| Sl. No. | Division
Working Divisions
|
Bill Number | Bill Date
Date of Issuance of the Work Order as per PHED-MIS
|
Vendor Name
Vendor Appointed Against this Work Order as per PHED-MIS
|
System Order Number
System generated Order No. for the Work Order as per PHED-MIS
|
Memo Number
Memo no. for Work Order Provided by the Divisions as per PHED-MIS
|
Order Date
Date of Issuance of the Work Order as per PHED-MIS
|
work_name
Name of the Work as per the Issued Work Order
|
Bill Gross Amount | Voucher Number | Voucher Date | System Voucher Number |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 0 | 158.93 | |||||||||||
| 1 | Hooghly Division | BILL/01048/2024-2025 | 29/11/2024 | AMBIAN INFRASTRUCTURE | ORD/000292/2024-2025 | 928/Chan | 05/11/2024 | Making of 2 nos 1.8m x 1.45m x 2.1m KIOSK at Khordaapurbapur 1st T/W site & Kamarkundu (Zone-1) 1st T/W site under Chandannagar Sub-Division PHE Dte. | 0.93 | 01000214408 | 22/06/2026 | VCH/002703/2024-2025 |
| 2 | Hooghly Division | BILL/01360/2024-2025 | 25/02/2025 | BIMAL KUMAR HALDER | ORD/000152/2023-2024 | 1566/HUG | 29/05/2023 | SINHAL Piped Water Supply Scheme with Sinking of tube-well, LDS, Rising Main, FHTC & construction of switch-room & boundary wall at Proposed TW site, under Chandannagar Sub-Division of Hooghly Division P.H.E Dte. Block Singur, District:- Hooghly [NEW SCHE | 62.90 | 01000214384 | 22/06/2026 | VCH/002705/2024-2025 |
| 3 | Hooghly Division | BILL/00359/2025-2026 | 25/06/2025 | AYUSH ENTERPRISE | ORD/000553/2023-2024 | 3182/HUG | 30/10/2023 | GOPALDAHA Piped Water Supply Scheme with Sinking of tube-well, LDS, Rising Main, FHTC & construction of switch-room & boundary wall at Proposed TW site under Arambagh Sub-Division of Hooghly Division P.H.E Dte. Block Arambagh, District:- Hooghly [NEW SCHE | 47.24 | 01000214320 | 22/06/2026 | VCH/003192/2025-2026 |
| 4 | Hooghly Division | BILL/01015/2024-2025 | 21/11/2024 | KALPATARU ENTERPRISE | ORD/000065/2024-2025 | 2506/HUG | 03/07/2024 | Sinking of Additional tubewell with Construction of switch-room & boundary wall, Laying Rising Main at Proposed TW site at kharda-apurbapur Water Supply Scheme under Chandannagar Sub-Division of Hooghly Division P.H.E Dte.Block Singur, District:- Hooghl | 14.00 | 01000214392 | 22/06/2026 | VCH/002704/2024-2025 |
| 5 | Hooghly Division | BILL/00132/2025-2026 | 08/05/2025 | UNIQUE AGENCY | ORD/000447/2024-2025 | 4084/HUG | 19/12/2024 | Repair and Renovation Works of R.C.C. Elevated Reservoir, Boundary Wall, Switch Room of GOURHATI PWSS under Arambagh Sub-Division of Hooghly Division, P.H.E. Dte. | 11.23 | 01000239436 | 27/07/2026 | VCH/003194/2025-2026 |
| 6 | Hooghly Division | BILL/00415/2025-2026 | 15/07/2025 | TAPAS ADHYA | ORD/000748/2023-2024 | 381/HUG | 08/02/2024 | Sinking of tube-well, Rising Main, construction of switch-room & boundary wall at Rajhat Uttar Proposed TW site, under Chinsurah Sub-Division of Hooghly Division P.H.E Dte. Block Polba-Dadpur, District:- Hooghly | 11.20 | 01000236973 | 24/07/2026 | VCH/003193/2025-2026 |
| 7 | Hooghly Division | BILL/00754/2026-2027 | 03/08/2026 | SATYA NARAYAN BISWAS | ORD/000180/2023-2024 | 1686/HUG | 08/06/2023 | KHORDAAPURBAPUR Piped Water Supply Scheme with Sinking of tube-well, LDS, Rising Main, FHTC & construction of switch-room & boundary wall at Proposed TW site, under Chandannagar Sub-Division of Hooghly Division P.H.E Dte. Block Singur, District:- Hooghly | 11.43 | 01000258294 | 10/08/2026 | VCH/000894/2026-2027 |
| Total | 158.93 | |||||||||||