC-1; Dt.: 02-03-23 | 116.56 | BP-285 | 14/08/2024 | VCH/000266/2024-2025 |
18 | Coochbehar Division | BILL/00391/2024-2025 | 31/08/2024 | M/S. MANDAL CONSTRUCTION | ORD/000006/2023-2024 | 50/CD | 17/04/2023 | Execution of different works related to Aug of BALABHUT PWSS under JAL JEEVAN MISSION | 0.24 | BP-347 | 04/09/2024 | VCH/000322/2024-2025 |
19 | Coochbehar Division | BILL/00451/2024-2025 | 03/09/2024 | MS SSB CONSTRUCTION CO | ORD/000110/2023-2024 | 663/CD | 14/07/2023 | Execution of different works related to BARA ATIABARI PRATHAM KHANDA PWSS under JAL JEEVAN MISSION | 91.99 | BP-357 | 10/09/2024 | VCH/000327/2024-2025 |
20 | Coochbehar Division | BILL/00455/2024-2025 | 04/09/2024 | S & P ENTERPRISE | ORD/000089/2023-2024 | 624/CD | 12/07/2023 | Execution of different works related to DUDHER KUTHIDEWANBAS Z2 PWSS under JAL JEEVAN MISSION | 99.00 | BP-372 | 11/09/2024 | VCH/000354/2024-2025 |
21 | Coochbehar Division | BILL/00462/2024-2025 | 06/09/2024 | AKBAR ALI | ORD/000139/2023-2024 | 808/CD | 08/08/2023 | Execution of different works related to FALIMARI (ZONE-II) PWSS under JAL JEEVAN MISSION | 112.68 | BP-391 | 20/09/2024 | VCH/000332/2024-2025 |
22 | Coochbehar Division | BILL/00466/2024-2025 | 11/09/2024 | M/S A. B. ENTERPRISE | ORD/000050/2024-2025 | 1265/CD | 02/07/2024 | Execution of different works related to KHARIKABARI PWSS under JAL JEEVAN MISSION PART D1 | 24.05 | BP-380 | 20/09/2024 | VCH/000361/2024-2025 |
23 | Coochbehar Division | BILL/01006/2023-2024 | 28/11/2023 | NABIN DEBNATH | ORD/000458/2022-2023 | 1509/CD | 19/01/2023 | Execution of different works related to PUTIMARI BAKSIBAS PWSS under JAL JEEVAN MISSIONSE NBC1/PHED A. O.: 978/1-5/NBC-1; DT: 19-01-23 | 30.77 | wr-110 | 25/10/2024 | VCH/001991/2023-2024 |
24 | Coochbehar Division | BILL/01294/2023-2024 | 23/01/2024 | JAL PRAVAHIKA PRIVATE LIMITED | ORD/000580/2022-2023 | 1770/CD | 02/03/2023 | Execution of different works related to MAHISHCHARU PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1207/1-5/NBC-1; Dt.: 01-03-23 | 1.10 | w 2155 | 25/10/2024 | VCH/001840/2023-2024 |
25 | Coochbehar Division | BILL/01297/2023-2024 | 23/01/2024 | M/S KAMAK ENGINEERS AND CO | ORD/000596/2022-2023 | 1788/CD | 02/03/2023 | Execution of different works related to JORPATKI PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1233/1-5/NBC-1; Dt.: 02-03-23 | 1.20 | wr-110 | 25/10/2024 | VCH/001855/2023-2024 |
26 | Coochbehar Division | BILL/01299/2023-2024 | 23/01/2024 | Z STAR COMMOTRADE PVT LTD | ORD/000557/2022-2023 | 1782/CD | 02/03/2023 | Execution of different works related to GHOKSADANGA ZONE - II PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1243/1-5/NBC-1; Dt.: 02-03-23 | 70.00 | 1999W | 25/10/2024 | VCH/001812/2023-2024 |
27 | Coochbehar Division | BILL/01336/2023-2024 | 25/01/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000104/2023-2024 | 718/CD | 25/07/2023 | Execution of different works related to AUG. of JAIGIR CHILAKHANA PWSS under JAL JEEVAN MISSION | 212.62 | r 2155 | 25/10/2024 | VCH/001850/2023-2024 |
28 | Coochbehar Division | BILL/01948/2023-2024 | 30/03/2024 | SHIBA ENTERPRISE | ORD/000346/2023-2024 | 1330/CD | 24/11/2023 | Execution of different works related to CHHOTO SAKDAL ADJACENT TO SATKURA PWSS PWSS under JAL JEEVAN MISSION | 23.33 | BP-5 | 03/05/2024 | VCH/001819/2023-2024 |
29 | Coochbehar Division | BILL/01951/2023-2024 | 30/03/2024 | ELECTRO SERVICES PVT.LTD | null | GEMC-511687783724294 | 18/03/2024 | supply CANON TONER TONER NPG 59 CANAON INK 050 CMYBK | 0.91 | BP-8 | 06/05/2024 | VCH/001821/2023-2024 |
30 | Coochbehar Division | BILL/01954/2023-2024 | 30/03/2024 | SSPR VALVE MANUFACTURING PVT. LTD. | ORD/000017/2023-2024 | 391/CD | 23/05/2023 | Execution of different works related to ANDARAN FULBARI (phulbari P A ) PWSS under JAL JEEVAN MISSION PART Y | 32.73 | BP-1 | 03/05/2024 | VCH/001822/2023-2024 |
31 | Coochbehar Division | BILL/00084/2024-2025 | 04/06/2024 | GOUTAM KUMAR DAS | ORD/000547/2023-2024 | 604/CD | 11/03/2024 | Laying DI P/Line & other allied works related to BAROKODALI Z 2 PWSS under JAL JEEVAN MISSION | 26.15 | BP-63 | 10/06/2024 | VCH/000173/2024-2025 |
32 | Coochbehar Division | BILL/00088/2024-2025 | 04/06/2024 | MS SSB CONSTRUCTION CO | ORD/000514/2023-2024 | 312/CD | 09/02/2024 | Execution of different works related to BHUTKURA PWSS under JAL JEEVAN MISSION | 44.37 | BP-65 | 10/06/2024 | VCH/000183/2024-2025 |
33 | Coochbehar Division | BILL/00106/2024-2025 | 07/06/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000545/2022-2023 | 1785/CD | 02/03/2023 | Execution of different works related to KSHETI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1240/1-5/NBC-1; Dt.: 02-03-23 | 75.53 | BP-81 | 12/06/2024 | VCH/000192/2024-2025 |
34 | Coochbehar Division | BILL/00159/2024-2025 | 18/06/2024 | SUBHAS CHANDRA ROY | ORD/000576/2023-2024 | 666/CD | 11/03/2024 | Laying DI P/Line & other allied works related to GHUGHUMARI PWSS under JAL JEEVAN MISSION | 5.56 | BP-112 | 25/06/2024 | VCH/000066/2024-2025 |
35 | Coochbehar Division | BILL/00176/2024-2025 | 22/06/2024 | BIJOY ROY | ORD/000164/2023-2024 | 941/CD | 04/09/2023 | Execution of different works related to JIRANPUR PWSS under JAL JEEVAN MISSION | 0.11 | BP-123 | 28/06/2024 | VCH/000079/2024-2025 |
36 | Coochbehar Division | BILL/00244/2024-2025 | 19/07/2024 | SWAPAN KUMAR ROY | ORD/000486/2022-2023 | 1551/CD | 24/01/2023 | Execution of different works related to BRAHMOTTAR KASAL DANGA Z1 PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 999/1-5/NBC-1; Dt.: 24-01-23 | 121.57 | BP-196 | 29/07/2024 | VCH/000165/2024-2025 |
37 | Coochbehar Division | BILL/00252/2024-2025 | 31/07/2024 | M/S. NITYAGOPAL BANIK | ORD/000622/2022-2023 | 1873/CD | 14/03/2023 | Execution of different works related to UPENCHAUKIKUCHLIBARI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1128/1-5/NBC-1; Dt.: 13-02-23 | 106.58 | BP-237 | 06/08/2024 | VCH/000230/2024-2025 |
38 | Coochbehar Division | BILL/00255/2024-2025 | 01/08/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000348/2023-2024 | 1332/CD | 24/11/2023 | Execution of different works related to KHARI ANALDHANDRA PWSS under JAL JEEVAN MISSION | 4.57 | BP-242 | 07/08/2024 | VCH/000236/2024-2025 |
39 | Coochbehar Division | BILL/00256/2024-2025 | 01/08/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000347/2023-2024 | 1331/CD | 24/11/2023 | Execution of different works related to KAMINIRGHAT PWSS under JAL JEEVAN MISSION | 3.30 | BP-243 | 07/08/2024 | VCH/000237/2024-2025 |
40 | Coochbehar Division | BILL/00276/2024-2025 | 02/08/2024 | S.G ENTERPRISE | ORD/000484/2022-2023 | 1549/CD | 24/01/2023 | Execution of different works related to KHARIJA BALADANGA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1002/1-5/NBC-1; Dt.: 24-01-23 | 37.33 | BP-254 | 09/08/2024 | VCH/000246/2024-2025 |
41 | Coochbehar Division | BILL/00416/2023-2024 | 18/08/2023 | MATARA CONSTRUCTION CO. | ORD/000269/2021-2022 | 948/CD | 31/12/2021 | Providing FHTC Pump House SSPost & New UPVC Pipe line and other allied works (PART ¿B) at RAKHALMARI PWSS under Cooch Behar Division, PHED | 13.41 | r 1588 | 25/10/2024 | VCH/001837/2023-2024 |
42 | Coochbehar Division | BILL/00442/2024-2025 | 03/09/2024 | SUBHAS CHANDRA ROY | ORD/000340/2023-2024 | 1397/CD | 05/12/2023 | Execution of different works related to KURSHAMARI PWSS under JAL JEEVAN MISSION | 26.76 | BP-358 | 10/09/2024 | VCH/000328/2024-2025 |
43 | Coochbehar Division | BILL/00320/2024-2025 | 13/08/2024 | MALAY KR.DEB | ORD/000427/2021-2022 | 1523/CD | 15/03/2022 | Providing FHTC, Constructions 3.6 m x 3.0 m switch room & Boundary wall, Street stand post along with soakpit, New laying of UPVC/DI Pipe Line & Other allied works at Baneswar Zone-III PWSS under Cooch Behar Division, P.H.E Dte. (Part-B) | 15.12 | BP-295 | 21/08/2024 | VCH/000275/2024-2025 |
44 | Coochbehar Division | BILL/00329/2024-2025 | 14/08/2024 | MS BIDYUT SARKAR | ORD/000146/2023-2024 | 860/CD | 22/08/2023 | Execution of different works related to BHORAM PWSS under JAL JEEVAN MISSION | 110.24 | BP-298 | 21/08/2024 | VCH/000120/2024-2025 |
45 | Coochbehar Division | BILL/00361/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE Najirhat trimohini adjacent KISMAT MOKRABARI road VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR, | 22.13 | BP-317 | 31/08/2024 | VCH/000129/2024-2025 |
46 | Coochbehar Division | BILL/00577/2024-2025 | 14/09/2024 | SUBHAS CHANDRA ROY | ORD/000518/2023-2024 | 316/CD | 09/02/2024 | Execution of different works related to AUG of GURIAHATI PWSS under JAL JEEVAN MISSION | 10.85 | BP-400 | 20/09/2024 | VCH/000348/2024-2025 |
47 | Coochbehar Division | BILL/00603/2024-2025 | 16/09/2024 | HIRAK CONSTRUCTION | ORD/000602/2023-2024 | 646/CD | 11/03/2024 | Execution of different works related to KHAGRIBARI PWSS under JAL JEEVAN MISSION | 44.23 | BP-393 | 20/09/2024 | VCH/000358/2024-2025 |
48 | Coochbehar Division | BILL/00785/2024-2025 | 23/09/2024 | MS BIDYUT SARKAR | ORD/000021/2024-2025 | 1129/CD | 14/06/2024 | Execution of different works related to BAISGURI KHANDA PWSS under JAL JEEVAN MISSION | 85.91 | BP-422 | 26/09/2024 | VCH/000386/2024-2025 |
49 | Coochbehar Division | BILL/00787/2024-2025 | 24/09/2024 | MS TM CONSTRUCTION | ORD/000111/2023-2024 | 664/CD | 14/07/2023 | Execution of different works related to GURIAHATI(NM) (ZONE- III) PWSS under JAL JEEVAN MISSION | 144.15 | BP-426 | 27/09/2024 | VCH/000390/2024-2025 |
50 | Coochbehar Division | BILL/00912/2023-2024 | 16/10/2023 | M/S TORSHA CONSTRUCTION | ORD/000587/2022-2023 | 1677/CD | 13/02/2023 | Execution of different works related to NIJTARAF PWSS under JAL JEEVAN MISSION | 12.00 | wr-110 | 25/10/2024 | VCH/001835/2023-2024 |
51 | Coochbehar Division | BILL/00962/2024-2025 | 04/10/2024 | SRI SAYAN SAHA | null | PHE/2270/0-49/2021(PT-I) | 29/08/2024 | Remuneration of Sri SAYAN SAHA AE contractual under cooch behar division,PHED. | 0.30 | W R 12222 | 05/11/2024 | VCH/000399/2024-2025 |
52 | Coochbehar Division | BILL/00797/2024-2025 | 25/09/2024 | BRAJA GOPAL SAHA | ORD/000140/2023-2024 | 806/CD | 08/08/2023 | Execution of different works related to BARA MADHUSUDAN PWSS under JAL JEEVAN MISSION | 79.57 | BP-434 | 27/09/2024 | VCH/000396/2024-2025 |
53 | Coochbehar Division | BILL/00816/2023-2024 | 09/10/2023 | GOUTAM KUMAR DAS | ORD/000172/2023-2024 | 949/CD | 04/09/2023 | Execution of different works related to BALARAMPUR PWSS under JAL JEEVAN MISSION | 8.96 | wr entry | 25/10/2024 | VCH/001848/2023-2024 |
54 | Coochbehar Division | BILL/00837/2024-2025 | 28/09/2024 | PARITOSH KR.CHOUDHARY | ORD/000793/2022-2023 | 1869/CD | 14/03/2023 | Execution of different works related to BANESWAR Z1 PWSS under JAL JEEVAN MISSION | 5.09 | wr entry | 15/11/2024 | VCH/000430/2024-2025 |
55 | Coochbehar Division | BILL/00017/2024-2025 | 09/05/2024 | UMEX POLYMERS PVT LTD | ORD/000515/2022-2023 | 1602/CD | 03/02/2023 | Execution of different works related to INDRA NARAYAN PWSS under JAL JEEVAN MISSION | 15.01 | BP-73 | 07/06/2024 | VCH/000210/2024-2025 |
56 | Coochbehar Division | BILL/00060/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000535/2023-2024 | 373/CD | 27/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Sitalkuchi, Dinhata(P) Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-47 | 29/05/2024 | VCH/000049/2024-2025 |
57 | Coochbehar Division | BILL/00061/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000536/2023-2024 | 374/CD | 27/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Mathabhanga-I, Augmentation of Naharhat Bandar Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-40 | 29/05/2024 | VCH/000042/2024-2025 |
58 | Coochbehar Division | BILL/00064/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000543/2023-2024 | 377/CD | 27/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Haldibari, Dinhata(P) Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-45 | 29/05/2024 | VCH/000047/2024-2025 |
59 | Coochbehar Division | BILL/00113/2024-2025 | 11/06/2024 | ASHIM KUMAR CHAKRABORTY | ORD/000041/2023-2024 | 436/CD | 31/05/2023 | Execution of different works related to BARAIBARI PWSS under JAL JEEVAN MISSION | 163.75 | BP-90 | 15/06/2024 | VCH/000097/2024-2025 |
60 | Coochbehar Division | BILL/00122/2023-2024 | 12/05/2023 | GOUTAM KUMAR DAS | ORD/000217/2022-2023 | 706/CD | 27/08/2022 | Constructions of 250 Cum OHR as per Departmental Design & drawing , Providing F.H.T.C ,New laying DI Pipe Line & other allied work at CHHAT RAMPUR PWSS under JAL JEEVAN MISSION (PART ¿D) | 3.90 | R 21455 | 25/10/2024 | VCH/001851/2023-2024 |
61 | Coochbehar Division | BILL/00126/2024-2025 | 14/06/2024 | M/S B PAUL AND COMPANY | ORD/000627/2022-2023 | 1961/CD | 24/03/2023 | Execution of different works related to SHALBARI ZONE 1 PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1334/1-5/NBC-1; Dt.: 24-03-23 | 100.42 | BP-166 | 11/07/2024 | VCH/000148/2024-2025 |
62 | Coochbehar Division | BILL/00142/2023-2024 | 19/05/2023 | DAS TRADING CO | ORD/000037/2022-2023 | 95/CD | 18/04/2022 | Providing FHTC Construction of B/Wall & New Laying of Pipe Line and other allied works at AUG. PAYAMARI PWSS under Cooch Behar Division, PHED PART - A | 1.83 | BP-70 | 07/06/2024 | VCH/001985/2023-2024 |
63 | Coochbehar Division | BILL/00205/2024-2025 | 01/07/2024 | HARIDAS GHOSH | ORD/000138/2023-2024 | 807/CD | 08/08/2023 | Execution of different works related to FALIMARI (ZONE-I) PWSS under JAL JEEVAN MISSION | 72.29 | BP-148 | 15/07/2024 | VCH/000145/2024-2025 |
64 | Coochbehar Division | BILL/00219/2024-2025 | 08/07/2024 | BABA LOKENATH UN EMPLOYED ENGINEERS CO OP SOCIETY LTD | ORD/000487/2022-2023 | 1552/CD | 24/01/2023 | Execution of different works related to HASTABUD KASALDANGA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1003/1-5/NBC-1; Dt.: 24-01-23 | 72.42 | BP-173 | 15/07/2024 | VCH/000153/2024-2025 |
65 | Coochbehar Division | BILL/00221/2024-2025 | 08/07/2024 | MATRI ENTERPRISEES | ORD/000442/2021-2022 | 1434/CD | 10/03/2022 | Providing FHTC, Constructions 3.6 m x 3.0 m switch room & Boundary wall, Street stand post along with soakpit , New laying of UPVC/DI Pipe Line & Other allied works at Baneswar Zone-II (Part-B) PWSS under Cooch Behar Division, P.H.E Dte. | 3.58 | BP-172 | 15/07/2024 | VCH/000106/2024-2025 |
66 | Coochbehar Division | BILL/00222/2024-2025 | 08/07/2024 | KRISHNA GOPAL BASK | ORD/000786/2022-2023 | 1862/CD | 14/03/2023 | Execution of different works related to BANESWAR Z2 PWSS under JAL JEEVAN MISSION | 19.88 | BP-169 | 15/07/2024 | VCH/000105/2024-2025 |
67 | Coochbehar Division | BILL/00233/2024-2025 | 12/07/2024 | UTTAM SAHA | ORD/000268/2023-2024 | 1034/cd | 22/09/2023 | Name of Work: Execution of different works related to CHHAT RAMPUR PWSS under JAL JEEVAN MISSION PART A | 7.03 | BP-180 | 17/07/2024 | VCH/000083/2024-2025 |
68 | Coochbehar Division | BILL/00280/2024-2025 | 02/08/2024 | SWAPAN KR.SARKAR | ORD/000010/2023-2024 | 395/CD | 23/05/2023 | Execution of different works related to Aug. of CHAKCHAKA ZONE - II PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 163/1-5/NBC-1; Dt.: 18-05-23 | 110.26 | BP-261 | 09/08/2024 | VCH/000216/2024-2025 |
69 | Coochbehar Division | BILL/00286/2022-2023 | 16/02/2023 | RADIANT | ORD/000169/2022-2023 | 628/CD | 16/08/2022 | Preparation of DPR for Augmentation of HEMKUMARI (Zone-II) Piped Water Supply Scheme under MATHABHANGA Sub-Division of Cooch Behar Division,P.H.E.Dte. | 3.02 | W 5666 | 25/10/2024 | VCH/001734/2022-2023 |
70 | Coochbehar Division | BILL/00286/2024-2025 | 03/08/2024 | DILIP MAHATO | ORD/000039/2024-2025 | 1147/CD | 14/06/2024 | Execution of different works related to BAILPARI PWSS under JAL JEEVAN MISSION | 96.76 | BP-270 | 09/08/2024 | VCH/000256/2024-2025 |
71 | Coochbehar Division | BILL/00299/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000331/2024-2025 | 849/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Dinhata-I, DUDDER KUTHIDEWANBAS PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-279 | 14/08/2024 | VCH/000138/2024-2025 |
72 | Coochbehar Division | BILL/00304/2024-2025 | 08/08/2024 | M/S PALIT ENTERPRISE | ORD/000516/2023-2024 | 314/CD | 09/02/2024 | Execution of different works related to KUCHLIBARI Z-I PWSS under JAL JEEVAN MISSION | 26.53 | BP-322 | 03/09/2024 | VCH/000345/2024-2025 |
73 | Coochbehar Division | BILL/00377/2024-2025 | 21/08/2024 | M/S MAA MANASA CONSTRUCTION CO. | ORD/000572/2023-2024 | 614/CD | 11/03/2024 | Execution of different works related to CHANDAMARI AREA PHALIMARI PWSS under JAL JEEVAN MISSION | 9.65 | BP-429 | 27/09/2024 | VCH/000330/2024-2025 |
74 | Coochbehar Division | BILL/00379/2024-2025 | 21/08/2024 | M/S BADAL CH SAHA | ORD/000158/2023-2024 | 888/CD | 25/08/2023 | Execution of different works related to ANDARAN KUCHLIBARI PWSS under JAL JEEVAN MISSION | 37.98 | BP-325 | 03/09/2024 | VCH/000311/2024-2025 |
75 | Coochbehar Division | BILL/00453/2024-2025 | 04/09/2024 | MS SSB CONSTRUCTION CO | ORD/000059/2024-2025 | 1298/CD | 11/07/2024 | Execution of different works related to BARARANGRAS PWSS under JAL JEEVAN MISSION | 84.78 | BP-371 | 11/09/2024 | VCH/000335/2024-2025 |
76 | Coochbehar Division | BILL/00454/2024-2025 | 04/09/2024 | M/S DHAR ENTERPRISE | ORD/000120/2023-2024 | 636/CD | 12/07/2023 | Execution of different works related to TUPAMARI DEWANBAS PWSS under JAL JEEVAN MISSION | 55.74 | BP-377 | 10/09/2024 | VCH/000371/2024-2025 |
77 | Coochbehar Division | BILL/00458/2024-2025 | 06/09/2024 | M/S TORSHA CONSTRUCTION | ORD/000162/2023-2024 | 893/CD | 31/08/2023 | Execution of different works related to KUCHNI PRATHAM KHANDA PWSS under JAL JEEVAN MISSION | 71.01 | BP-410 | 26/09/2024 | VCH/000378/2024-2025 |
78 | Coochbehar Division | BILL/00467/2024-2025 | 11/09/2024 | MS SSB CONSTRUCTION CO | ORD/000060/2024-2025 | 1309/CD | 16/07/2024 | Execution of different works related to TUTIARKUTHI PWSS under JAL JEEVAN MISSION | 84.01 | BP-379 | 20/09/2024 | VCH/000347/2024-2025 |
79 | Coochbehar Division | BILL/00470/2024-2025 | 11/09/2024 | ANIMESH DHAR CHOUDHURY | ORD/000488/2022-2023 | 1553/CD | 24/01/2023 | Execution of different works related to AUG. of BASKOTAL PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1018/1-5/NBC-1; Dt.: 24-01-23 | 51.80 | BP-395 | 20/09/2024 | VCH/000374/2024-2025 |
80 | Coochbehar Division | BILL/01334/2023-2024 | 25/01/2024 | GOUTAM KUMAR DAS | ORD/000528/2021-2022 | 1628/CD | 29/03/2022 | Providing FHTC Works, Laying of pipe line Constructions of 3rd site Pump House, Boundary Wall at PANISALA W.S.S under Cooch Behar Division P.H.E.Dte. | 2.89 | wr 12345 | 25/10/2024 | VCH/001999/2023-2024 |
81 | Coochbehar Division | BILL/01517/2023-2024 | 23/02/2024 | SWAPAN SAHA | ORD/000451/2022-2023 | 1427/CD | 29/12/2022 | Execution of different works related to GHUGHUMARI PWSS under JAL JEEVAN MISSION | 5.55 | wr entry | 25/10/2024 | VCH/001849/2023-2024 |
82 | Coochbehar Division | BILL/01950/2023-2024 | 30/03/2024 | ELECTRO SERVICES PVT.LTD | null | GEMC-511687701221992 | 04/03/2024 | CANON COPIER 2925 AQND 2224N MID END PRINTER TONAR | 2.96 | BP-7 | 06/05/2024 | VCH/001820/2023-2024 |
83 | Coochbehar Division | BILL/00068/2024-2025 | 28/05/2024 | PALLAB BHAWAL | ORD/000489/2022-2023 | 1554/CD | 24/01/2023 | Execution of different works related to UCHALPUKURI ZONE -I PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1017/1-5/NBC-1; Dt.: 24-01-23 | 148.19 | BP-51 | 04/06/2024 | VCH/000178/2024-2025 |
84 | Coochbehar Division | BILL/00069/2024-2025 | 28/05/2024 | PALLAB BHAWAL | ORD/000572/2022-2023 | 1690/CD | 13/02/2023 | Execution of different works related to UCHALPUKURI ZONE - II PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1121/1-5/NBC-1; Dt.: 13-02-23 | 163.47 | BP-50 | 04/06/2024 | VCH/000177/2024-2025 |
85 | Coochbehar Division | BILL/00076/2024-2025 | 30/05/2024 | SWAPAN KUMAR ROY | ORD/000461/2022-2023 | 1512/CD | 19/01/2023 | Execution of different works related to BRAHMOTTAR KASAL DANGA Z2 PWSS under JAL JEEVAN MISSIONSE NBC1/PHED A. O.: 981/1-5/NBC-1; DT: 19-01-23 | 114.09 | BP-60 | 07/06/2024 | VCH/000072/2024-2025 |
86 | Coochbehar Division | BILL/00161/2024-2025 | 19/06/2024 | GOUTAM KUMAR DAS | ORD/000544/2023-2024 | 638/CD | 11/03/2024 | Execution of different works related to GABUA PWSS under JAL JEEVAN MISSION | 49.13 | bp-109 | 25/06/2024 | VCH/000199/2024-2025 |
87 | Coochbehar Division | BILL/00168/2024-2025 | 21/06/2024 | LONGLAST PIPES (INDIA) PVT. LTD. | ORD/000498/2021-2022 | 1446/CD | 10/03/2022 | Sinking of 250mm x 200 mm Big dia. Tube well with UPVC Pipes & Strainer at 3rd Site ofSATBHANDARI PWSS under Cooch Behar Division PHE Dte. | 10.61 | BP-126 | 28/06/2024 | VCH/000203/2024-2025 |
88 | Coochbehar Division | BILL/00181/2024-2025 | 22/06/2024 | SHREE RANI SATI ENTERPRISE | ORD/000634/2022-2023 | 1995/CD | 28/03/2023 | Execution of different works related to AUG. of Bherbheri PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1365/1-5/NBC-1; Dt.: 28-03-23 | 2.21 | BP-165 | 11/07/2024 | VCH/000084/2024-2025 |
89 | Coochbehar Division | BILL/00184/2023-2024 | 31/05/2023 | WBSEDCL | null | SM/MTBCCC254 | 30/05/2023 | SHIFTING OF EXISTING 25 KVA DTR | 4.66 | R 555555 | 25/10/2024 | VCH/001833/2023-2024 |
90 | Coochbehar Division | BILL/00192/2024-2025 | 26/06/2024 | LIMRA SOCIAL WELFARE SOCIETY | ORD/000581/2023-2024 | 621/CD | 11/03/2024 | Designing, Making & erecting of DB using logo tagline for Cooch Behar districts under Jal Jeevan Mission (JJM) Support Activities Part D | 25.83 | BP-130 | 02/07/2024 | VCH/000131/2024-2025 |
91 | Coochbehar Division | BILL/00251/2024-2025 | 25/07/2024 | GEETA CONSTRUCTION | ORD/000476/2023-2024 | 278/CD | 09/02/2024 | Execution of different works related to RUIERKUTHI PWSS under JAL JEEVAN MISSION | 17.75 | BP-201 | 31/07/2024 | VCH/000170/2024-2025 |
92 | Coochbehar Division | BILL/00266/2024-2025 | 01/08/2024 | M/S A. B. ENTERPRISE | ORD/000055/2024-2025 | 1269/CD | 02/07/2024 | Execution of different works related to AUG. SOULMARI PWSS under JAL JEEVAN MISSION | 39.05 | BP-238 | 07/08/2024 | VCH/000231/2024-2025 |
93 | Coochbehar Division | BILL/00270/2024-2025 | 02/08/2024 | UMEX POLYMERS PVT LTD | ORD/000518/2022-2023 | 1605/CD | 03/02/2023 | Execution of different works related to DAKSHIN KHARIJA GITALDAHA PWSS under JAL JEEVAN MISSION | 66.28 | BP-264 | 09/08/2024 | VCH/000252/2024-2025 |
94 | Coochbehar Division | BILL/00273/2024-2025 | 02/08/2024 | DILIP MAHATO | ORD/000594/2022-2023 | 1964/CD | 24/03/2023 | Execution of different works related to BAILPARI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1338/1-5/NBC-1; Dt.: 24-03-23 | 70.08 | BP-269 | 09/08/2024 | VCH/000255/2024-2025 |
95 | Coochbehar Division | BILL/00440/2024-2025 | 03/09/2024 | GOUTAM KUMAR DAS | ORD/000035/2024-2025 | 1144/CD | 14/06/2024 | Execution of different works related to KISMAT MOKARARI PWSS under JAL JEEVAN MISSION | 50.78 | BP-365 | 10/09/2024 | VCH/000338/2024-2025 |
96 | Coochbehar Division | BILL/00336/2024-2025 | 30/08/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000430/2021-2022 | 1526/CD | 15/03/2022 | Providing FHTC, Sinking of big dia tube well( 250 mm X 200 mm), Construction of pump house, boundary wall, Repairing of boundary wall at head work site and laying of UPVC pipe line and other allied works at in-connection with augmentation NALANGIBARI P | 6.69 | BP-342 | 04/09/2024 | VCH/000320/2024-2025 |
97 | Coochbehar Division | BILL/00352/2023-2024 | 03/08/2023 | MS BIDYUT SARKAR | ORD/000552/2022-2023 | 1774/CD | 02/03/2023 | Execution of different works related to BAISGURI KHANDA PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1242/1-5/NBC-1; Dt.: 02-03-23 | 39.28 | R C1255 | 25/10/2024 | VCH/001852/2023-2024 |
98 | Coochbehar Division | BILL/00360/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDEOKRABARI Gobrachara Road road adjacent lonkabar VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR, (1) LANKABAR P | 10.13 | BP-303 | 31/08/2024 | VCH/000281/2024-2025 |
99 | Coochbehar Division | BILL/00363/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE BALARAMPUR road ADJACENT TO BOSKOTAL VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR, | 23.22 | BP-314 | 31/08/2024 | VCH/000232/2024-2025 |
100 | Coochbehar Division | BILL/00606/2024-2025 | 16/09/2024 | M/S SURAJIT MAJUMDER | ORD/000511/2023-2024 | 308/CD | 09/02/2024 | Execution of different works related to (SALMARA PKHANDA area) KHARIKABARI PWSS under JAL JEEVAN MISSION | 1.74 | BP-397 | 20/09/2024 | VCH/000362/2024-2025 |
101 | Coochbehar Division | BILL/00607/2024-2025 | 16/09/2024 | SWAPAN KUMAR ROY | ORD/000623/2022-2023 | 1691/CD | 13/02/2023 | Execution of different works related to SOULMARI Z 1 PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1129/1-5/NBC-1; Dt.: 13-02-23 | 110.31 | BP-403 | 26/09/2024 | VCH/000377/2024-2025 |
102 | Coochbehar Division | BILL/00608/2024-2025 | 18/09/2024 | M/S. DUTTA AND CO | ORD/000459/2022-2023 | 1510/CD | 19/01/2023 | Execution of different works related to BHANGRI PRATHAM KHANDA PWSS under JAL JEEVAN MISSION SE NBC1/PHED A. O.: 979/1-5/NBC-1; DT: 19-01-23 | 49.12 | BP-414 | 26/09/2024 | VCH/000379/2024-2025 |
103 | Coochbehar Division | BILL/00512/2022-2023 | 27/03/2023 | GHOSH AND SAHA CONSTRUCTION | ORD/000457/2022-2023 | 1508/CD | 19/01/2023 | Execution of different works related to NAHARHATBANDAR PWSS under JAL JEEVAN MISSIONSE NBC1/PHED A. O.: 977/1-5/NBC-1; DT: 19-01-23 | 160.00 | wr-110 | 25/10/2024 | VCH/001730/2022-2023 |
104 | Coochbehar Division | BILL/00522/2022-2023 | 27/03/2023 | GHOSH AND SAHA CONSTRUCTION | ORD/000430/2021-2022 | 1526/CD | 15/03/2022 | Providing FHTC, Sinking of big dia tube well( 250 mm X 200 mm), Construction of pump house, boundary wall, Repairing of boundary wall at head work site and laying of UPVC pipe line and other allied works at in-connection with augmentation NALANGIBARI P | 33.00 | wr-110 | 25/10/2024 | VCH/001727/2022-2023 |
105 | Coochbehar Division | BILL/00793/2024-2025 | 25/09/2024 | GOUTAM KUMAR DAS | ORD/000591/2022-2023 | 1673/CD | 13/02/2023 | Execution of different works related to DEBGRAM PWSS under JAL JEEVAN MISSION | 55.84 | BP-431 | 27/09/2024 | VCH/000393/2024-2025 |
106 | Coochbehar Division | BILL/00796/2024-2025 | 25/09/2024 | BILTU DAS | ORD/000052/2024-2025 | 1270/CD | 02/07/2024 | Execution of different works related to KHAGRABARI PWSS under JAL JEEVAN MISSION Z3 | 36.59 | BP-435 | 30/09/2024 | VCH/000397/2024-2025 |
107 | Coochbehar Division | BILL/00010/2024-2025 | 09/05/2024 | LONGLAST PIPES (INDIA) PVT. LTD. | ORD/000389/2022-2023 | 1034/CD | 29/09/2022 | Sinking of Big Dia Tubewell at GHOSKADANGA PWSS under JAL JEEVAN MISSION (Z-I: 3rd Site Z-II: HWS & 2ndSite) | 23.33 | BP-10 | 15/05/2024 | VCH/000002/2024-2025 |
108 | Coochbehar Division | BILL/00018/2024-2025 | 09/05/2024 | M/S KARNATAKA CONSTRUCTION COMPANY | ORD/000524/2022-2023 | 1679/CD | 13/02/2023 | Execution of different works related to CHHOTA KESHARI BARI PWSS under JAL JEEVAN MISSION | 74.47 | BP-161 | 11/07/2024 | VCH/000175/2024-2025 |
109 | Coochbehar Division | BILL/00022/2024-2025 | 09/05/2024 | SHREE RANI SATI ENTERPRISE | ORD/000660/2022-2023 | 1989/CD | 28/03/2023 | Execution of different works related to BARAI BARI, PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1369/1-5/NBC-1; Dt.: 28-03-23 | 11.44 | BP-27 | 29/05/2024 | VCH/000027/2024-2025 |
110 | Coochbehar Division | BILL/00037/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000533/2023-2024 | 367/CD | 22/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Dinhata-II Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-22 | 29/06/2024 | VCH/000022/2024-2025 |
111 | Coochbehar Division | BILL/00044/2023-2024 | 24/04/2023 | S AND P ENTERPRISE | ORD/000420/2021-2022 | 1518/CD | 15/03/2022 | Construction of 450 cum OHR Providing FHTC & New UPVC Pipe line & other allied works (PART ¿A) at SITAI ZONE ¿ I I PWSS under Cooch Behar Division, PHED | 149.54 | W15000 | 25/10/2024 | VCH/001826/2023-2024 |
112 | Coochbehar Division | BILL/00056/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000526/2023-2024 | 363/CD | 22/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Cooch Behar-II, Augmentation of Naharhat Bandar Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-43 | 29/05/2024 | VCH/000045/2024-2025 |
113 | Coochbehar Division | BILL/00062/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000538/2023-2024 | 375/CD | 27/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Mathabhanga-II, Augmentation of Naharhat Bandar Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-39 | 29/05/2024 | VCH/000041/2024-2025 |
114 | Coochbehar Division | BILL/00063/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000540/2023-2024 | 376/CD | 27/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Mekhliganj, Dinhata(P) Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-46 | 29/05/2024 | VCH/000048/2024-2025 |
115 | Coochbehar Division | BILL/00142/2024-2025 | 16/06/2024 | TAPAN CHANDA | ORD/000520/2021-2022 | 1568/CD | 23/03/2022 | Supply and delivery of 200 mm dia UPVC pipe(CD) for Balarampur Zone-II 3rd Site Tubewell under Cooch Behar Division , P.H.E Dte. | 2.98 | BP-115 | 25/06/2024 | VCH/000108/2024-2025 |
116 | Coochbehar Division | BILL/00195/2024-2025 | 27/06/2024 | KARTICK CH SEAL | ORD/000443/2021-2022 | 1435/CD | 10/03/2022 | Laying of raising main & delivery line connection , Constructions of Head works site Pump & Boundary walland Other allied works at Baneswar Zone-III PWSS under Cooch Behar Division, P.H.E Dte. | 4.60 | BP-144 | 02/07/2024 | VCH/000064/2024-2025 |
117 | Coochbehar Division | BILL/00203/2024-2025 | 01/07/2024 | M/S SURAJIT MAJUMDER | ORD/000492/2023-2024 | 294/CD | 09/02/2024 | Execution of different works related to (Kismat Bhatrigachhi area) CHHOTO BOALMARI PWSS under JAL JEEVAN MISSION | 1.36 | BP-151 | 15/07/2024 | VCH/000100/2024-2025 |
118 | Coochbehar Division | BILL/00208/2024-2025 | 01/07/2024 | NABIN DEBNATH | ORD/000621/2022-2023 | 1875/CD | 14/03/2023 | Execution of different works related to AUG. of BAJEJAMA CHILAKHANA ZONE-II PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1175/1-5/NBC-1; Dt.: 24-02-23 | 39.36 | BP-162 | 15/07/2024 | VCH/000147/2024-2025 |
119 | Coochbehar Division | BILL/00210/2024-2025 | 01/07/2024 | M/S JAYANTA KUMAR GOPE | ORD/000086/2023-2024 | 621/CD | 12/07/2023 | Execution of different works related to KHATERBARTI PWSS under JAL JEEVAN MISSION | 53.29 | BP-155 | 15/07/2024 | VCH/000125/2024-2025 |
120 | Coochbehar Division | BILL/00297/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000335/2024-2025 | 853/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Mathabhanga-I, UTTAR SINGIMARI PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-277 | 14/08/2024 | VCH/000260/2024-2025 |
121 | Coochbehar Division | BILL/00301/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000336/2024-2025 | 854/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Mathabhanga-II, UTTAR SINGIMARI PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-276 | 14/08/2024 | VCH/000259/2024-2025 |
122 | Coochbehar Division | BILL/00394/2024-2025 | 31/08/2024 | GOUTAM KUMAR DAS | ORD/000529/2021-2022 | 1629/CD | 29/03/2022 | Providing FHTC Works, Laying of pipe line Constructions of 3rd site Pump House, Boundary Wall at BHANDIJALAS W.S.S under Cooch Behar Division P.H.E.Dte. | 2.79 | BP-348 | 04/09/2024 | VCH/000323/2024-2025 |
123 | Coochbehar Division | BILL/00459/2024-2025 | 06/09/2024 | GOUTAM KUMAR DAS | ORD/000264/2023-2024 | 1032/CD | 22/09/2023 | Name of Work: Execution of different works related to Aug. of BAROKODALI PWSS under JAL JEEVAN MISSION | 29.69 | BP-384 | 20/09/2024 | VCH/000343/2024-2025 |
124 | Coochbehar Division | BILL/00468/2024-2025 | 11/09/2024 | MA MAHAMAYA UNP.CO-OP LABOUR CONTRACT AND CONST SOCIETY LTD. | ORD/000439/2022-2023 | 1416/CD | 29/12/2022 | Execution of different works related to SHIKARPUR P2 PWSS under JAL JEEVAN MISSION | 1.81 | BP-382 | 20/09/2024 | VCH/000372/2024-2025 |
125 | Coochbehar Division | BILL/00481/2023-2024 | 28/08/2023 | SUCHITRO FUEL STATION | null | 446 | 01/05/2023 | supply of fuel for the month of may 2023 | 0.41 | R 45888 | 25/10/2024 | VCH/001853/2023-2024 |
126 | Coochbehar Division | BILL/00694/2024-2025 | 21/09/2024 | SWAPAN KUMAR ROY | ORD/000524/2023-2024 | 322/CD | 09/02/2024 | Execution of different works related to BRAHMOTTAR KASALDANGA Z-I PWSS under JAL JEEVAN MISSION | 35.56 | BP-412 | 26/09/2024 | VCH/000359/2024-2025 |
127 | Coochbehar Division | BILL/00881/2024-2025 | 02/10/2024 | MACKINTOSH BURN LIMITED | ORD/000339/2024-2025 | 1264/CD | 02/07/2024 | Laying of DI line along both the flanks of Roads in Cooch Behar District(PHALIMARI,SHALBARI,Mansai,SIKARPUR,SAJHERPARGHORAMARA,Nandina,Garbhadanga,BHORAM,FALIMARI,DAKSHINBOKNABANDHA,BHOGRAMGURI,BHERBHERIMANABARI,KHATERBARI,NENDARPAR,NAKARJAN,CHHOTO BOALMA | 1,950.29 | wr-110 | 14/11/2024 | VCH/000420/2024-2025 |
128 | Coochbehar Division | BILL/01301/2023-2024 | 23/01/2024 | SHREE RANI SATI ENTERPRISE | ORD/000657/2022-2023 | 1988/CD | 28/03/2023 | Execution of different works related to PHULBARI PART-A PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1366/1-5/NBC-1; Dt.: 28-03-23 | 50.00 | wr-110 | 04/10/2024 | VCH/002000/2023-2024 |
129 | Coochbehar Division | BILL/00065/2024-2025 | 24/05/2024 | NABIN DEBNATH | ORD/000621/2022-2023 | 1875/CD | 14/03/2023 | Execution of different works related to AUG. of BAJEJAMA CHILAKHANA ZONE-II PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1175/1-5/NBC-1; Dt.: 24-02-23 | 48.91 | BP-49 | 04/06/2024 | VCH/000013/2024-2025 |
130 | Coochbehar Division | BILL/00071/2024-2025 | 28/05/2024 | NORTH BENGAL CONSTRUCTION CO | ORD/000279/2023-2024 | 1047/CD | 22/09/2023 | Name of Work: Execution of different works related to Aug. of SITAI PWSS under JAL JEEVAN MISSION PART N | 7.39 | BP-66 | 07/06/2024 | VCH/000029/2024-2025 |
131 | Coochbehar Division | BILL/00072/2024-2025 | 19/04/2024 | MATARA CONSTRUCTION CO. | ORD/000639/2022-2023 | 2016/CD | 30/03/2023 | Execution of different works related to AUG. of GOPALPUR PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1368/1-5/NBC-1; Dt.: 28-03-23 | 81.53 | BP-52 | 04/06/2024 | VCH/000179/2024-2025 |
132 | Coochbehar Division | BILL/00085/2024-2025 | 04/06/2024 | SIDHARTHA ROY | ORD/000479/2023-2024 | 282/CD | 09/02/2024 | Execution of different works related to CHAKIARCHHARA PWSS under JAL JEEVAN MISSION | 21.13 | BP-56 | 10/06/2024 | VCH/000017/2024-2025 |
133 | Coochbehar Division | BILL/00089/2024-2025 | 04/06/2024 | UTTAM SAHA | ORD/000779/2023-2024 | 660/CD | 11/03/2024 | Execution of different works related to Andaran Fulbari area under Tanapakha PWSS under JAL JEEVAN MISSION Z1 | 2.92 | BP-55 | 10/06/2024 | VCH/000073/2024-2025 |
134 | Coochbehar Division | BILL/00092/2024-2025 | 04/06/2024 | GOUTAM KUMAR DAS | ORD/000542/2023-2024 | 631/CD | 11/03/2024 | Execution of different works related to BAROKODALI Z 1 PWSS under JAL JEEVAN MISSION | 55.95 | BP-57 | 10/06/2024 | VCH/000172/2024-2025 |
135 | Coochbehar Division | BILL/00093/2024-2025 | 06/06/2024 | S & P ENTERPRISE | ORD/000091/2023-2024 | 626/CD | 12/07/2023 | Execution of different works related to CHHOTO BOALMARI z1 PWSS under JAL JEEVAN MISSION | 135.98 | BP-77 | 12/06/2024 | VCH/000021/2024-2025 |
136 | Coochbehar Division | BILL/00095/2024-2025 | 06/06/2024 | PARTHA DAS | ORD/000141/2023-2024 | 809/CD | 08/08/2023 | Execution of different works related to SARHATI PWSS under JAL JEEVAN MISSION | 102.54 | BP-75 | 12/06/2024 | VCH/000188/2024-2025 |
137 | Coochbehar Division | BILL/00102/2024-2025 | 07/06/2024 | TORSHA CONSTRUCTION | ORD/000776/2023-2024 | 659/CD | 11/03/2024 | Construction of 500 cum OHR and Laying distrbution System and other allied works Gajendrapur Chowrangee Piped Water Supply Scheme at Haldibari Block for DistrictCoochbehar under Coochbehar Division of North Bengal Circle-I,PHE Dte. | 127.36 | BP-82 | 12/06/2024 | VCH/000023/2024-2025 |
138 | Coochbehar Division | BILL/00103/2024-2025 | 07/06/2024 | SANKAR CHAKRABORTY | ORD/000422/2023-2024 | 1478/CD | 20/12/2023 | Execution of different works related to DAKSHIN DIGHALTARI PWSS under JAL JEEVAN MISSION | 52.84 | BP-85 | 12/06/2024 | VCH/000063/2024-2025 |
139 | Coochbehar Division | BILL/00158/2024-2025 | 18/06/2024 | M/S TORSHA CONSTRUCTION | ORD/000604/2022-2023 | 1854/CD | 14/03/2023 | Execution of different works related to GAJENDRAPUR CHOWRANGEE PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1116/1-5/NBC-1; Dt.: 13-02-23 | 64.52 | BP-113 | 25/06/2024 | VCH/000200/2024-2025 |
140 | Coochbehar Division | BILL/00185/2024-2025 | 24/06/2024 | UTTAM SAHA | ORD/000268/2023-2024 | 1034/cd | 22/09/2023 | Name of Work: Execution of different works related to CHHAT RAMPUR PWSS under JAL JEEVAN MISSION PART A | 7.53 | BP-135 | 01/07/2024 | VCH/000075/2024-2025 |
141 | Coochbehar Division | BILL/00193/2024-2025 | 26/06/2024 | MS DD ENTERPRISE | ORD/000794/2022-2023 | 1870/CD | 14/03/2023 | Execution of different works related to BANESWAR Z1 PWSS under JAL JEEVAN MISSION | 12.36 | BP-134 | 01/07/2024 | VCH/000065/2024-2025 |
142 | Coochbehar Division | BILL/00242/2024-2025 | 19/07/2024 | BIJOY ROY | ORD/000553/2023-2024 | 602/CD | 11/03/2024 | Execution of different works related to JIRANPUR PWSS under JAL JEEVAN MISSION | 43.41 | BP-194 | 29/07/2024 | VCH/000164/2024-2025 |
143 | Coochbehar Division | BILL/00247/2024-2025 | 24/07/2024 | MS DD ENTERPRISE | ORD/000523/2023-2024 | 321/cd | 09/02/2024 | Execution of different works related to CHANDAMARI PWSS under JAL JEEVAN MISSION MTB | 45.15 | BP-198 | 29/07/2024 | VCH/000167/2024-2025 |
144 | Coochbehar Division | BILL/00256/2022-2023 | 07/02/2023 | NABIN DEBNATH | ORD/000425/2021-2022 | 1475/CD | 10/03/2022 | Construction of 300 cum OHR Providing FHTC New Pipe line & other allied works (PART ¿A) at ANDARAN FULBARI ZONE-II PWSS under Cooch Behar Division, PHED | 19.90 | w 45666 | 25/10/2024 | VCH/001732/2022-2023 |
145 | Coochbehar Division | BILL/00264/2024-2025 | 01/08/2024 | CHAKRABORTY ENTERPRISE. | ORD/000121/2023-2024 | 637/CD | 12/07/2023 | Execution of different works related to BHURKULDANGA PWSS under JAL JEEVAN MISSION | 50.82 | BP-241 | 07/08/2024 | VCH/000235/2024-2025 |
146 | Coochbehar Division | BILL/00278/2024-2025 | 02/08/2024 | KRISHNA GOPAL BASK | ORD/000771/2022-2023 | 1658/CD | 10/02/2023 | Execution of different works related to NALANGIBARI PWSS under JAL JEEVAN MISSION | 9.07 | BP-341 | 04/09/2024 | VCH/000365/2024-2025 |
147 | Coochbehar Division | BILL/00425/2024-2025 | 01/09/2024 | SUBHAJIT DUTTA | ORD/000444/2022-2023 | 1421/CD | 29/12/2022 | Execution of different works related to KHAGRABARI PWSS under JAL JEEVAN MISSION | 9.07 | BP-362 | 10/09/2024 | VCH/000349/2024-2025 |
148 | Coochbehar Division | BILL/00438/2024-2025 | 03/09/2024 | BIJOY ROY | ORD/000029/2024-2025 | 1138/CD | 14/06/2024 | Execution of different works related to GURIAHATI PWSS under JAL JEEVAN MISSION Z3 | 24.45 | BP-356 | 11/09/2024 | VCH/000254/2024-2025 |
149 | Coochbehar Division | BILL/00318/2024-2025 | 12/08/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000104/2023-2024 | 718/CD | 25/07/2023 | Execution of different works related to AUG. of JAIGIR CHILAKHANA PWSS under JAL JEEVAN MISSION | 140.96 | BP-290 | 21/08/2024 | VCH/000271/2024-2025 |
150 | Coochbehar Division | BILL/00319/2024-2025 | 12/08/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000579/2023-2024 | 619/CD | 11/03/2024 | Execution of different works related to JAIGIR CHILAKHANA PWSS under JAL JEEVAN MISSION | 34.10 | BP-289 | 21/08/2024 | VCH/000270/2024-2025 |
151 | Coochbehar Division | BILL/00338/2024-2025 | 17/08/2024 | ASHIM KUMAR CHAKRABORTY | ORD/000013/2022-2023 | 29/CD | 07/04/2022 | Providing FHTC, Construction of pump house, Boundary wall and laying of Pipe line and other allied works at inconnection with augmentation of NIJTARAF PWSS under Cooch Behar Division, PHED. (Part-A) | 0.70 | BP-336 | 03/09/2024 | VCH/000229/2024-2025 |
152 | Coochbehar Division | BILL/00339/2023-2024 | 31/07/2023 | GOUTAM KUMAR DAS | ORD/000779/2022-2023 | 1695/CD | 13/02/2023 | Execution of different works related to SITALKUCHI Z2 PWSS under JAL JEEVAN MISSION | 6.69 | C 1200 | 25/10/2024 | VCH/001810/2023-2024 |
153 | Coochbehar Division | BILL/00346/2024-2025 | 17/08/2024 | TAPAN CHANDA | ORD/000018/2023-2024 | 369/CD | 23/05/2023 | Balance portion Pipe line, Rising & Delivery line & other allied work related to pipe line at RAMPUR ZONE I & II WSSunder Tufanganj Sub- Division, Cooch Behar Divn., P.H.E Dte. Under JJM Programme. | 70.72 | BP-331 | 03/09/2024 | VCH/000315/2024-2025 |
154 | Coochbehar Division | BILL/00349/2024-2025 | 17/08/2024 | NARESH CH.MANDAL | ORD/000442/2022-2023 | 1419/CD | 29/12/2022 | Execution of different works related to DEBOTTAR BAKSHIGANJ PWSS under JAL JEEVAN MISSION | 4.08 | BP-353 | 04/09/2024 | VCH/000325/2024-2025 |
155 | Coochbehar Division | BILL/00780/2024-2025 | 23/09/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000471/2023-2024 | 273/CD | 09/02/2024 | Execution of different works related to KHARI ANALDHONDRA PWSS under JAL JEEVAN MISSION | 66.64 | BP-418 | 26/09/2024 | VCH/000385/2024-2025 |
156 | Coochbehar Division | BILL/00792/2024-2025 | 25/09/2024 | SEKHAR GHOSAL | ORD/000414/2022-2023 | 1225/CD | 28/11/2022 | Providing FHTC & other allied works at BALARAMPUR ZONE - II PWSS under JAL JEEVAN MISSION | 3.80 | BP-432 | 27/09/2024 | VCH/000394/2024-2025 |
157 | Coochbehar Division | BILL/01103/2023-2024 | 13/12/2023 | SWAPAN KR.SARKAR | ORD/000835/2022-2023 | 1617/CD/B | 03/02/2023 | Training for improvement of Skillness of Pump Operator & Valve Operator of different PWSS of Cooch Behar-II Block held at khagrabari under Cooch Behar Division, PHED. | 0.40 | wr-110 | 25/10/2024 | VCH/001866/2023-2024 |
158 | Coochbehar Division | BILL/00005/2024-2025 | 09/05/2024 | SHREE RANI SATI ENTERPRISE | ORD/000034/2023-2024 | 371/CD | 23/05/2023 | New Laying of Balance Pipe line, Providing FHTC Construction TW, PH, BW & Other allied work related to pipe lineat MARADANGA WSS under Tufanganj Sub- Division, Cooch Behar Divn., P.H.E Dte. Under JJM Programme. Part B | 10.93 | BP-17 | 15/05/2024 | VCH/000009/2024-2025 |
159 | Coochbehar Division | BILL/00013/2024-2025 | 09/05/2024 | Z STAR COMMOTRADE PVT LTD | ORD/000582/2022-2023 | 1772/CD | 02/03/2023 | Execution of different works related to SITALKUCHI ZONE - I PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1213/1-5/NBC-1; Dt.: 01-03-23 | 48.41 | BP-13 | 15/05/2024 | VCH/000004/2024-2025 |
160 | Coochbehar Division | BILL/00019/2024-2025 | 09/05/2024 | UMEX POLYMERS PVT LTD | ORD/000013/2023-2024 | 398/CD | 23/05/2023 | Execution of different works related to GABUA PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 160/1-5/NBC-1; Dt.: 18-05-23 | 40.84 | BP-29 | 29/05/2024 | VCH/000012/2024-2025 |
161 | Coochbehar Division | BILL/00025/2024-2025 | 09/05/2024 | UMEX POLYMERS PVT LTD | ORD/000606/2022-2023 | 1900/CD | 17/03/2023 | Execution of different works related to BARA MARICHA PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1293/1-5/NBC-1; Dt.: 17-03-23 | 22.31 | BP-30 | 29/05/2024 | VCH/000032/2024-2025 |
162 | Coochbehar Division | BILL/00029/2024-2025 | 09/05/2024 | ASHIT KUMAR SINGHA | ORD/000583/2022-2023 | 1773/CD | 02/03/2023 | Execution of different works related to ASAKBARI PRATHAM KHANDA PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1241/1-5/NBC-1; Dt.: 02-03-23 | 71.16 | BP-9 | 15/05/2024 | VCH/000006/2024-2025 |
163 | Coochbehar Division | BILL/00046/2024-2025 | 17/05/2024 | M/S VINOD KUMAR JAIN | ORD/000520/2022-2023 | 1607/CD | 03/02/2023 | Execution of different works related to ATPUKURI PWSS under JAL JEEVAN MISSION | 80.54 | BP-25 | 29/05/2024 | VCH/000026/2024-2025 |
164 | Coochbehar Division | BILL/00116/2024-2025 | 13/06/2024 | KAJAL KUMAR DE | ORD/000546/2022-2023 | 1680/CD | 13/02/2023 | Execution of different works related to CHAKIARCHHARA (RUNIBARI) PWSS under JAL JEEVANMISSION | 38.52 | BP-97 | 14/06/2024 | VCH/000053/2024-2025 |
165 | Coochbehar Division | BILL/00123/2024-2025 | 13/06/2024 | LIMRA SOCIAL WELFARE SOCIETY | ORD/000583/2023-2024 | 622/CD | 11/03/2024 | Designing, Making & erecting of DB using logo tagline for Cooch Behar districts under Jal Jeevan Mission (JJM) Support Activities Part F | 10.39 | BP-98 | 20/06/2024 | VCH/000030/2024-2025 |
166 | Coochbehar Division | BILL/00127/2024-2025 | 14/06/2024 | M/S B PAUL AND COMPANY | ORD/000625/2022-2023 | 1962/CD | 24/03/2023 | Execution of different works related to SHALBARI ZONE 2 PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1344/1-5/NBC-1; Dt.: 24-03-23 | 140.11 | BP-167 | 11/07/2024 | VCH/000150/2024-2025 |
167 | Coochbehar Division | BILL/00133/2024-2025 | 15/06/2024 | LIMRA SOCIAL WELFARE SOCIETY | ORD/000586/2023-2024 | 623/CD | 11/03/2024 | Designing, Making & erecting of DB using logo tagline for Cooch Behar districts under Jal Jeevan Mission (JJM) Support Activities Part H | 26.03 | BP-111 | 25/06/2024 | VCH/000080/2024-2025 |
168 | Coochbehar Division | BILL/00138/2024-2025 | 15/06/2024 | ASHIT KUMAR GHOSH | ORD/000472/2022-2023 | 1527/CD | 20/01/2023 | PROVIDING FHTC LAYING OF PIPE LINE AT KALARAYER KUTHE (ZONE-I) PWSS under JAL JEEVAN MISSION (PART ¿C) | 5.05 | BP-105 | 25/06/2024 | VCH/000060/2024-2025 |
169 | Coochbehar Division | BILL/00281/2024-2025 | 02/08/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000107/2023-2024 | 660/CD | 14/07/2023 | Execution of different works related to PATCHHARA ZONE 1 PWSS under JAL JEEVAN MISSION | 119.17 | BP-257 | 09/08/2024 | VCH/000249/2024-2025 |
170 | Coochbehar Division | BILL/00298/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000334/2024-2025 | 852/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Sitalkuchi, UTTAR SINGIMARI PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-278 | 14/08/2024 | VCH/000261/2024-2025 |
171 | Coochbehar Division | BILL/00312/2023-2024 | 25/07/2023 | BENGAL YOUTH UN EMPLOYED ENGINEERS CO | ORD/000588/2022-2023 | 1676/CD | 13/02/2023 | Execution of different works related to SAJHERPAR KHATALBARI PWSS under JAL JEEVAN MISSION | 73.48 | 1200W | 25/10/2024 | VCH/001814/2023-2024 |
172 | Coochbehar Division | BILL/00312/2024-2025 | 10/08/2024 | SSPR VALVE MANUFACTURING PVT. LTD. | ORD/000555/2023-2024 | 648/CD | 11/03/2024 | Execution of different works related to B.CHILAKHANA 1 PWSS under JAL JEEVAN MISSION | 25.60 | BP-302 | 21/08/2024 | VCH/000280/2024-2025 |
173 | Coochbehar Division | BILL/00366/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE ATIABARI FAKIRTAKIA road ADJACENT TO PASCHIM MOYAMARI VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHA | 10.31 | BP-315 | 31/08/2024 | VCH/000290/2024-2025 |
174 | Coochbehar Division | BILL/00367/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE DINHATA GITALDHA ADJACENT TO KISMAT MOKRABARI road VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR, | 12.05 | BP-319 | 31/08/2024 | VCH/000128/2024-2025 |
175 | Coochbehar Division | BILL/00368/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE DHAPRAMORE TO DHAPRAHAT BAZAR ADJACENT TO PASHIM MOAMARI road VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR, | 4.20 | BP-316 | 31/08/2024 | VCH/000291/2024-2025 |
176 | Coochbehar Division | BILL/00371/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1471 | 06/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDESHIBPUR BAWRAH ADJACENT HEMKUMARI road VR ( IN stretches FROM 0.00 KM TO 8.00 KM UNDER MATHABHANGA SUB DIVISION UNDER PWD Cooch Behar division DURING YEAR 2024-2025 | 10.62 | BP-309 | 31/08/2024 | VCH/000286/2024-2025 |
177 | Coochbehar Division | BILL/00380/2024-2025 | 21/08/2024 | S N POLYMERS PVT LTD | ORD/000684/2022-2023 | 1615/CD | 03/02/2023 | Execution of different works related to CHILKIRHAT PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1175/1-5/NBC-1; Dt.: 24-02-23 | 56.10 | BP-324 | 03/09/2024 | VCH/000310/2024-2025 |
178 | Coochbehar Division | BILL/00384/2024-2025 | 21/08/2024 | M/S MAA MANASA CONSTRUCTION CO. | ORD/000546/2023-2024 | 650/CD | 11/03/2024 | Gap filling between pipe line related to Bhogdabri & M DIGHALHATI PWSS under JAL JEEVAN MISSION | 17.44 | BP-335 | 03/09/2024 | VCH/000317/2024-2025 |
179 | Coochbehar Division | BILL/00389/2024-2025 | 31/08/2024 | M/S A. B. ENTERPRISE | ORD/000163/2023-2024 | 940/CD | 04/09/2023 | Execution of different works at Dewanhat Sub District Water Testing Laboratory related to Dewanhat PWSS under JAL JEEVAN MISSION. | 19.88 | BP-345 | 04/09/2024 | VCH/000321/2024-2025 |
180 | Coochbehar Division | BILL/00392/2024-2025 | 31/08/2024 | SHREE RANI SATI ENTERPRISE | ORD/000263/2021-2022 | 933/CD | 31/12/2021 | Providing FHTC & New laying UPVC/DI GI Pipe line construction of Sluice valve chamber & other alliedworks at NATABARI PWSS under Cooch Behar Division, PHED (PART ¿B) | 7.30 | BP-344 | 04/09/2024 | VCH/000334/2024-2025 |
181 | Coochbehar Division | BILL/00460/2024-2025 | 06/09/2024 | SUDIPTA BOSE | ORD/000137/2023-2024 | 805/CD | 08/08/2023 | Execution of different works related to MOAMARI PWSS under JAL JEEVAN MISSION | 58.56 | BP-421 | 26/09/2024 | VCH/000342/2024-2025 |
182 | Coochbehar Division | BILL/00473/2023-2024 | 26/08/2023 | MAHENDRA CHHETRI | ORD/000553/2022-2023 | 1610/CD | 03/02/2023 | Execution of different works related to CHAUDANGA PWSS under JAL JEEVAN MISSION | 5.73 | c 122355 | 21/11/2024 | VCH/002003/2023-2024 |
183 | Coochbehar Division | BILL/00486/2022-2023 | 24/03/2023 | RAJAT ROY | ORD/000505/2022-2023 | 1233/CD | 28/11/2022 | Providing FHTC Laying of Pipe Line & other allied works at SITALKUCHI ZONE III PWSS under JAL JEEVAN MISSION | 7.90 | wr-110 | 25/10/2024 | VCH/001735/2022-2023 |
184 | Coochbehar Division | BILL/00644/2023-2024 | 22/09/2023 | DAS ENTERPRISE | ORD/000555/2022-2023 | 1702/CD | 13/02/2023 | Execution of different works related to DEBOTTAR BAKSHIGANJ PWSS under JAL JEEVAN MISSION | 35.11 | w 12555 | 25/10/2024 | VCH/001864/2023-2024 |
185 | Coochbehar Division | BILL/00696/2023-2024 | 25/09/2023 | NABIN DEBNATH | ORD/000225/2021-2022 | 758/CD | 03/12/2021 | Construction of Pillar & other allied works for supporting of DI Pipeline at BILSI PWSS under Cooch Behar Division. PHE Dte. | 4.61 | BP-352 | 04/09/2024 | VCH/002002/2023-2024 |
186 | Coochbehar Division | BILL/01200/2023-2024 | 30/12/2023 | GHOSH AND SAHA CONSTRUCTION | ORD/000431/2021-2022 | 1515/CD | 15/03/2022 | Constructions of 350 OHR as per Departmental Design & drawing , New laying of UPVC/DI Pipe Line(PART-A) , Providing F.H.T.C & other allied work at Kaminirghat PWSS under Cooch Behar Division , P.H.E Dte. | 45.00 | wr-110 | 25/10/2024 | VCH/001856/2023-2024 |
187 | Coochbehar Division | BILL/01947/2023-2024 | 30/03/2024 | ASHIT KUMAR SINGHA | ORD/000473/2023-2024 | 275/CD | 09/02/2024 | Execution of different works related to DAKSHIN ALOKJHARI PWSS under JAL JEEVAN MISSION | 50.74 | BP-329 | 03/09/2024 | VCH/001994/2023-2024 |
188 | Coochbehar Division | BILL/00075/2024-2025 | 30/05/2024 | JAINCO TRADERS | ORD/000277/2023-2024 | 1045/CD | 22/09/2023 | Execution of different works related to Aug. of SITAI PWSS under JAL JEEVAN MISSION PART-Y | 0.45 | BP-61 | 07/06/2024 | VCH/000028/2024-2025 |
189 | Coochbehar Division | BILL/00083/2024-2025 | 31/05/2024 | MANABENDRA DE | ORD/000408/2021-2022 | 1466/CD | 10/03/2022 | Shifting of Pipe line incl River Crossing with suppurting RSJ pile at Kangratoli immigr. Rd. at PURBAFULKADABRI PWSS under Cooch Behar Division, PHED | 3.56 | BP-68 | 07/06/2024 | VCH/000185/2024-2025 |
190 | Coochbehar Division | BILL/00098/2024-2025 | 07/06/2024 | UNIBRO INFRASERV PRIVATE LIMITED | ORD/000671/2022-2023 | 1884/CD | 14/03/2023 | Execution of different works related to HEMKUMARI ZONE 3 PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1106/1-5/NBC-1; Dt.: 13-02-23 | 110.57 | BP-78 | 12/06/2024 | VCH/000190/2024-2025 |
191 | Coochbehar Division | BILL/00100/2024-2025 | 07/06/2024 | HARIDAS GHOSH | ORD/000174/2023-2024 | 951/CD | 04/09/2023 | Execution of different works related to B. CHILAKHANA PWSS under JAL JEEVAN MISSION | 23.53 | BP-84 | 12/06/2024 | VCH/000058/2024-2025 |
192 | Coochbehar Division | BILL/00167/2024-2025 | 21/06/2024 | SWAPAN KUMAR ROY | ORD/000497/2022-2023 | 1562/CD | 24/01/2023 | Execution of different works related to SOULMARI Z 2 PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1009/1-5/NBC-1; Dt.: 24-01-23 | 204.28 | BP-132 | 01/07/2024 | VCH/000088/2024-2025 |
193 | Coochbehar Division | BILL/00169/2024-2025 | 21/06/2024 | ASHIM KUMAR CHAKRABORTY | ORD/000420/2022-2023 | 1278/CD | 02/12/2022 | Providing FHTC & other allied works at DHALPAL PWSS under JAL JEEVAN MISSION | 26.34 | BP-120 | 28/06/2024 | VCH/000202/2024-2025 |
194 | Coochbehar Division | BILL/00183/2024-2025 | 24/06/2024 | MS BIDYUT SARKAR | ORD/000240/2022-2023 | 726/CD | 27/08/2022 | Providing FHTC & Construction of Pump house at HW site & 2nd Site GOSANIMARI ZONE ¿ I PWSS under JAL JEEVAN MISSION | 4.73 | BP-142 | 01/07/2024 | VCH/000071/2024-2025 |
195 | Coochbehar Division | BILL/00184/2024-2025 | 24/06/2024 | GEETA CONSTRUCTION | ORD/000731/2022-2023 | 1739/CD | 21/02/2023 | Providing FHTC & Construction of pump house, Boundary wall (HW site) and laying of Pipe line other allied works at ATPUKURI ZONE - II PWSS Under Cooch Behar division P.H.E.Dte.(Part-B) | 21.94 | BP-137 | 01/07/2024 | VCH/000077/2024-2025 |
196 | Coochbehar Division | BILL/00191/2024-2025 | 26/06/2024 | SIDHARTHA ROY | ORD/000456/2022-2023 | 1507/CD | 19/01/2023 | Execution of different works related to CHAKIARCHHARA PWSS under JAL JEEVAN MISSION SE NBC1/PHED A. O.: 975/1-5/NBC-1; DT: 19-01-23 | 65.15 | BP-133 | 01/07/2024 | VCH/000119/2024-2025 |
197 | Coochbehar Division | BILL/00234/2024-2025 | 16/07/2024 | MS SSB CONSTRUCTION CO | ORD/000114/2023-2024 | 667/CD | 14/07/2023 | Execution of different works related to DUDHERKUTHI PWSS under JAL JEEVAN MISSION | 115.95 | BP-190 | 25/07/2024 | VCH/000162/2024-2025 |
198 | Coochbehar Division | BILL/00237/2024-2025 | 16/07/2024 | SWAPAN KUMAR ROY | ORD/000489/2023-2024 | 291/CD | 09/02/2024 | Execution of different works related to BHOGMARA PWSS under JAL JEEVAN MISSION | 43.54 | BP-189 | 25/07/2024 | VCH/000161/2024-2025 |
199 | Coochbehar Division | BILL/00248/2024-2025 | 24/07/2024 | ASHIM KUMAR CHAKRABORTY | ORD/000599/2022-2023 | 1968/CD | 24/03/2023 | Execution of different works related to AMBARI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1341/1-5/NBC-1; Dt.: 24-03-23 | 51.77 | BP-263 | 09/08/2024 | VCH/000251/2024-2025 |
200 | Coochbehar Division | BILL/00249/2024-2025 | 25/07/2024 | SAIMONS CO- OPARATIVE LAB CONT & CONSTN SOCY LTD | ORD/000613/2022-2023 | 1908/CD | 17/03/2023 | Execution of different works related to TATERKUTHI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1292/1-5/NBC-1; Dt.: 17-03-23 | 42.08 | BP-200 | 31/07/2024 | VCH/000169/2024-2025 |
201 | Coochbehar Division | BILL/00260/2024-2025 | 01/08/2024 | MS BIDYUT SARKAR | ORD/000261/2023-2024 | 1029/CD | 22/09/2023 | Name of Work: Execution of different works related to MEGHNARAYANER KUTHI PWSS under JAL JEEVAN MISSION PART O | 74.88 | BP-245 | 07/08/2024 | VCH/000239/2024-2025 |
202 | Coochbehar Division | BILL/00262/2024-2025 | 19/07/2024 | SANKAR BANIK | ORD/000258/2023-2024 | 1023/CD | 22/09/2023 | Name of Work: Execution of different works related to KALARAYERKUTHI PWSS under JAL JEEVAN MISSION | 25.57 | BP-247 | 07/08/2024 | VCH/000207/2024-2025 |
203 | Coochbehar Division | BILL/00417/2023-2024 | 18/08/2023 | S & P ENTERPRISE | ORD/000275/2021-2022 | 954/CD | 31/12/2021 | Construction of 150 cum OHR Providing FHTC Sinking 250mm X 200mm Big dia Tubewell & New UPVC/DI Pipe line & other allied works (PART ¿A) at RAKHALMARI PWSS under Cooch Behar Division, PHED | 38.41 | r 2555 | 25/10/2024 | VCH/001836/2023-2024 |
204 | Coochbehar Division | BILL/00444/2024-2025 | 03/09/2024 | PINAKI SAHA | ORD/000364/2023-2024 | 1393/CD | 05/12/2023 | Execution of different works related to Aug. of KHATERBARI PWSS under JAL JEEVAN MISSION | 27.14 | BP-359 | 10/09/2024 | VCH/000329/2024-2025 |
205 | Coochbehar Division | BILL/00445/2024-2025 | 03/09/2024 | SAIMONS CONTRACT AND CONSTRUCTION CO | ORD/000042/2023-2024 | 403CD | 23/05/2023 | Execution of different works related to CHHOTO GODAIKHORA PWSS under JAL JEEVAN MISSION | 7.98 | BP-376 | 13/09/2024 | VCH/000370/2024-2025 |
206 | Coochbehar Division | BILL/00330/2024-2025 | 14/08/2024 | S & P ENTERPRISE | ORD/000276/2021-2022 | 955/CD | 31/12/2021 | Construction of 250 cum OHR Providing FHTC & New UPVC/DI Pipe line & other allied works (PART ¿A) at PETLA PWSS under Cooch Behar Division, PHED | 21.01 | BP-296 | 21/08/2024 | VCH/000276/2024-2025 |
207 | Coochbehar Division | BILL/00331/2024-2025 | 14/08/2024 | MATARA CONSTRUCTION CO. | ORD/000250/2021-2022 | 899/CD | 24/12/2021 | Construction of 600 cum OHR Providing FHTC & New UPVC Pipe line & other allied works (PART ¿A) atBALARAMPUR ZONE ¿ I PWSS under Cooch Behar Division, PHED | 13.19 | BP-321 | 03/09/2024 | VCH/000217/2024-2025 |
208 | Coochbehar Division | BILL/00358/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE NAJIRHAT DIGHALTARY ADJACENT TO NAJIRGANJ VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR | 4.88 | 306 | 31/08/2024 | VCH/000283/2024-2025 |
209 | Coochbehar Division | BILL/00594/2023-2024 | 05/09/2023 | Z STAR COMMOTRADE PVT LTD | ORD/000492/2022-2023 | 1557/CD | 24/01/2023 | Execution of different works related to SITALKUCHI ZONE -III PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1014/1-5/NBC-1; Dt.: 24-01-23 | 28.95 | wr-110 | 25/10/2024 | VCH/001993/2023-2024 |
210 | Coochbehar Division | BILL/00825/2024-2025 | 27/09/2024 | MATARA CONSTRUCTION CO. | ORD/000639/2022-2023 | 2016/CD | 30/03/2023 | Execution of different works related to AUG. of GOPALPUR PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1368/1-5/NBC-1; Dt.: 28-03-23 | 57.72 | wr 12455 | 12/11/2024 | VCH/000402/2024-2025 |
211 | Coochbehar Division | BILL/01095/2023-2024 | 13/12/2023 | MS BIDYUT SARKAR | ORD/000240/2022-2023 | 726/CD | 27/08/2022 | Providing FHTC & Construction of Pump house at HW site & 2nd Site GOSANIMARI ZONE ¿ I PWSS under JAL JEEVAN MISSION | 3.77 | wr-110 | 25/10/2024 | VCH/001858/2023-2024 |
212 | Coochbehar Division | BILL/00020/2024-2025 | 09/05/2024 | M/S. AMIT KUMAR GUPTA | ORD/000327/2022-2023 | 976/CD | 29/09/2022 | Providing FHTC & Laying of Pipe line of CHAKIAR CHHARA ZONE - II PWSS under JAL JEEVAN MISSION (PART ¿C) | 7.95 | BP-26 | 29/05/2024 | VCH/000011/2024-2025 |
213 | Coochbehar Division | BILL/00027/2024-2025 | 09/05/2024 | M/S KAMAK ENGINEERS AND CO | ORD/000551/2022-2023 | 1787/CD | 02/03/2023 | Execution of different works related to UNISH BASA PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1235/1-5/NBC-1; Dt.: 02-03-23 | 0.89 | BP-38 | 29/05/2024 | VCH/000040/2024-2025 |
214 | Coochbehar Division | BILL/00051/2024-2025 | 22/05/2024 | MS SSB CONSTRUCTION CO | ORD/000578/2023-2024 | 618/CD | 11/03/2024 | Execution of different works related to B.RANGARAS Z2 PWSS under JAL JEEVAN MISSION | 67.34 | BP-34 | 29/05/2024 | VCH/000037/2024-2025 |
215 | Coochbehar Division | BILL/00052/2024-2025 | 22/05/2024 | MS SSB CONSTRUCTION CO | ORD/000549/2023-2024 | 607/CD | 11/03/2024 | Execution of different works related to DUDHERKUTHI Z2 PWSS under JAL JEEVAN MISSION | 41.18 | BP-35 | 29/05/2024 | VCH/000038/2024-2025 |
216 | Coochbehar Division | BILL/00054/2024-2025 | 22/05/2024 | LIMRA SOCIAL WELFARE SOCIETY | ORD/000517/2023-2024 | 315/CD | 09/02/2024 | Wall Painting, Designing, Making & erecting of DB using logo tagline for Cooch Behar districts under Jal Jeevan Mission (JJM) Support Activities Part D | 20.71 | BP-121 | 28/06/2024 | VCH/000104/2024-2025 |
217 | Coochbehar Division | BILL/00057/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000528/2023-2024 | 364/CD | 22/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Tufanganj-I, Augmentation of Naharhat Bandar Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-42 | 29/05/2024 | VCH/000044/2024-2025 |
218 | Coochbehar Division | BILL/00115/2024-2025 | 11/06/2024 | SWAPAN KUMAR ROY | ORD/000503/2023-2024 | 299/CD | 09/02/2024 | Execution of different works related to SOULMARI Z- II PWSS under JAL JEEVAN MISSION DHT | 70.62 | BP-94 | 15/06/2024 | VCH/000052/2024-2025 |
219 | Coochbehar Division | BILL/00131/2024-2025 | 14/06/2024 | MATARA CONSTRUCTION CO. | ORD/000579/2022-2023 | 1769/CD | 02/03/2023 | Execution of different works related to PASCHIM MOAMARI PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1208/1-5/NBC-1; Dt.: 01-03-23 | 110.26 | BP-100 | 20/06/2024 | VCH/000114/2024-2025 |
220 | Coochbehar Division | BILL/00143/2024-2025 | 16/06/2024 | GEETA CONSTRUCTION | ORD/000846/2022-2023 | 1764/A/CD | 01/03/2023 | Temporary Water Supply arrangement at Baneswar PWSS under JJM in the District of Cooch Behar under Cooch Behar Division, PHE Dte. | 0.96 | BP-107 | 25/06/2024 | VCH/000055/2024-2025 |
221 | Coochbehar Division | BILL/00148/2022-2023 | 27/12/2022 | TAPAN CHANDA | ORD/000460/2021-2022 | 1610/CD | 24/03/2022 | Providing FHTC 3rd Site Pump House Boundary Wall SSPost with soakpit Sinking 250mm X 200mm Big dia Tubewell & NewUPVC Pipe line and other allied works (PART ¿A) at GOSANIMARI ZONE ¿ I I PWSS under Cooch Behar Division, PHED | 90.00 | wr-110 | 25/10/2024 | VCH/001724/2022-2023 |
222 | Coochbehar Division | BILL/00211/2024-2025 | 02/07/2024 | GOUTAM KUMAR DAS | ORD/000084/2023-2024 | 619/CD | 12/07/2023 | Execution of different works related to CHHAT RAMPUR PWSS under JAL JEEVAN MISSION | 62.92 | BP-149 | 15/07/2024 | VCH/000082/2024-2025 |
223 | Coochbehar Division | BILL/00212/2024-2025 | 02/07/2024 | SUBHAS CHANDRA ROY | ORD/000290/2023-2024 | 11/CD | 05/04/2023 | Execution of different works related to AUG. of Kurshamari PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 11/1-5/NBC-1; Dt.: 05-04-23 | 70.78 | BP-150 | 15/07/2024 | VCH/000126/2024-2025 |
224 | Coochbehar Division | BILL/00216/2024-2025 | 08/07/2024 | KHOKAN DAS | ORD/000515/2023-2024 | 313/CD | 09/02/2024 | Execution of different works related to MAIDAM PWSS under JAL JEEVAN MISSION | 36.13 | BP-175 | 15/07/2024 | VCH/000154/2024-2025 |
225 | Coochbehar Division | BILL/00225/2024-2025 | 10/07/2024 | KAJAL KUMAR DE | ORD/000575/2022-2023 | 1876/CD | 14/03/2023 | Execution of different works related to BARA PHALIMARI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1114/1-5/NBC-1; Dt.: 13-02-23 | 18.14 | BP-178 | 17/07/2024 | VCH/000155/2024-2025 |
226 | Coochbehar Division | BILL/00232/2024-2025 | 12/07/2024 | SANJAY MANDAL | ORD/000480/2023-2024 | 283/CD | 09/02/2024 | Execution of different works related to (with in B Chilakhana Z1) DEOCHARAI PWSS under JAL JEEVAN MISSION | 3.45 | BP-185 | 17/07/2024 | VCH/000098/2024-2025 |
227 | Coochbehar Division | BILL/00282/2024-2025 | 02/08/2024 | SENGUPTA ENTERPRISE | ORD/000619/2023-2024 | 677/CD | 11/03/2024 | Uploading charges of (https://ejalshakti.gov.in/imisreports/IMISReportLogin.aspx) related to FHTC under Jal Jeevan Mission in presence of JJM Login authority under Cooch Behar Division, PHE Dte. (Part-D) Under CHANDAN CHOWRA PIPED WATER SUPPLY SCHEME. | 0.97 | BP-253 | 09/08/2024 | VCH/000245/2024-2025 |
228 | Coochbehar Division | BILL/00287/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000327/2024-2025 | 845/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Cooch Behar-I, DUDDER KUTHIDEWANBAS PIPED WATER SUPPLY SCHEME. under Cooch Behar Division, PHED. | 0.98 | BP-262 | 09/08/2024 | VCH/000136/2024-2025 |
229 | Coochbehar Division | BILL/00376/2024-2025 | 20/08/2024 | WBSEDCL | null | SM/MTB/115 | 13/05/2024 | LT PLE SHTING AND ALLIED WORKS | 0.22 | BP-320 | 31/08/2024 | VCH/000292/2024-2025 |
230 | Coochbehar Division | BILL/00386/2024-2025 | 29/08/2024 | M/S SURAJIT MAJUMDER | ORD/000367/2023-2024 | 1392/CD | 05/12/2023 | Execution of different works related to CHAKIARCHARA PWSS under JAL JEEVAN MISSION | 20.02 | BP-338 | 04/09/2024 | VCH/000305/2024-2025 |
231 | Coochbehar Division | BILL/00393/2024-2025 | 31/08/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000536/2021-2022 | 1636/CD | 29/03/2022 | Providing FHTC Works, Laying of pipe line Constructions of 3rd site Pump House, Boundary Wall at PUTIMARI FULESWARI W.S.S under Cooch Behar Division P.H.E.Dte. | 2.75 | BP-350 | 04/09/2024 | VCH/000324/2024-2025 |
232 | Coochbehar Division | BILL/00396/2024-2025 | 31/08/2024 | PARITOSH DATTA | ORD/000896/2022-2023 | 204/TFG | 05/07/2022 | Providing FHTC with replacing old damaged pipe line with new UPVC pipe line other allied works at SHIKARPUR PWSS under Tufanganj Sub-Division, PHED. | 1.56 | BP-349 | 04/09/2024 | VCH/000157/2024-2025 |
233 | Coochbehar Division | BILL/00465/2024-2025 | 03/08/2024 | MALAY KR.DEB | ORD/000576/2022-2023 | 1856/CD | 14/03/2023 | Execution of different works related to JIRANPUR PART B PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1119/1-5/NBC-1; Dt.: 13-02-23 | 41.07 | BP-385 | 20/09/2024 | VCH/000398/2024-2025 |
234 | Coochbehar Division | BILL/00473/2024-2025 | 11/09/2024 | Z STAR COMMOTRADE PVT LTD | ORD/000143/2023-2024 | 863/CD | 02/08/2023 | Execution of different works related to SAJHERPAR GHORAMARA PWSS under JAL JEEVAN MISSION | 61.21 | BP-381 | 20/09/2024 | VCH/000331/2024-2025 |
235 | Coochbehar Division | BILL/00477/2023-2024 | 26/08/2023 | CHAKRABORTY ENTERPRISE. | ORD/000480/2022-2023 | 1535/CD | 20/01/2023 | PROVIDING FHTC LAYING OF PIPE LINE AT KALARAYER KUTHE (ZONE-II) PWSS under JAL JEEVAN MISSION (PART ¿C) | 3.04 | R 12555 | 25/10/2024 | VCH/001847/2023-2024 |
236 | Coochbehar Division | BILL/00556/2024-2025 | 13/09/2024 | MS DD ENTERPRISE | ORD/000330/2023-2024 | 1313/CD | 24/11/2023 | Execution of different works related to KHARIKABARI PWSS under JAL JEEVAN MISSION | 9.06 | BP-399 | 20/09/2024 | VCH/000363/2024-2025 |
237 | Coochbehar Division | BILL/00566/2024-2025 | 13/09/2024 | D S CONSTRUCTION | ORD/000569/2022-2023 | 1687/CD | 13/02/2023 | Execution of different works related to HOKADAHA PRATHAM KHANDA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1111/1-5/NBC-1; Dt.: 13-02-23 | 125.64 | BP-402 | 20/09/2024 | VCH/000376/2024-2025 |
238 | Coochbehar Division | BILL/00846/2024-2025 | 28/09/2024 | UDAY CHAKI | ORD/000369/2023-2024 | 1390/CD | 05/12/2023 | Execution of different works related to UCHALPUKURI PWSS under JAL JEEVAN MISSION | 19.32 | wr-110 | 14/11/2024 | VCH/000418/2024-2025 |
239 | Coochbehar Division | BILL/00867/2023-2024 | 13/10/2023 | SWAPAN KUMAR ROY | ORD/000426/2021-2022 | 1476/CD | 10/03/2022 | Construction of 300 cum OHR Providing FHTC New Pipe line & other allied works (PART ¿A) at ANDARAN FULBARI ZONE-I PWSS under Cooch Behar Division, PHED | 7.00 | R 21555 | 25/10/2024 | VCH/001843/2023-2024 |
240 | Coochbehar Division | BILL/00087/2024-2025 | 04/06/2024 | M/S TORSHA CONSTRUCTION | ORD/000147/2023-2024 | 859/CD | 22/08/2023 | Execution of different works related to PATCHHARA ZONE 2 PWSS under JAL JEEVAN MISSION | 88.13 | BP-62 | 07/06/2024 | VCH/000020/2024-2025 |
241 | Coochbehar Division | BILL/00091/2024-2025 | 04/06/2024 | NABIN DEBNATH | ORD/000301/2023-2024 | 1055/CD | 22/09/2023 | Execution of different works related to BHALKA area related to Baro Soulmari PWSS under JAL JEEVAN MISSION | 8.78 | BP-59 | 07/06/2024 | VCH/000182/2024-2025 |
242 | Coochbehar Division | BILL/00160/2024-2025 | 19/06/2024 | MESSRS A.B.G CONSTRUCTION | ORD/000466/2021-2022 | 1604/CD | 24/03/2022 | Providing FHTC 3rd Site Pump House Boundary Wall SSPost with soak pit Sinking 250mm X 200mm Big dia Tubewell & New UPVC/DI/GI Pipe line and other allied works (PART ¿B) at SITAI ZONE ¿ I I PWSS under Cooch Behar Division, PHED | 35.39 | BP-122 | 04/07/2024 | VCH/000090/2024-2025 |
243 | Coochbehar Division | BILL/00163/2024-2025 | 19/06/2024 | MS SSB CONSTRUCTION CO | ORD/000507/2023-2024 | 304/CD | 09/02/2024 | Execution of different works related to B.ATIABARI P.KHANDA PWSS under JAL JEEVAN MISSION | 42.83 | BP-108 | 25/06/2024 | VCH/000110/2024-2025 |
244 | Coochbehar Division | BILL/00179/2024-2025 | 22/06/2024 | S & P ENTERPRISE | ORD/000275/2021-2022 | 954/CD | 31/12/2021 | Construction of 150 cum OHR Providing FHTC Sinking 250mm X 200mm Big dia Tubewell & New UPVC/DI Pipe line & other allied works (PART ¿A) at RAKHALMARI PWSS under Cooch Behar Division, PHED | 13.22 | BP-119 | 28/06/2024 | VCH/000149/2024-2025 |
245 | Coochbehar Division | BILL/00187/2024-2025 | 26/06/2024 | SSPR VALVE MANUFACTURING PVT. LTD. | ORD/000554/2023-2024 | 636/CD | 11/03/2024 | Execution of different works related to BHOGRAMGURI PWSS under JAL JEEVAN MISSION | 24.69 | BP-129 | 02/07/2024 | VCH/000103/2024-2025 |
246 | Coochbehar Division | BILL/00246/2024-2025 | 23/07/2024 | MS SSB CONSTRUCTION CO | ORD/000545/2023-2024 | 639/CD | 11/03/2024 | Execution of different works related to DUAI SUAI PWSS under JAL JEEVAN MISSION | 52.79 | BP-195 | 29/07/2024 | VCH/000091/2024-2025 |
247 | Coochbehar Division | BILL/00263/2024-2025 | 01/08/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000151/2023-2024 | 855/CD | 21/08/2023 | Construction of 450 cum OHR and Laying of Pipe line at SHIKARPUR ZONE ? I PWSS under JAL JEEVAN MISSION (PART ?A) | 120.26 | BP-244 | 07/08/2024 | VCH/000238/2024-2025 |
248 | Coochbehar Division | BILL/00275/2024-2025 | 02/08/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000457/2022-2023 | 1508/CD | 19/01/2023 | Execution of different works related to NAHARHATBANDAR PWSS under JAL JEEVAN MISSION SE NBC1/PHED A. O.: 977/1-5/NBC-1; DT: 19-01-23 | 32.36 | BP-258 | 09/08/2024 | VCH/000123/2024-2025 |
249 | Coochbehar Division | BILL/00277/2024-2025 | 02/08/2024 | NABIN DEBNATH | ORD/000490/2022-2023 | 1555/CD | 24/01/2023 | Execution of different works related to LANKABAR PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1016/1-5/NBC-1; Dt.: 24-01-23 | 43.64 | BP-266 | 09/08/2024 | VCH/000113/2024-2025 |
250 | Coochbehar Division | BILL/00436/2024-2025 | 03/09/2024 | SANKAR BANIK | ORD/000566/2023-2024 | 606/CD | 11/03/2024 | Execution of different works related to KALARAYERKUTHI PWSS under JAL JEEVAN MISSION | 16.22 | BP-374 | 10/09/2024 | VCH/000337/2024-2025 |
251 | Coochbehar Division | BILL/00439/2024-2025 | 03/09/2024 | PATLAKHOWA UN EMP CO OP LAB CONT AND CONST SOC LTD | ORD/000403/2021-2022 | 1461/CD | 10/03/2022 | Providing FHTC and Laying of Pipe line at BARO DHAPERCHATRA PWSS under Cooch Behar Division, PHED | 5.74 | BP-369 | 11/09/2024 | VCH/000369/2024-2025 |
252 | Coochbehar Division | BILL/00441/2024-2025 | 03/09/2024 | SUBHAS CHANDRA ROY | ORD/000027/2024-2025 | 1135/CD | 14/06/2024 | Execution of different works related to CHHAT GURIAHATI PWSS under JAL JEEVAN MISSION Z3 | 19.47 | BP-355 | 11/09/2024 | VCH/000253/2024-2025 |
253 | Coochbehar Division | BILL/00443/2024-2025 | 03/09/2024 | PATLAKHOWA UN EMP CO OP LAB CONT AND CONST SOC LTD | ORD/000071/2022-2023 | 268/CD | 24/05/2022 | Providing FHTC, Repairing of reservoir and Boundary Wall at H/W site and laying new Pipe line and other allied works at Augmentation BARO DHAPERCHATRA PWSS under Cooch Behar Division, PHED.(Part-C) | 1.57 | BP-367 | 10/09/2024 | VCH/000368/2024-2025 |
254 | Coochbehar Division | BILL/00325/2024-2025 | 13/08/2024 | RHYNO INFRASTRUCTURE | ORD/000587/2023-2024 | 624/CD | 11/03/2024 | Designing, Making & erecting of DB using logo tagline for Cooch Behar districts under Jal Jeevan Mission (JJM) Support Activities Part I | 95.88 | BP-297 | 21/08/2024 | VCH/000142/2024-2025 |
255 | Coochbehar Division | BILL/00326/2024-2025 | 13/08/2024 | SUPER TECH ENGINEERS CO- OPERATIVE SPOCY.LTD | ORD/000088/2023-2024 | 623/CD | 12/07/2023 | Execution of different works related to BHEBHERI MANABARI PWSS under JAL JEEVAN MISSION | 81.85 | BP-300 | 21/08/2024 | VCH/000278/2024-2025 |
256 | Coochbehar Division | BILL/00339/2024-2025 | 17/08/2024 | ASHIM KUMAR CHAKRABORTY | ORD/000735/2022-2023 | 1735/CD | 21/02/2023 | Providing FHTC and Laying of pipe line, Const. Of Pump house , B/Wall at 3rd T/W site and other allied work of ATPUKURI ZONE ¿I PWSS under JAL JEEVAN MISSION (PART ¿D) | 15.16 | BP-332 | 03/09/2024 | VCH/000208/2024-2025 |
257 | Coochbehar Division | BILL/00356/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE KISMAT DASGRAM VR ADJACENT TO NAJIRGANJ ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR | 18.53 | BP-304 | 31/08/2024 | VCH/000293/2024-2025 |
258 | Coochbehar Division | BILL/00605/2024-2025 | 16/09/2024 | GOUTAM KUMAR DAS | ORD/000423/2023-2024 | 1479/CD | 20/12/2023 | Execution of different works related to DEBGRAM PWSS under JAL JEEVAN MISSION | 18.79 | BP-396 | 20/09/2024 | VCH/000350/2024-2025 |
259 | Coochbehar Division | BILL/00782/2024-2025 | 23/09/2024 | MS BIDYUT SARKAR | ORD/000598/2023-2024 | 641/CD | 11/03/2024 | Laying DI P/Line & other allied works related to BHORAM PWSS under JAL JEEVAN MISSION | 67.47 | BP-424 | 26/09/2024 | VCH/000388/2024-2025 |
260 | Coochbehar Division | BILL/00814/2024-2025 | 26/09/2024 | SAMBHU BANIK | ORD/000056/2024-2025 | 1335/CD | 24/07/2024 | Execution of different works related to LAWCHAPRA PWSS under JAL JEEVAN MISSION | 52.38 | wr-110 | 14/11/2024 | VCH/000422/2024-2025 |
261 | Coochbehar Division | BILL/01072/2023-2024 | 07/12/2023 | KARTICK CH SEAL | ORD/000787/2022-2023 | 1863/CD | 14/03/2023 | Execution of different works related to TAKAGACH PWSS under JAL JEEVAN MISSION | 13.49 | BP-346 | 04/09/2024 | VCH/002001/2023-2024 |
262 | Coochbehar Division | BILL/00026/2024-2025 | 09/05/2024 | DULAL MAJUMDER | ORD/000386/2022-2023 | 804/CD | 09/09/2022 | Providing FHTC and Laying of Pipe line & Construction of Pump house 2ND Site of PANIGRAM ZONE - I I PWSS under JAL JEEVAN MISSION (PART ¿R) | 0.45 | BP-28 | 29/05/2024 | VCH/000015/2024-2025 |
263 | Coochbehar Division | BILL/00038/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000532/2023-2024 | 366/CD | 22/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Dinhata-I Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-23 | 29/05/2024 | VCH/000024/2024-2025 |
264 | Coochbehar Division | BILL/00058/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000530/2023-2024 | 365/CD | 22/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Tufanganj-II, Augmentation of Naharhat Bandar Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-41 | 29/05/2024 | VCH/000043/2024-2025 |
265 | Coochbehar Division | BILL/00128/2024-2025 | 14/06/2024 | SHRI ANNAPURNA DISTRIBUTORS | ORD/000519/2022-2023 | 1606/CD | 03/02/2023 | Execution of different works related to PURBA DHULIA BALDIHATI PWSS under JAL JEEVAN MISSION | 30.33 | BP-103 | 20/06/2024 | VCH/000062/2024-2025 |
266 | Coochbehar Division | BILL/00201/2024-2025 | 28/06/2024 | S DUTTA | ORD/000462/2022-2023 | 1513/CD | 19/01/2023 | Execution of different works related to MAINAGURI DIGHALHATI PWSS under JAL JEEVAN MISSION SE NBC1/PHED A. O.: 982/1-5/NBC-1; DT: 19-01-23 | 91.44 | BP-146 | 15/07/2024 | VCH/000118/2024-2025 |
267 | Coochbehar Division | BILL/00202/2024-2025 | 01/07/2024 | SIDHARTHA ROY | ORD/000732/2022-2023 | 1738/CD | 21/02/2023 | Providing FHTC & Construction of pump house, Boundary wall (2nd t/w site) and laying of Pipe line other allied works at ATPUKURI ZONE - II PWSS Under Cooch Behar division P.H.E.Dte.(Part-C) | 11.09 | BP-152 | 15/07/2024 | VCH/000076/2024-2025 |
268 | Coochbehar Division | BILL/00204/2024-2025 | 01/07/2024 | MS BIDYUT SARKAR | ORD/000552/2022-2023 | 1774/CD | 02/03/2023 | Execution of different works related to BAISGURI KHANDA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1242/1-5/NBC-1; Dt.: 02-03-23 | 85.25 | BP-145 | 15/07/2024 | VCH/000143/2024-2025 |
269 | Coochbehar Division | BILL/00220/2024-2025 | 08/07/2024 | SANKAR CHAKRABORTY | ORD/000603/2022-2023 | 1855/CD | 14/03/2023 | Execution of different works related to DAKHSHIN DIGHALTARI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1122/1-5/NBC-1; Dt.: 13-02-23 | 68.04 | BP-171 | 15/07/2024 | VCH/000152/2024-2025 |
270 | Coochbehar Division | BILL/00224/2024-2025 | 09/07/2024 | M/S PRADIP KUMAR PAL | ORD/000521/2023-2024 | 319/CD | 09/02/2024 | Execution of different works related to JHAUKUTHI PWSS under JAL JEEVAN MISSION | 40.21 | BP-186 | 17/07/2024 | VCH/000099/2024-2025 |
271 | Coochbehar Division | BILL/00226/2024-2025 | 10/07/2024 | BIJOY ROY | ORD/000504/2023-2024 | 300/CD | 09/02/2024 | Execution of different works related to NENDARPAR PWSS under JAL JEEVAN MISSION | 19.72 | BP-179 | 17/07/2024 | VCH/000156/2024-2025 |
272 | Coochbehar Division | BILL/00228/2024-2025 | 11/07/2024 | ABHIJIT KUMAR DAS | ORD/000007/2023-2024 | 45/CD | 17/04/2023 | Execution of different works related to AUG of TANAPAKHA PWSS under JAL JEEVAN MISSION. SE,NBC-1,PHED A.O. No.: 44/1-5/NBC-1; Dt.: 17-04-23 | 49.36 | BP-183 | 17/07/2024 | VCH/000159/2024-2025 |
273 | Coochbehar Division | BILL/00229/2024-2025 | 11/07/2024 | M/S J C ENTERPRISE | ORD/000598/2022-2023 | 1613/CD | 03/02/2023 | Execution of different works related to DINHATA (P) PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1054/1-5/NBC-1; Dt.: 03-02-23 | 91.80 | BP-187 | 17/07/2024 | VCH/000160/2024-2025 |
274 | Coochbehar Division | BILL/00292/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000329/2024-2025 | 847/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Tufanganj-I, DUDDER KUTHIDEWANBAS PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-267 | 09/08/2024 | VCH/000141/2024-2025 |
275 | Coochbehar Division | BILL/00293/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000330/2024-2025 | 848/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Tufanganj-II, DUDDER KUTHIDEWANBAS PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-272 | 14/08/2024 | VCH/000139/2024-2025 |
276 | Coochbehar Division | BILL/00313/2024-2025 | 10/08/2024 | M/S PRADIP KUMAR PAL | ORD/000521/2023-2024 | 319/CD | 09/02/2024 | Execution of different works related to JHAUKUTHI PWSS under JAL JEEVAN MISSION | 18.05 | BP-301 | 21/08/2024 | VCH/000279/2024-2025 |
277 | Coochbehar Division | BILL/00314/2024-2025 | 10/08/2024 | ASHIM KUMAR CHAKRABORTY | ORD/000535/2022-2023 | 1611/CD | 03/02/2023 | Execution of different works related to KHENGCHI PWSS under JAL JEEVAN MISSION | 87.07 | BP-299 | 21/08/2024 | VCH/000277/2024-2025 |
278 | Coochbehar Division | BILL/00369/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDEGOBRACHOWRA CHOWPATHI TO AMBARI BAZAR ALLAR BAZAR BHAGNIR PART ADJACENT HEMKUMARI Z 2road VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in t | 10.62 | BP-307 | 31/08/2024 | VCH/000284/2024-2025 |
279 | Coochbehar Division | BILL/00372/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1471 | 06/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING JIKABARI GHAT TO KAWARGHAT ROAD ADJACENT HEMKUMARI ADJACENT PUTIA BARA MASIA road VR ( IN stretches FROM 0.00 KM TO 3.50 KM UNDER MATHABHANGA SUB DIVISION UNDER PWD Cooch Behar divi | 7.12 | BP-310 | 31/08/2024 | VCH/000287/2024-2025 |
280 | Coochbehar Division | BILL/00456/2024-2025 | 05/09/2024 | MS SSB CONSTRUCTION CO | ORD/000565/2022-2023 | 1959/CD | 24/03/2023 | Execution of different works related to DUAI SUAI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1342/1-5/NBC-1; Dt.: 24-03-23 | 105.77 | BP-370 | 10/09/2024 | VCH/000333/2024-2025 |
281 | Coochbehar Division | BILL/00457/2024-2025 | 05/09/2024 | M/S CLASSIC BUILDERS AND TRADERS | ORD/000128/2023-2024 | 633/CD | 12/07/2023 | Execution of different works related to KALARAYERKUTHI PWSS under JAL JEEVAN MISSION | 63.39 | BP-375 | 10/09/2024 | VCH/000336/2024-2025 |
282 | Coochbehar Division | BILL/00469/2024-2025 | 11/09/2024 | ORIENTAL CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. | ORD/000616/2022-2023 | 1874/CD | 14/03/2023 | Execution of different works related to MADHURBHASA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1135/1-5/NBC-1; Dt.: 13-02-23 | 58.95 | BP-386 | 20/09/2024 | VCH/000400/2024-2025 |
283 | Coochbehar Division | BILL/00472/2024-2025 | 11/09/2024 | M/S VINOD KUMAR JAIN | ORD/000023/2024-2025 | 1131/CD | 14/06/2024 | Execution of different works related to ATPUKURI PWSS under JAL JEEVAN MISSION Z1 A | 29.02 | BP-389 | 20/09/2024 | VCH/000339/2024-2025 |
284 | Coochbehar Division | BILL/00557/2024-2025 | 13/09/2024 | RAHAMAN ENTERPRISE | ORD/000065/2023-2024 | 401/CD | 23/05/2023 | Execution of different works related to DAWAGURI PWSS under JAL JEEVAN MISSION | 9.86 | BP-398 | 20/09/2024 | VCH/000375/2024-2025 |
285 | Coochbehar Division | BILL/00558/2024-2025 | 13/09/2024 | SEKHAR GHOSAL | ORD/000414/2022-2023 | 1225/CD | 28/11/2022 | Providing FHTC & other allied works at BALARAMPUR ZONE - II PWSS under JAL JEEVAN MISSION | 12.33 | BP-401 | 20/09/2024 | VCH/000351/2024-2025 |
286 | Coochbehar Division | BILL/00693/2024-2025 | 21/09/2024 | NABIN DEBNATH | ORD/000621/2022-2023 | 1875/CD | 14/03/2023 | Execution of different works related to AUG. of BAJEJAMA CHILAKHANA ZONE-II PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1175/1-5/NBC-1; Dt.: 24-02-23 | 20.51 | BP-416 | 26/09/2024 | VCH/000383/2024-2025 |
287 | Coochbehar Division | BILL/01491/2023-2024 | 20/02/2024 | CHAKRABORTY ENTERPRISE | ORD/000168/2023-2024 | 945/CD | 04/09/2023 | Execution of different works related to GURIAHATI PWSS under JAL JEEVAN MISSION | 29.97 | W 1245 | 25/10/2024 | VCH/001861/2023-2024 |
288 | Coochbehar Division | BILL/01523/2023-2024 | 24/02/2024 | BRAJA GOPAL SAHA | ORD/000140/2023-2024 | 806/CD | 08/08/2023 | Execution of different works related to BARA MADHUSUDAN PWSS under JAL JEEVAN MISSION | 5.30 | wr-110 | 25/10/2024 | VCH/001987/2023-2024 |
289 | Coochbehar Division | BILL/01744/2023-2024 | 16/03/2024 | MALAY KR.DEB | ORD/000576/2022-2023 | 1856/CD | 14/03/2023 | Execution of different works related to JIRANPUR PART B PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1119/1-5/NBC-1; Dt.: 13-02-23 | 111.82 | W 12455 | 25/10/2024 | VCH/001984/2023-2024 |
290 | Coochbehar Division | BILL/01935/2023-2024 | 28/03/2024 | M/S NARAYAN KUMAR GHOSH | ORD/000067/2023-2024 | 404/CD | 23/05/2023 | Execution of different works related to A. NIZTARAF PWSS under JAL JEEVAN MISSION | 10.60 | BP-72 | 07/06/2024 | VCH/001986/2023-2024 |
291 | Coochbehar Division | BILL/01946/2023-2024 | 30/03/2024 | M/S DHAR ENTERPRISE | ORD/000590/2022-2023 | 1674/CD | 13/02/2023 | Execution of different works related to BARA PINJARIRJHAR PWSS under JAL JEEVAN MISSION | 56.06 | BP-3 | 03/05/2024 | VCH/001817/2023-2024 |
292 | Coochbehar Division | BILL/01952/2023-2024 | 30/03/2024 | NORTH BENGAL CONSTRUCTION CO | ORD/000028/2023-2024 | 382/CD | 23/05/2023 | Execution of different works related to JAMALDAH HAT (Bhogramguri Adj. Area) PWSS under JAL JEEVAN MISSION | 4.83 | BP-2 | 03/05/2024 | VCH/001811/2023-2024 |
293 | Coochbehar Division | BILL/00066/2024-2025 | 28/05/2024 | M/S J C ENTERPRISE | ORD/000624/2022-2023 | 1614/CD | 03/02/2023 | Execution of different works related to JHURIPARA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1058/1-5/NBC-1; Dt.: 03-02-23 | 39.79 | BP-54 | 04/06/2024 | VCH/000181/2024-2025 |
294 | Coochbehar Division | BILL/00067/2024-2025 | 28/05/2024 | KRISHNA GOPAL BASK | ORD/000262/2023-2024 | 1028/CD | 22/09/2023 | Name of Work: Execution of different works related to BOXIRHAT PWSS under JAL JEEVAN MISSION PART O | 25.97 | BP-53 | 05/06/2024 | VCH/000180/2024-2025 |
295 | Coochbehar Division | BILL/00077/2024-2025 | 30/05/2024 | JAL PRAVAHIKA PRIVATE LIMITED | ORD/000097/2023-2024 | 632/CD | 12/07/2023 | Execution of different works related to NAKARANJAN PWSS under JAL JEEVAN MISSION | 92.03 | BP-67 | 07/06/2024 | VCH/000184/2024-2025 |
296 | Coochbehar Division | BILL/00080/2024-2025 | 31/05/2024 | ASHIM KUMAR CHAKRABORTY | ORD/000619/2022-2023 | 1905/CD | 17/03/2023 | Execution of different works related to AUG. SIKARPUR PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1287/1-5/NBC-1; Dt.: 17-03-23 | 48.82 | BP-69 | 07/06/2024 | VCH/000018/2024-2025 |
297 | Coochbehar Division | BILL/00090/2024-2025 | 04/06/2024 | GOUTAM KUMAR DAS | ORD/000551/2023-2024 | 620/CD | 11/03/2024 | Execution of different works related to DHALDABRI PWSS under JAL JEEVAN MISSION | 52.27 | BP-64 | 10/06/2024 | VCH/000122/2024-2025 |
298 | Coochbehar Division | BILL/00094/2024-2025 | 06/06/2024 | SUBHAS CHANDRA ROY | ORD/000361/2023-2024 | 1396/CD | 05/12/2023 | Execution of different works related to BARO GOPALPUR PWSS under JAL JEEVAN MISSION | 33.11 | BP-76 | 12/06/2024 | VCH/000189/2024-2025 |
299 | Coochbehar Division | BILL/00099/2024-2025 | 07/06/2024 | JAL PRAVAHIKA PVT. LTD. | ORD/000580/2022-2023 | 1770/CD | 02/03/2023 | Execution of different works related to MAHISHCHARU PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1207/1-5/NBC-1; Dt.: 01-03-23 | 61.54 | BP-87 | 12/06/2024 | VCH/000194/2024-2025 |
300 | Coochbehar Division | BILL/00150/2022-2023 | 27/12/2022 | MATARA CONSTRUCTION CO. | ORD/000250/2021-2022 | 899/CD | 24/12/2021 | Construction of 600 cum OHR Providing FHTC & New UPVC Pipe line & other allied works (PART ¿A) atBALARAMPUR ZONE ¿ I PWSS under Cooch Behar Division, PHED | 37.69 | wr entry | 25/10/2024 | VCH/001728/2022-2023 |
301 | Coochbehar Division | BILL/00152/2024-2025 | 16/06/2024 | SHREE RANI SATI ENTERPRISE | ORD/000466/2022-2023 | 1517/CD | 19/01/2023 | Execution of different works related to PETLAEPRA PWSS under JAL JEEVAN MISSIONSE NBC1/PHED A. O.: 986/1-5/NBC-1; DT: 19-01-23 | 1.36 | BP-106 | 25/06/2024 | VCH/000198/2024-2025 |
302 | Coochbehar Division | BILL/00164/2024-2025 | 19/06/2024 | GOUTAM KUMAR DAS | ORD/000084/2023-2024 | 619/CD | 12/07/2023 | Execution of different works related to CHHAT RAMPUR PWSS under JAL JEEVAN MISSION | 2.63 | BP-110 | 25/06/2024 | VCH/000051/2024-2025 |
303 | Coochbehar Division | BILL/00166/2024-2025 | 21/06/2024 | D S CONSTRUCTION | ORD/000569/2022-2023 | 1687/CD | 13/02/2023 | Execution of different works related to HOKADAHA PRATHAM KHANDA PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1111/1-5/NBC-1; Dt.: 13-02-23 | 4.37 | BP-127 | 28/06/2024 | VCH/000204/2024-2025 |
304 | Coochbehar Division | BILL/00170/2024-2025 | 22/06/2024 | PALLAB BHAWAL | ORD/000424/2021-2022 | 1522/CD | 15/03/2022 | Constructions of 250 Cum OHR as per Departmental Design & drawing, Providing F.H.T.C New laying of UPVC/DI Pipe Line & other allied work at BANESWAR Zone-III PWSS under Cooch Behar Division , P.H.E Dte. (PART-A) | 22.40 | BP-125 | 28/06/2024 | VCH/000054/2024-2025 |
305 | Coochbehar Division | BILL/00188/2024-2025 | 26/06/2024 | BHAGWATI BHUJEL | ORD/000781/2023-2024 | 662/CD | 11/03/2024 | Execution of different works related to TFG LAB under BAJEJAMA CHILAKHANA PRATHAM KHANDA PWSS under JAL JEEVAN MISSION | 6.94 | BP-136 | 01/07/2024 | VCH/000133/2024-2025 |
306 | Coochbehar Division | BILL/00190/2023-2024 | 02/06/2023 | HIRAK CONSTRUCTION | ORD/000427/2022-2023 | 195/SD | 27/06/2022 | Laying distribution system of pipe line with FHTC under Chandamari PWSS PHED. (Part-B-5) | 4.99 | R 500000 | 25/10/2024 | VCH/001830/2023-2024 |
307 | Coochbehar Division | BILL/00240/2024-2025 | 19/07/2024 | UMEX POLYMERS PVT LTD | ORD/000606/2022-2023 | 1900/CD | 17/03/2023 | Execution of different works related to BARA MARICHA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1293/1-5/NBC-1; Dt.: 17-03-23 | 81.07 | BP-197 | 29/07/2024 | VCH/000166/2024-2025 |
308 | Coochbehar Division | BILL/00243/2024-2025 | 19/07/2024 | M/S CLASSIC BUILDERS AND TRADERS | ORD/000128/2023-2024 | 633/CD | 12/07/2023 | Execution of different works related to KALARAYERKUTHI PWSS under JAL JEEVAN MISSION | 147.10 | BP-203 | 31/07/2024 | VCH/000130/2024-2025 |
309 | Coochbehar Division | BILL/00245/2024-2025 | 19/07/2024 | SAYAN SAHA | ORD/000777/2023-2024 | 543/CD | 29/02/2024 | Calibration of necessary Instrument ,Glasswares as per ISO/IEC 17025:2017 of Cooch Behar District Water Testing Laboratory under Cooch Behar Division P.H.E Dte | 0.46 | BP-199 | 29/07/2024 | VCH/000168/2024-2025 |
310 | Coochbehar Division | BILL/00258/2024-2025 | 01/08/2024 | BHAGWATI BHUJEL | ORD/000782/2023-2024 | 663/CD | 11/03/2024 | Execution of different works related to DHT LAB area under JARABARI PRATHAM KHANDA PWSS under JAL JEEVAN MISSION | 6.91 | BP-249 | 07/08/2024 | VCH/000241/2024-2025 |
311 | Coochbehar Division | BILL/00269/2024-2025 | 02/08/2024 | UNIQUE ENGINEERS CO OP SOCIETY LTD | ORD/000265/2023-2024 | 1035/CD | 22/09/2023 | Name of Work: Execution of different works related to CHHAT RAMPUR PWSS under JAL JEEVAN MISSION PART B | 12.86 | BP-259 | 09/08/2024 | VCH/000250/2024-2025 |
312 | Coochbehar Division | BILL/00271/2024-2025 | 02/08/2024 | BISWAJIT GUHA | ORD/000646/2022-2023 | 2017/CD | 30/03/2023 | Execution of different works related to AUG. of MARANADIRKUTHI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1376/1-5/NBC-1; Dt.: 28-03-23 | 35.00 | BP-255 | 09/08/2024 | VCH/000247/2024-2025 |
313 | Coochbehar Division | BILL/00446/2024-2025 | 03/09/2024 | GOUTAM KUMAR DAS | ORD/000018/2024-2025 | 1126/CD | 14/06/2024 | Execution of different works related to BARO NALANGIBARI PWSS under JAL JEEVAN MISSION MTB | 51.32 | BP-373 | 10/09/2024 | VCH/000344/2024-2025 |
314 | Coochbehar Division | BILL/00350/2024-2025 | 17/08/2024 | NANDALAL SARKAR | ORD/000069/2022-2023 | 266/CD | 24/05/2022 | Providing FHTC Works, Laying of pipe line Constructions of 3rd site Pump House, Boundary Wall at LAWCHAPRA ZONE I W.S.S under Cooch Behar Division P.H.E.Dte | 1.00 | BP-323 | 03/09/2024 | VCH/000121/2024-2025 |
315 | Coochbehar Division | BILL/00362/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE DINHATA SAHEB GANJ ADJACENT TO BOSKOTAL road VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR, | 7.38 | BP-313 | 31/08/2024 | VCH/000233/2024-2025 |
316 | Coochbehar Division | BILL/00781/2024-2025 | 23/09/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000483/2023-2024 | 285/CD | 09/02/2024 | Execution of different works related to PATCHHARA Z I PWSS under JAL JEEVAN MISSION PART A | 52.59 | BP-417 | 26/09/2024 | VCH/000384/2024-2025 |
317 | Coochbehar Division | BILL/00784/2024-2025 | 23/09/2024 | MS BIDYUT SARKAR | ORD/000169/2023-2024 | 946/CD | 04/09/2023 | Execution of different works related to GHUGHUMARI PWSS under JAL JEEVAN MISSION | 80.90 | BP-423 | 26/09/2024 | VCH/000387/2024-2025 |
318 | Coochbehar Division | BILL/00790/2024-2025 | 24/09/2024 | BILTU DAS | ORD/000065/2024-2025 | 1272/CD | 03/07/2024 | Execution of different works related to KHAGRABARI Z PWSS under JAL JEEVAN MISSION | 53.38 | BP-433 | 27/09/2024 | VCH/000395/2024-2025 |
319 | Coochbehar Division | BILL/00003/2024-2025 | 09/05/2024 | SUJIT KUMAR SAHA | ORD/000882/2022-2023 | 1984/CD | 27/03/2023 | Execution of different works related to AUG. of BHULKI PWSS under JAL JEEVAN MISSION | 56.68 | BP-11 | 15/05/2024 | VCH/000057/2024-2025 |
320 | Coochbehar Division | BILL/00007/2024-2025 | 09/05/2024 | MS SSB CONSTRUCTION CO | ORD/000087/2023-2024 | 622/CD | 12/07/2023 | Execution of different works related to Aug. of TUTIARKUTHI PWSS under JAL JEEVAN MISSION | 3.56 | BP-18 | 15/05/2024 | VCH/000005/2024-2025 |
321 | Coochbehar Division | BILL/00014/2024-2025 | 09/05/2024 | S & P ENTERPRISE | ORD/000094/2023-2024 | 629/CD | 12/07/2023 | Execution of different works related to CHHOTO BOALMARI (ZONE-ii) PWSS under JAL JEEVAN MISSION | 143.47 | BP-12 | 15/05/2024 | VCH/000003/2024-2025 |
322 | Coochbehar Division | BILL/00024/2024-2025 | 09/05/2024 | SHREE RANI SATI ENTERPRISE | ORD/000005/2023-2024 | 41/CD | 13/04/2023 | Execution of different works related to Aug. of PHULBARI PART-B PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 34/1-5/NBC-1; Dt.: 13-04-23 | 1.61 | BP-24 | 31/05/2024 | VCH/000025/2024-2025 |
323 | Coochbehar Division | BILL/00048/2024-2025 | 17/05/2024 | DISTRICT HEALTH & FAMILY WELFARE SAMITY COOCHBEHAR | null | 6171 6190 | 05/04/2021 | FTK SA,MPLE TEST ASHA | 16.78 | wr-110 | 03/10/2024 | VCH/000364/2024-2025 |
324 | Coochbehar Division | BILL/00109/2024-2025 | 11/06/2024 | GOUTAM KUMAR DAS | ORD/000674/2022-2023 | 1990/CD | 28/03/2023 | Execution of different works related to Aug. of BARASOLMARI-SINGIJANI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1370/1-5/NBC-1; Dt.: 28-03-23 | 60.94 | BP-91 | 15/06/2024 | VCH/000205/2024-2025 |
325 | Coochbehar Division | BILL/00132/2024-2025 | 14/06/2024 | M/S SURAJIT MAJUMDER | ORD/000488/2023-2024 | 290/CD | 09/02/2024 | Execution of different works related to SIKARPUR PWSS under JAL JEEVAN MISSION MKG | 5.03 | BP-102 | 20/06/2024 | VCH/000059/2024-2025 |
326 | Coochbehar Division | BILL/00134/2024-2025 | 15/06/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000550/2022-2023 | 1786/CD | 02/03/2023 | Execution of different works related to KHARI ANALDHONDRA PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1231/1-5/NBC-1; Dt.: 02-03-23 | 25.58 | BP-104 | 25/06/2024 | VCH/000086/2024-2025 |
327 | Coochbehar Division | BILL/00136/2024-2025 | 15/06/2024 | M/S. SAHA CONSTRUCTION | ORD/000537/2023-2024 | 325/CD | 09/02/2024 | Execution of different works related to BHANGRI P KHANDA PWSS under JAL JEEVAN MISSION | 29.32 | BP-128 | 28/06/2024 | VCH/000107/2024-2025 |
328 | Coochbehar Division | BILL/00196/2024-2025 | 27/06/2024 | DAKSHIN RANGALIBAZNA WELFARE ASSOCIATION | ORD/000142/2023-2024 | 810/CD | 08/08/2023 | Engagement of Block Level Community Mobilizer through Implementation Support Organization (ISAs) for Coochbehar districts under Jal Jeevan Mission (JJM) Support Activities | 30.62 | BP-131 | 01/07/2024 | VCH/000132/2024-2025 |
329 | Coochbehar Division | BILL/00200/2024-2025 | 28/06/2024 | GOUTAM KUMAR DAS | ORD/000477/2023-2024 | 279/CD | 09/02/2024 | Execution of different works related to BARA MARICHA PWSS under JAL JEEVAN MISSION | 65.36 | BP-156 | 15/07/2024 | VCH/000078/2024-2025 |
330 | Coochbehar Division | BILL/00207/2024-2025 | 01/07/2024 | SSPR VALVE MANUFACTURING PVT. LTD. | ORD/000555/2023-2024 | 648/CD | 11/03/2024 | Execution of different works related to B.CHILAKHANA 1 PWSS under JAL JEEVAN MISSION | 12.87 | BP-154 | 15/07/2024 | VCH/000074/2024-2025 |
331 | Coochbehar Division | BILL/00213/2024-2025 | 03/07/2024 | M/S NARAYAN KR. GHOSH | ORD/000156/2023-2024 | 865/CD | 22/08/2023 | Providing FHTC and Laying of Pipe line of SHIKARPUR ZONE ? II PWSS under JAL JEEVAN MISSION (PART ?D) | 73.05 | BP-153 | 15/07/2024 | VCH/000087/2024-2025 |
332 | Coochbehar Division | BILL/00214/2024-2025 | 03/07/2024 | ASOK KUMAR DHAR | ORD/000160/2023-2024 | 889/CD | 25/08/2023 | Execution of different works related to DAKSHIN BAJEJAMA KHASBAS PWSS under JAL JEEVAN MISSION | 32.99 | BP-157 | 15/07/2024 | VCH/000146/2024-2025 |
333 | Coochbehar Division | BILL/00215/2024-2025 | 08/07/2024 | MA MAHAMAYA UNP. CO-OP LABOUR CONT & CONT SOCITY LTD. | ORD/000505/2023-2024 | 301/CD | 09/02/2024 | Execution of different works related to LAWCHAPRA PWSS under JAL JEEVAN MISSION PART B | 26.31 | BP-174 | 15/07/2024 | VCH/000096/2024-2025 |
334 | Coochbehar Division | BILL/00223/2024-2025 | 08/07/2024 | KARTICK CH SEAL | ORD/000349/2023-2024 | 1333/CD | 24/11/2023 | Execution of different works related to GHUGHUMARI PWSS under JAL JEEVAN MISSION | 9.75 | BP-177 | 15/07/2024 | VCH/000112/2024-2025 |
335 | Coochbehar Division | BILL/00231/2024-2025 | 12/07/2024 | S & P ENTERPRISE | ORD/000144/2023-2024 | 862/CD | 22/08/2023 | Execution of different works related to GARBHADANGA PWSS under JAL JEEVAN MISSION | 90.99 | BP-181 | 17/07/2024 | VCH/000158/2024-2025 |
336 | Coochbehar Division | BILL/00279/2024-2025 | 02/08/2024 | MS SSB CONSTRUCTION CO | ORD/000592/2022-2023 | 1672/CD | 13/02/2023 | Execution of different works related to KHARIJA DURGANAGAR DWITIA KHANDA PWSS under JAL JEEVAN MISSION | 39.85 | BP-256 | 09/08/2024 | VCH/000248/2024-2025 |
337 | Coochbehar Division | BILL/00284/2024-2025 | 02/08/2024 | SENGUPTA ENTERPRISE | ORD/000621/2023-2024 | 679/CD | 11/03/2024 | Uploading charges of (https://ejalshakti.gov.in/imisreports/IMISReportLogin.aspx) related to FHTC under Jal Jeevan Mission in presence of JJM Login authority under Cooch Behar Division, PHE Dte. (Part-F) Under CHANDAN CHOWRA PIPED WATER SUPPLY SCHEME. | 0.97 | BP-252 | 09/08/2024 | VCH/000244/2024-2025 |
338 | Coochbehar Division | BILL/00308/2024-2025 | 08/08/2024 | ANUGRAH CONSTRUCTION PRIVATE LIMITED | ORD/000379/2023-2024 | 1363/CD | 05/12/2023 | Execution of different works related to DHANDHANIA PWSS under JAL JEEVAN MISSION | 45.45 | BP-284 | 14/08/2024 | VCH/000265/2024-2025 |
339 | Coochbehar Division | BILL/00309/2024-2025 | 08/08/2024 | UTPAL CHAKRABORTY | ORD/000046/2023-2024 | 408/CD | 23/05/2023 | Execution of different works related to Aug. of MAHISHKUCHI ZONE-II PWSS under JAL JEEVAN MISSION | 30.69 | BP-288 | 14/08/2024 | VCH/000269/2024-2025 |
340 | Coochbehar Division | BILL/00310/2024-2025 | 08/08/2024 | LIMRA CONSTRUCTION AND INDUSTRIAL DEVELOPMENT | ORD/000556/2023-2024 | 654/CD | 11/03/2024 | Execution of different works related to BARO SOULMARI PWSS under JAL JEEVAN MISSION MTB | 15.66 | BP-282 | 14/08/2024 | VCH/000263/2024-2025 |
341 | Coochbehar Division | BILL/00311/2024-2025 | 08/08/2024 | MS N S CONSTRUCTION | ORD/000135/2023-2024 | 803/CD | 08/08/2023 | Execution of different works related to DAKSHIN SAMILABAS PWSS under JAL JEEVAN MISSION | 42.83 | BP-287 | 14/08/2024 | VCH/000268/2024-2025 |
342 | Coochbehar Division | BILL/00313/2022-2023 | 21/02/2023 | TISTA LABOUR CO-OP CONT AND CONST SOCIETY LTD | ORD/000143/2022-2023 | 211/MTB | 26/07/2022 | Providing functional house hold tap connection within command area of GAJENDRAPUR CHOWRANGEE Piped Water Supply Scheme under Mathabhanga Sub-Division, P.H.E.Dte. Under Jaldhara Programme. Part-B | 4.81 | R 12555 | 25/10/2024 | VCH/001729/2022-2023 |
343 | Coochbehar Division | BILL/00365/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE BHETAGURI NAJIRHAT road KISMAT MOKRABARI VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR, (1) LANKABAR PIPED | 15.41 | BP-318 | 31/08/2024 | VCH/000127/2024-2025 |
344 | Coochbehar Division | BILL/00370/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE DINHATA MEKLIGANJ ADJACENT HEMKUMARI Z 2 road VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR, | 2.99 | BP-308 | 31/08/2024 | VCH/000285/2024-2025 |
345 | Coochbehar Division | BILL/00373/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1471 | 06/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSID 5 NO BAZAR BHOWMIK PARA ADJACENT PUTIA BARA MASIA road VR ( IN stretches FROM 0.00 KM TO 4.00 KM UNDER MATHABHANGA SUB DIVISION UNDER PWD Cooch Behar division DURING YEAR 202 | 7.02 | BP-311 | 31/08/2024 | VCH/000288/2024-2025 |
346 | Coochbehar Division | BILL/00374/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1471 | 06/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDUDUYAR PAR TO FULBARI HOSPITAL MORE ROAD ADJACENT PUTIA BARA MASIA road VR ( IN stretches FROM 0.00 KM TO 8.00 KM UNDER MATHABHANGA SUB DIVISION UNDER PWD Cooch Behar divis | 5.19 | BP-312 | 31/08/2024 | VCH/000289/2024-2025 |
347 | Coochbehar Division | BILL/00381/2024-2025 | 21/08/2024 | MS SSB CONSTRUCTION CO | ORD/000568/2022-2023 | 1688/CD | 13/02/2023 | Execution of different works related to UTTAR PESHTARJHAR PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1108/1-5/NBC-1; Dt.: 13-02-23 | 29.61 | BP-327 | 03/09/2024 | VCH/000313/2024-2025 |
348 | Coochbehar Division | BILL/00382/2024-2025 | 21/08/2024 | LIMRA SOCIAL WELFARE SOCIETY | ORD/000584/2023-2024 | 600/CD | 11/03/2024 | Designing, Making & erecting of DB using logo tagline for Cooch Behar districts under Jal Jeevan Mission (JJM) Support Activities Part G | 52.86 | BP-337 | 04/09/2024 | VCH/000171/2024-2025 |
349 | Coochbehar Division | BILL/00383/2024-2025 | 21/08/2024 | HIRAK CONSTRUCTION | ORD/000273/2021-2022 | 952/CD | 31/12/2021 | Providing FHTC Site Pump House Boundary Wall SSPost with soak pit & New UPVC/DI/GI Pipe line and other allied works (PART ¿B) at PETLA PWSS under Cooch Behar Division, PHED | 16.02 | BP-328 | 03/09/2024 | VCH/000314/2024-2025 |
350 | Coochbehar Division | BILL/00461/2024-2025 | 06/09/2024 | PATLAKHOWA UN EMP CO OP LAB CONT AND CONST SOC LTD | ORD/000076/2022-2023 | 273/CD | 24/05/2022 | Providing FHTC, Construction of pump house, Boundary wall (3rd T/W site) & laying of Pipe line and other allied works at Augmentation of BARO DHAPERCHATRA PWSS under Cooch Behar Division, PHED. (Part-B) | 4.65 | BP-387 | 20/09/2024 | VCH/000373/2024-2025 |
351 | Coochbehar Division | BILL/00692/2024-2025 | 21/09/2024 | SANKAR BANIK | ORD/000493/2023-2024 | 295/CD | 09/02/2024 | Execution of different works related to (Matikata area) CHANDAN CHOWRA PWSS under JAL JEEVAN MISSION | 18.19 | BP-413 | 26/09/2024 | VCH/000355/2024-2025 |
352 | Coochbehar Division | BILL/00695/2024-2025 | 21/09/2024 | DAKSHIN RANGALIBAZNA WELFARE ASSOCIATION | ORD/000142/2023-2024 | 810/CD | 08/08/2023 | Engagement of Block Level Community Mobilizer through Implementation Support Organization (ISAs) for Coochbehar districts under Jal Jeevan Mission (JJM) Support Activities | 10.21 | BP-411 | 26/09/2024 | VCH/000381/2024-2025 |
353 | Coochbehar Division | BILL/00843/2024-2025 | 28/09/2024 | PARITOSH PANDIT | ORD/000801/2023-2024 | 1388/CD | 05/12/2023 | Execution of different works within SIKARPUR area related to UCHALPUKURI ZONE-II PWSS under JAL JEEVAN MISSION | 14.33 | wr-110 | 14/11/2024 | VCH/000419/2024-2025 |
354 | Coochbehar Division | BILL/00845/2024-2025 | 28/09/2024 | MA MAHAMAYA UNP. CO-OP LABOUR CONT & CONT SOCITY LTD. | ORD/000505/2023-2024 | 301/CD | 09/02/2024 | Execution of different works related to LAWCHAPRA PWSS under JAL JEEVAN MISSION PART B | 3.95 | wr-110 | 14/11/2024 | VCH/000421/2024-2025 |
355 | Coochbehar Division | BILL/00847/2023-2024 | 11/10/2023 | BIJOY ROY | ORD/000229/2022-2023 | 715/CD | 27/08/2022 | Providing FHTC and Laying of Pipe line & other allied works related to AUG. of KHAGRABARI PWSS under JAL JEEVAN MISSION | 3.58 | w 12455 | 25/10/2024 | VCH/001868/2023-2024 |
356 | Coochbehar Division | BILL/00849/2024-2025 | 28/09/2024 | M/S KAMAK ENGINEERS AND CO | ORD/000596/2022-2023 | 1788/CD | 02/03/2023 | Execution of different works related to JORPATKI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1233/1-5/NBC-1; Dt.: 02-03-23 | 195.13 | wr 12455 | 14/11/2024 | VCH/000401/2024-2025 |
357 | Coochbehar Division | BILL/01396/2023-2024 | 26/01/2024 | BIJOY ROY | ORD/000533/2021-2022 | 1633/CD | 29/03/2022 | Providing FHTC Works, Laying of pipe line Constructions of Switch Room, Boundary Wall at SINGIMARI PASCHIMPAR W.S.S under Cooch Behar Division P.H.E.Dte. PART A | 13.03 | wr-110 | 25/10/2024 | VCH/001996/2023-2024 |
358 | Coochbehar Division | BILL/00081/2024-2025 | 31/05/2024 | RAJAT ROY | ORD/000325/2023-2024 | 1308/CD | 24/11/2023 | Execution of different works related to CHANDAMARI PWSS under JAL JEEVAN MISSION | 4.39 | BP-71 | 07/06/2024 | VCH/000081/2024-2025 |
359 | Coochbehar Division | BILL/00096/2024-2025 | 07/06/2024 | WBSEDCL | null | 196/cd | 05/02/2024 | shifting of H.T electric line hws natunbas | 2.34 | BP-89 | 12/06/2024 | VCH/000195/2024-2025 |
360 | Coochbehar Division | BILL/00097/2024-2025 | 07/06/2024 | WBSEDCL | null | DM/DHD/NS/813 | 01/12/2023 | shifting of LTOH LINE AT GABUA PWS SITAI CCC | 0.47 | BP-88 | 12/06/2024 | VCH/000031/2024-2025 |
361 | Coochbehar Division | BILL/00106/2023-2024 | 04/05/2023 | MESSRS A.B.G CONSTRUCTION | ORD/000466/2021-2022 | 1604/CD | 24/03/2022 | Providing FHTC 3rd Site Pump House Boundary Wall SSPost with soak pit Sinking 250mm X 200mm Big dia Tubewell & New UPVC/DI/GI Pipe line and other allied works (PART ¿B) at SITAI ZONE ¿ I I PWSS under Cooch Behar Division, PHED | 5.72 | R 2544444 | 25/10/2024 | VCH/001828/2023-2024 |
362 | Coochbehar Division | BILL/00165/2024-2025 | 20/06/2024 | MESSRS A.B.G CONSTRUCTION | ORD/000466/2021-2022 | 1604/CD | 24/03/2022 | Providing FHTC 3rd Site Pump House Boundary Wall SSPost with soak pit Sinking 250mm X 200mm Big dia Tubewell & New UPVC/DI/GI Pipe line and other allied works (PART ¿B) at SITAI ZONE ¿ I I PWSS under Cooch Behar Division, PHED | 8.44 | BP-118 | 04/07/2024 | VCH/000089/2024-2025 |
363 | Coochbehar Division | BILL/00184/2022-2023 | 30/12/2022 | SANKAR BANIK | ORD/000317/2022-2023 | 926/CD | 26/09/2022 | Providing F.H.T.C & Restoration of damage Pipeline allied Work at GOPALPUR Water Supply Scheme P.H.E Dte | 4.33 | w 5555 | 25/10/2024 | VCH/001722/2022-2023 |
364 | Coochbehar Division | BILL/00236/2024-2025 | 16/07/2024 | BIJOY ROY | ORD/000092/2023-2024 | 627/CD | 12/07/2023 | Execution of different works related to NENDAPAR PWSS under JAL JEEVAN MISSION | 40.07 | BP-192 | 25/07/2024 | VCH/000163/2024-2025 |
365 | Coochbehar Division | BILL/00250/2024-2025 | 25/07/2024 | KISHORE BOSE | ORD/000344/2023-2024 | 1328/CD | 24/11/2023 | Execution of different works related to KISMAT MOKARARI PWSS under JAL JEEVAN MISSION | 21.09 | BP-202 | 31/07/2024 | VCH/000115/2024-2025 |
366 | Coochbehar Division | BILL/00259/2024-2025 | 01/08/2024 | BHAGWATI BHUJEL | ORD/000783/2023-2024 | 664/CD | 11/03/2024 | Execution of different works related to DEWANHAT LAB area under GHARGHARIA PWSS under JAL JEEVAN MISSION | 6.84 | BP-248 | 07/08/2024 | VCH/000240/2024-2025 |
367 | Coochbehar Division | BILL/00265/2024-2025 | 01/08/2024 | UTPAL CHAKRABORTY | ORD/000418/2023-2024 | 1473/CD | 20/12/2023 | Execution of different works related to BILSI PWSS under JAL JEEVAN MISSION | 24.32 | BP-240 | 07/08/2024 | VCH/000111/2024-2025 |
368 | Coochbehar Division | BILL/00274/2024-2025 | 02/08/2024 | ANUGRAH CONSTRUCTION PRIVATE LIMITED | ORD/000602/2022-2023 | 1791/CD | 02/03/2023 | Execution of different works related to DHANDHANIA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1238/1-5/NBC-1; Dt.: 02-03-23 | 66.47 | BP-250 | 09/08/2024 | VCH/000242/2024-2025 |
369 | Coochbehar Division | BILL/00402/2023-2024 | 14/08/2023 | SUBHAS CHANDRA ROY | ORD/000586/2022-2023 | 1671/CD | 13/02/2023 | Execution of different works related to BARA GOPALPUR PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1109/1-5/NBC-1; Dt.: 13-02-23 | 3.79 | w 2252 | 25/10/2024 | VCH/001838/2023-2024 |
370 | Coochbehar Division | BILL/00435/2024-2025 | 03/09/2024 | SHREE RANI SATI ENTERPRISE | ORD/000573/2022-2023 | 1684/CD | 13/02/2023 | Execution of different works related to CHARALJANI PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1115/1-5/NBC-1; Dt.: 13-02-23 | 58.43 | BP-361 | 12/09/2024 | VCH/000366/2024-2025 |
371 | Coochbehar Division | BILL/00437/2024-2025 | 03/09/2024 | TORSHA CONSTRUCTION | ORD/000575/2023-2024 | 596/CD | 11/03/2024 | Laying DI P/Line & other allied works related to KUCHNI P KHANDA PWSS under JAL JEEVAN MISSION | 54.42 | BP-354 | 10/09/2024 | VCH/000326/2024-2025 |
372 | Coochbehar Division | BILL/00447/2024-2025 | 03/09/2024 | M/S. NITYAGOPAL BANIK | ORD/000108/2023-2024 | 661/CD | 14/07/2023 | Execution of different works related to SHIKARPUR PIPED WATER SUPPLY SCHEME. | 120.00 | BP-364 | 10/09/2024 | VCH/000367/2024-2025 |
373 | Coochbehar Division | BILL/00448/2024-2025 | 03/09/2024 | NABIN DEBNATH | ORD/000548/2022-2023 | 1682/CD | 13/02/2023 | Execution of different works related to BHANGAMORE PWSS under JAL JEEVAN MISSION | 15.24 | BP-368 | 10/09/2024 | VCH/000346/2024-2025 |
374 | Coochbehar Division | BILL/00322/2024-2025 | 13/08/2024 | UDAY CHAKI | ORD/000041/2024-2025 | 1149/CD | 14/06/2024 | Execution of different works related to NAGAR CHANGRABANDHA PWSS under JAL JEEVAN MISSION | 7.16 | BP-291 | 21/08/2024 | VCH/000272/2024-2025 |
375 | Coochbehar Division | BILL/00337/2024-2025 | 30/08/2024 | NARAYAN CHANDRA BANIK | ORD/000048/2023-2024 | 409/CD | 23/05/2023 | Execution of different works related to CHHAGALBER PWSS under JAL JEEVAN MISSION | 2.50 | BP-340 | 04/09/2024 | VCH/000319/2024-2025 |
376 | Coochbehar Division | BILL/00353/2024-2025 | 19/08/2024 | DAS ENTERPRISE | ORD/000402/2022-2023 | 1166/CD | 10/11/2022 | Providing FHTC & Laying of Pipe line Repairing of Boundary wall, Pumphouse & other allied works at ANDARAN NIZTARAF PWSS Under Cooch Behar division P.H.E.Dte. (Part-B) | 6.80 | BP-333 | 03/09/2024 | VCH/000209/2024-2025 |
377 | Coochbehar Division | BILL/00600/2023-2024 | 15/09/2023 | PALLAB BHAWAL | ORD/000572/2022-2023 | 1690/CD | 13/02/2023 | Execution of different works related to UCHALPUKURI ZONE - II PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1121/1-5/NBC-1; Dt.: 13-02-23 | 5.42 | W 25444 | 25/10/2024 | VCH/001825/2023-2024 |
378 | Coochbehar Division | BILL/00786/2024-2025 | 23/09/2024 | SUBHAS CHANDRA ROY | ORD/000290/2023-2024 | 11/CD | 05/04/2023 | Execution of different works related to AUG. of Kurshamari PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 11/1-5/NBC-1; Dt.: 05-04-23 | 32.80 | BP-419 | 26/09/2024 | VCH/000357/2024-2025 |
379 | Coochbehar Division | BILL/00788/2024-2025 | 24/09/2024 | ABHIJIT KUMAR DAS | ORD/000352/2023-2024 | 1336/CD | 24/11/2023 | Execution of different works related to TANAPAKHA PWSS under JAL JEEVAN MISSION | 13.51 | BP-427 | 27/09/2024 | VCH/000360/2024-2025 |
380 | Coochbehar Division | BILL/00960/2024-2025 | 04/10/2024 | DAS ENTERPRISE | ORD/000490/2023-2024 | 292/CD | 09/02/2024 | Execution of different works related to DAKSHIN BAJEJAMA KHASBAS PWSS under JAL JEEVAN MISSION | 11.43 | c 125455 | 21/11/2024 | VCH/000452/2024-2025 |
381 | Coochbehar Division | BILL/00833/2024-2025 | 27/09/2024 | PALLAB BHAWAL | ORD/000572/2022-2023 | 1690/CD | 13/02/2023 | Execution of different works related to UCHALPUKURI ZONE - II PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1121/1-5/NBC-1; Dt.: 13-02-23 | 162.21 | wr-110 | 14/11/2024 | VCH/000417/2024-2025 |
382 | Coochbehar Division | BILL/00009/2024-2025 | 09/05/2024 | Z STAR COMMOTRADE PVT LTD | ORD/000106/2023-2024 | 720/CD | 25/07/2023 | Execution of different works related to BHOGRAMGURI PWSS under JAL JEEVAN MISSION | 88.92 | BP-16 | 15/05/2024 | VCH/000001/2024-2025 |
383 | Coochbehar Division | BILL/00012/2024-2025 | 09/05/2024 | AMBITIOUS ENTERPRISE | ORD/000566/2022-2023 | 1689/CD | 13/02/2023 | Execution of different works related to BHOGDABARI PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1112/1-5/NBC-1; Dt.: 13-02-23 | 14.11 | BP-19 | 15/05/2024 | VCH/000007/2024-2025 |
384 | Coochbehar Division | BILL/00021/2024-2025 | 09/05/2024 | ANUGRAH CONSTRUCTION PRIVATE LIMITED | ORD/000602/2022-2023 | 1791/CD | 02/03/2023 | Execution of different works related to DHANDHANIA PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1238/1-5/NBC-1; Dt.: 02-03-23 | 5.26 | BP--37 | 29/05/2024 | VCH/000039/2024-2025 |
385 | Coochbehar Division | BILL/00023/2024-2025 | 09/05/2024 | S. DUTTA | ORD/000391/2022-2023 | 1035/CD | 29/09/2022 | Providing FHTC and Laying of Pipe line of PANIGRAM ZONE ¿ I PWSS under JAL JEEVAN MISSION (PART ¿D) | 13.90 | BP-32 | 29/05/2024 | VCH/000016/2024-2025 |
386 | Coochbehar Division | BILL/00049/2024-2025 | 16/05/2024 | MATARA CONSTRUCTION CO. | ORD/000578/2022-2023 | 1768/CD | 02/03/2023 | Execution of different works related to JARABARI PRATHAM KHANDA PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1209/1-5/NBC-1; Dt.: 01-03-23 | 91.99 | BP-33 | 29/05/2024 | VCH/000036/2024-2025 |
387 | Coochbehar Division | BILL/00059/2024-2025 | 16/05/2024 | BIPASHA MAHANTA BANIK | ORD/000534/2023-2024 | 372/CD | 27/02/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Sitai, Dinhata(P) Water Supply Scheme under Cooch Behar Division, PHED. | 0.98 | BP-48 | 29/05/2024 | VCH/000050/2024-2025 |
388 | Coochbehar Division | BILL/00110/2024-2025 | 11/06/2024 | PALLAB BHAWAL | ORD/000423/2021-2022 | 1521/CD | 15/03/2022 | Repairing of 250 Cum OHR as per Departmental Design & drawing, Providing F.H.T.C New laying of UPVC/DI Pipe Line & other allied work at BANESWAR Zone-I PWSS under Cooch Behar Division , P.H.E Dte. (PART-A) | 41.65 | BP-92 | 15/06/2024 | VCH/000035/2024-2025 |
389 | Coochbehar Division | BILL/00112/2024-2025 | 11/06/2024 | SUBHAS CHANDRA ROY | ORD/000586/2022-2023 | 1671/CD | 13/02/2023 | Execution of different works related to BARA GOPALPUR PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1109/1-5/NBC-1; Dt.: 13-02-23 | 102.75 | BP-96 | 15/06/2024 | VCH/000196/2024-2025 |
390 | Coochbehar Division | BILL/00114/2024-2025 | 11/06/2024 | M/S. MANDAL CONSTRUCTION | ORD/000577/2023-2024 | 617/CD | 11/03/2024 | Laying DI P/Line & other allied works related to CHAKCHAKA PWSS under JAL JEEVAN MISSION | 14.41 | BP-95 | 15/06/2024 | VCH/000093/2024-2025 |
391 | Coochbehar Division | BILL/00124/2024-2025 | 14/06/2024 | MATARA CONSTRUCTION CO. | ORD/000506/2023-2024 | 303/CD | 09/02/2024 | Execution of different works related to RAJPUR PWSS under JAL JEEVAN MISSION | 7.73 | BP-101 | 20/06/2024 | VCH/000197/2024-2025 |
392 | Coochbehar Division | BILL/00135/2024-2025 | 15/06/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000107/2023-2024 | 660/CD | 14/07/2023 | Execution of different works related to PATCHHARA ZONE 1 PWSS under JAL JEEVAN MISSION | 15.55 | BP-114 | 25/06/2024 | VCH/000094/2024-2025 |
393 | Coochbehar Division | BILL/00198/2024-2025 | 27/06/2024 | MATRI ENTERPRISEES | ORD/000815/2022-2023 | 1997 | 28/03/2023 | Execution of different works related to AUG. of HARINCHAOWRA PWSS under JAL JEEVAN MISSION | 58.04 | BP-141 | 01/07/2024 | VCH/000135/2024-2025 |
394 | Coochbehar Division | BILL/00217/2024-2025 | 08/07/2024 | LIMRA SOCIAL WELFARE SOCIETY | ORD/000508/2023-2024 | 305/CD | 09/02/2024 | Wall Painting, Designing, Making & erecting of DB using logo tagline for Cooch Behar districts under Jal Jeevan Mission (JJM) Support Activities Part C | 24.87 | BP-168 | 15/07/2024 | VCH/000151/2024-2025 |
395 | Coochbehar Division | BILL/00227/2024-2025 | 11/07/2024 | MS SSB CONSTRUCTION CO | ORD/000401/2022-2023 | 1165/CD | 10/11/2022 | Providing FHTC & Laying of Pipe line Construction of Boundary wall, Pumphouse at 3RD site & other allied works at ANDARAN NIZTARAF PWSS Under Cooch Behar division P.H.E.Dte. (Part-A) | 41.70 | BP-182 | 17/07/2024 | VCH/000095/2024-2025 |
396 | Coochbehar Division | BILL/00230/2024-2025 | 11/07/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000457/2022-2023 | 1508/CD | 19/01/2023 | Execution of different works related to NAHARHATBANDAR PWSS under JAL JEEVAN MISSION SE NBC1/PHED A. O.: 977/1-5/NBC-1; DT: 19-01-23 | 70.47 | BP-184 | 17/07/2024 | VCH/000092/2024-2025 |
397 | Coochbehar Division | BILL/00283/2024-2025 | 02/08/2024 | SENGUPTA ENTERPRISE | ORD/000620/2023-2024 | 678/CD | 11/03/2024 | Uploading charges of (https://ejalshakti.gov.in/imisreports/IMISReportLogin.aspx) related to FHTC under Jal Jeevan Mission in presence of JJM Login authority under Cooch Behar Division, PHE Dte. (Part-E) Under CHANDAN CHOWRA PIPED WATER SUPPLY SCHEME. | 0.97 | BP-251 | 09/08/2024 | VCH/000243/2024-2025 |
398 | Coochbehar Division | BILL/00294/2024-2025 | 03/08/2024 | BIPASHA MAHANTA BANIK | ORD/000332/2024-2025 | 850/CD | 12/04/2024 | Extension work for Collection of House Hold Details at Prescribed Format through Mobile App / Hard Copy including Geo-Reference of Dinhata-II, DUDDER KUTHIDEWANBAS PIPED WATER SUPPLY SCHEME under Cooch Behar Division, PHED. | 0.98 | BP-273 | 14/08/2024 | VCH/000140/2024-2025 |
399 | Coochbehar Division | BILL/00298/2022-2023 | 17/02/2023 | AUXILIARY TUBEWELL DRILLERS | ORD/000507/2021-2022 | 1455/CD | 10/03/2022 | Sinking of 250mm x 200 mm Big dia. Tube well with UPVC Pipes & Strainer at Different Location ofANDARAN FULBARI ZONE I & II PWSS under Cooch Behar Division PHE Dte | 10.72 | R 21455 | 25/10/2024 | VCH/001726/2022-2023 |
400 | Coochbehar Division | BILL/00306/2024-2025 | 08/08/2024 | SANJAY MANDAL | ORD/000421/2023-2024 | 1477/CD | 20/12/2023 | Execution of different works related to CHHITRIBARI PWSS under JAL JEEVAN MISSION | 15.79 | BP-286 | 14/08/2024 | VCH/000267/2024-2025 |
401 | Coochbehar Division | BILL/00378/2024-2025 | 21/08/2024 | SSPR VALVE MANUFACTURING PVT. LTD. | ORD/000554/2023-2024 | 636/CD | 11/03/2024 | Execution of different works related to BHOGRAMGURI PWSS under JAL JEEVAN MISSION | 28.92 | BP-326 | 03/09/2024 | VCH/000312/2024-2025 |
402 | Coochbehar Division | BILL/00390/2024-2025 | 31/08/2024 | SUSHANTA SAHA | ORD/000060/2021-2022 | 264/CD | 06/08/2021 | Pipe Line in the Command area incl. Providing House connection at CHARALJANI PWSS under Cooch Behar Division. PHE Dte. PART - B | 19.16 | BP-339 | 04/09/2024 | VCH/000318/2024-2025 |
403 | Coochbehar Division | BILL/00397/2023-2024 | 14/08/2023 | MANABENDRA DE | ORD/000493/2022-2023 | 1558/CD | 24/01/2023 | Execution of different works related to KUCHLIBARI Z 2 PWSS under JAL JEEVAN MISSIONSE,NBC-1,PHED A.O. No.: 1013/1-5/NBC-1; Dt.: 24-01-23 | 15.00 | wr-110 | 25/10/2024 | VCH/001995/2023-2024 |
404 | Coochbehar Division | BILL/00471/2024-2025 | 11/09/2024 | M/S VINOD KUMAR JAIN | ORD/000038/2024-2025 | 1146/CD | 14/06/2024 | Execution of different works related to ATPUKURI PWSS under JAL JEEVAN MISSION Z2 A | 20.71 | BP-388 | 20/09/2024 | VCH/000340/2024-2025 |
405 | Coochbehar Division | BILL/00559/2024-2025 | 13/09/2024 | SWAPAN KR.SARKAR | ORD/000341/2023-2024 | 1325/CD | 24/11/2023 | Execution of different works related to (within TAKAGACH area) CHAKCHAKA ZONE II PWSS under JAL JEEVAN MISSION | 31.56 | BP-394 | 20/09/2024 | VCH/000352/2024-2025 |
406 | Coochbehar Division | BILL/00866/2023-2024 | 13/10/2023 | NABIN DEBNATH | ORD/000425/2021-2022 | 1475/CD | 10/03/2022 | Construction of 300 cum OHR Providing FHTC New Pipe line & other allied works (PART ¿A) at ANDARAN FULBARI ZONE-II PWSS under Cooch Behar Division, PHED | 7.00 | w 12455 | 25/10/2024 | VCH/001862/2023-2024 |
407 | Coochbehar Division | BILL/01956/2023-2024 | 31/03/2024 | SAIMONS CO- OPARATIVE LAB CONT & CONSTN SOCY LTD | ORD/000336/2023-2024 | 1320/CD | 24/11/2023 | Execution of different works related to KHARIKABARI PWSS under JAL JEEVAN MISSION | 41.07 | BP-4 | 03/05/2024 | VCH/001818/2023-2024 |
408 | Coochbehar Division | BILL/00104/2024-2025 | 07/06/2024 | UNIBRO INFRASERV PRIVATE LIMITED | ORD/000002/2023-2024 | 51/CD | 17/04/2023 | Execution of different works related to HEMKUMARI ZONE 2 PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 31/1-5/NBC-1; Dt.: 13-04-23 | 99.74 | BP-80 | 12/06/2024 | VCH/000116/2024-2025 |
409 | Coochbehar Division | BILL/00105/2024-2025 | 07/06/2024 | SUMI ENTERPRISE | ORD/000113/2023-2024 | 666/CD | 14/07/2023 | Execution of different works related to AUG. of CHAKCHAKA ZONE-I PWSS under JAL JEEVAN MISSION | 139.15 | BP-79 | 12/06/2024 | VCH/000191/2024-2025 |
410 | Coochbehar Division | BILL/00107/2024-2025 | 07/06/2024 | S & P ENTERPRISE | ORD/000593/2022-2023 | 1963/CD | 24/03/2023 | Execution of different works related to ABUAR PATHAR PWSS under JAL JEEVAN MISSION SE,NBC-1,PHED A.O. No.: 1335/1-5/NBC-1; Dt.: 24-03-23 | 39.86 | BP-86 | 12/06/2024 | VCH/000193/2024-2025 |
411 | Coochbehar Division | BILL/00162/2024-2025 | 19/06/2024 | ORIENTAL CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. | ORD/000334/2022-2023 | 983/CD | 29/09/2022 | Providing FHTC Repairing of Pump House & B/Wall and Laying of Pipe line at HW Site of PURBA DHULIA BALDIHATI PWSS under JAL JEEVAN MISSION (PART ?R) | 8.77 | BP-116 | 25/06/2024 | VCH/000061/2024-2025 |
412 | Coochbehar Division | BILL/00171/2024-2025 | 22/06/2024 | JAI BHARAT COMERCIAL CORPORATION | ORD/000383/2022-2023 | 802/CD | 09/09/2022 | Providing FHTC and Laying of Pipe line & Construction of Pump house HW Site of PANIGRAM ZONE - II PWSS under JAL JEEVAN MISSION (PART ¿Y) | 8.52 | BP-117 | 28/06/2024 | VCH/000201/2024-2025 |
413 | Coochbehar Division | BILL/00175/2024-2025 | 22/06/2024 | GHOSH AND SAHA CONSTRUCTION | ORD/000104/2023-2024 | 718/CD | 25/07/2023 | Execution of different works related to AUG. of JAIGIR CHILAKHANA PWSS under JAL JEEVAN MISSION | 1.17 | BP-124 | 28/06/2024 | VCH/000101/2024-2025 |
414 | Coochbehar Division | BILL/00189/2024-2025 | 26/06/2024 | SHRI ANNAPURNA DISTRIBUTORS | ORD/000112/2023-2024 | 665/CD | 14/07/2023 | Execution of different works related to AUG. of NAKKATIGACHHI PWSS under JAL JEEVAN MISSION | 54.11 | BP-139 | 01/07/2024 | VCH/000134/2024-2025 |
415 | Coochbehar Division | BILL/00194/2024-2025 | 27/06/2024 | MA MAHAMAYA UNP.CO-OP LABOUR CONTRACT AND CONST SOCIETY LTD. | ORD/000439/2022-2023 | 1416/CD | 29/12/2022 | Execution of different works related to SHIKARPUR P2 PWSS under JAL JEEVAN MISSION | 3.68 | BP-138 | 01/07/2024 | VCH/000117/2024-2025 |
416 | Coochbehar Division | BILL/00238/2024-2025 | 16/07/2024 | MODERN UN EMP CO OP LAB CONT AND CONST SOCIETY LTD | ORD/000733/2022-2023 | 1737/CD | 21/02/2023 | Providing FHTC & Construction of Pumphouse at HWSite and laying of Pipe line and other allied works at ATPUKURI ZONE - I PWSS Under Cooch Behar division P.H.E.Dte.(Part-F) | 16.95 | BP-193 | 25/07/2024 | VCH/000109/2024-2025 |
417 | Coochbehar Division | BILL/00253/2024-2025 | 01/08/2024 | KAJAL KUMAR DE | ORD/000433/2023-2024 | 363/CD | 23/05/2023 | Execution of different works related to KHARIJA KHAWARDARA PWSS under JAL JEEVAN MISSION | 125.21 | BP-239 | 07/08/2024 | VCH/000234/2024-2025 |
418 | Coochbehar Division | BILL/00261/2024-2025 | 01/08/2024 | PATLAKHOWA UN EMP CO OP LAB CONT AND CONST SOC LTD | ORD/000040/2023-2024 | 466/CD | 02/06/2023 | Execution of different works related to Aug. of CHHOTA GADAIKHORA PWSS under JAL JEEVAN MISSION | 79.70 | BP-246 | 07/08/2024 | VCH/000124/2024-2025 |
419 | Coochbehar Division | BILL/00268/2024-2025 | 02/08/2024 | MOTI INDUSTRIES | ORD/000276/2023-2024 | 1043/CD | 22/09/2023 | Name of Work: Execution of different works related Chamta & other mouzas at Aug. of SITAI PWSS under JAL JEEVAN MISSION PART X | 46.02 | BP-260 | 09/08/2024 | VCH/000206/2024-2025 |
420 | Coochbehar Division | BILL/00324/2024-2025 | 13/08/2024 | SHRI ANNAPURNA DISTRIBUTORS | ORD/000426/2023-2024 | 1482/CD | 20/12/2023 | Execution of different works related to PRAN MAJUMDER PWSS under JAL JEEVAN MISSION | 31.57 | BP-292 | 21/08/2024 | VCH/000273/2024-2025 |
421 | Coochbehar Division | BILL/00327/2024-2025 | 14/08/2024 | RAHAMAN ENTERPRISE | ORD/000351/2023-2024 | 1335/CD | 24/11/2023 | Execution of different works related to GURIAHATI PWSS under JAL JEEVAN MISSION | 40.61 | BP-293 | 21/08/2024 | VCH/000274/2024-2025 |
422 | Coochbehar Division | BILL/00328/2024-2025 | 14/08/2024 | KARTICK CH SEAL | ORD/000372/2023-2024 | 1357/CD | 05/12/2023 | Execution of different works related to RAMPUR PWSS under JAL JEEVAN MISSION | 63.27 | BP-334 | 03/09/2024 | VCH/000316/2024-2025 |
423 | Coochbehar Division | BILL/00347/2024-2025 | 17/08/2024 | BIJOY ROY | ORD/000549/2022-2023 | 1683/CD | 13/02/2023 | Execution of different works related to CHONGERKHATA KHAGRIBARI PWSS under JAL JEEVANMISSION | 28.20 | BP-343 | 04/09/2024 | VCH/000211/2024-2025 |
424 | Coochbehar Division | BILL/00357/2024-2025 | 20/08/2024 | EXECUTIVE ENGINEER PWD COOCHBEHAR DIVISION | null | 1488/WE | 07/08/2024 | REPARING AND RESTORATION OF DAMAGED FLANK DUE TO PHED PIPE LINE LAYING ALONGSIDE KHARUBHAJ KHOCHABARI ROAD ADJACENT NAJIRGANJ VR ( IN stretches UNDER PWD DINHATA SUB DIVISION UNDER PWD Cooch Behar division in the DISTRICT OF COOCHBEHAR | 4.38 | BP-305 | 31/08/2024 | VCH/000282/2024-2025 |
425 | Coochbehar Division | BILL/00568/2024-2025 | 14/09/2024 | SENGUPTA ENTERPRISE | ORD/000512/2023-2024 | 310/CD | 09/02/2024 | Execution of different works related to LAWCHAPRA PWSS under JAL JEEVAN MISSION PART C | 15.48 | BP-378 | 20/09/2024 | VCH/000353/2024-2025 |
426 | Coochbehar Division | BILL/00602/2024-2025 | 16/09/2024 | M/S KARNATAKA CONSTRUCTION COMPANY | ORD/000472/2023-2024 | 274/CD | 09/02/2024 | Execution of different works related to CHHOTO KESARIBARI PWSS under JAL JEEVAN MISSION | 54.59 | BP-420 | 26/09/2024 | VCH/000380/2024-2025 |
427 | Coochbehar Division | BILL/00604/2024-2025 | 16/09/2024 | MATARA CONSTRUCTION CO. | ORD/000784/2023-2024 | 665/CD | 11/03/2024 | Execution of different works related to CHAKIARCHHARA PWSS under JAL JEEVAN MISSION | 8.94 | BP-392 | 20/09/2024 | VCH/000356/2024-2025 |
428 | Coochbehar Division | BILL/00783/2024-2025 | 23/09/2024 | MS BIDYUT SARKAR | ORD/000571/2023-2024 | 613/CD | 11/03/2024 | Laying DI P/Line & other allied works related to BHORAM PWSS under JAL JEEVAN MISSION | 66.57 | BP-425 | 26/09/2024 | VCH/000389/2024-2025 |
429 | Coochbehar Division | BILL/00789/2024-2025 | 24/09/2024 | DULAL MAJUMDER | ORD/000417/2023-2024 | 1472/CD | 20/12/2023 | Execution of different works related to ALOKJHARI PWSS under JAL JEEVAN MISSION | 21.98 | BP-428 | 27/09/2024 | VCH/000391/2024-2025 |
430 | Coochbehar Division | BILL/00795/2024-2025 | 25/09/2024 | HIRAK CONSTRUCTION | ORD/000414/2023-2024 | 499/CD | 14/07/2023 | Laying of Pipe Line between gap of different pin point site & other allied works under DINHATA (M) PWSS under Cooch Behar Division, PHE Dte. P2 | 4.99 | BP-430 | 27/09/2024 | VCH/000392/2024-2025 |
Total | 18,123.99 |