Sl. No. | Division
Working Divisions
|
Bill Number | Bill Date
Date of Issuance of the Work Order as per PHED-MIS
|
Vendor Name
Vendor Appointed Against this Work Order as per PHED-MIS
|
System Order Number
System generated Order No. for the Work Order as per PHED-MIS
|
Memo Number
Memo no. for Work Order Provided by the Divisions as per PHED-MIS
|
Order Date
Date of Issuance of the Work Order as per PHED-MIS
|
work_name
Name of the Work as per the Issued Work Order
|
Bill Gross Amount | Voucher Number | Voucher Date | System Voucher Number |
---|---|---|---|---|---|---|---|---|---|---|---|---|
0 | 13,680.08 | |||||||||||
1 | Purulia Division | BILL/00410/2024-2025 | 04/07/2024 | CHANCHAL MISHRA | ORD/001460/2023-2024 | 1776/PD | 08/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewellat OHR Site of Zone - X of Kashipur Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Division | 16.07 | BP-2024-25-223 | 10/07/2024 | VCH/000252/2024-2025 |
2 | Purulia Division | BILL/00415/2024-2025 | 04/07/2024 | MANATOSH SINGH | ORD/000393/2021-2022 | 232/PD | 09/02/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM) and JAL SAPNA at different habitation and extention of distribution pipe line for Augmentation of Balarampur (Zone-II) W/S Scheme of Purulia Sadar Sub_Divisi | 13.04 | BP-2024-25-236 | 11/07/2024 | VCH/000301/2024-2025 |
3 | Purulia Division | BILL/00490/2024-2025 | 29/07/2024 | SUDHANSHU OJHA | ORD/001218/2022-2023 | 506/PD | 31/03/2023 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at Namo Pindra Village of Pindra G.P. under command area of Bongabari Water Supply Scheme at Purulia-II Block under Purulia Sadar Sub-Division | 3.37 | BP-2024-25-278 | 02/08/2024 | VCH/000404/2024-2025 |
4 | Purulia Division | BILL/00522/2024-2025 | 05/08/2024 | PRIYATOSH MUKHERJEE | ORD/001213/2022-2023 | 502/PD | 31/03/2023 | Laying of Loop Pipe Line for distribution System under command area Zone-II at different habitation For Providing Functional Household Tap Connection (FHTC) in connection under Jal Jeevan Mission (JJM and JAL SAPNA) of Manbazar II Block (part) Wa | 35.35 | BP-2024-25-297 | 12/08/2024 | VCH/000394/2024-2025 |
5 | Purulia Division | BILL/00536/2024-2025 | 09/08/2024 | PRASENJIT BASAK | ORD/001329/2022-2023 | 1050_PD | 08/07/2022 | Water supply Tap Connection Arrangement for 20 nos. AWC within Jhalda-I, Arsha & Bandwan Block (Part-C) of Purulia District under Purulia Division, PHE Dte. | 70.38 | BP-2024-25-317 | 16/08/2024 | VCH/000390/2024-2025 |
6 | Purulia Division | BILL/00681/2024-2025 | 05/09/2024 | JAYANTA KUMAR MONDAL | ORD/000903/2023-2024 | 1573/PD | 30/10/2023 | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the | 24.76 | BP-2024-25-362 | 12/09/2024 | VCH/000477/2024-2025 |
7 | Purulia Division | BILL/00695/2024-2025 | 06/09/2024 | SADHAN GORAIN | ORD/000737/2022-2023 | 1477/PD | 20/09/2022 | Repairing and renovation of the Over Head reservoir (OHR) of 250 m3 Capacity, Staging Height 20 mtr. of Sindri-Chasmore W/S Scheme under Purulia Sadar Sub-Division, Purulia Division, P.H.E. Dte. | 11.80 | BP-2024-25-360 | 12/09/2024 | VCH/000475/2024-2025 |
8 | Purulia Division | BILL/00788/2024-2025 | 26/09/2024 | SIKHA ENTERPRISES | ORD/000118/2024-2025 | 891/PD | 07/05/2024 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM) and JAL SAPNA at different habitation and extention of distribution pipe line of Balarampur (Zone-II) W/S Scheme of Purulia SadarSub_Division under Purulia D | 10.72 | BP-2024-25-447 | 01/10/2024 | VCH/000585/2024-2025 |
9 | Purulia Division | BILL/00791/2024-2025 | 26/09/2024 | CHAIL CONSTRUCTION | ORD/000462/2024-2025 | 1521/PD | 27/08/2024 | Sinking of 1(One) nos tubewell at OHR Site of Zone - V of Raghunathpur-II Block under Northen Sector Scheme of Raghunathpur Sub-Division under Purulia Division, P.H.E. Dte. | 4.65 | BP-2024-25-445 | 29/09/2024 | VCH/000561/2024-2025 |
10 | Purulia Division | BILL/00800/2024-2025 | 26/09/2024 | SUDHANSHU OJHA | ORD/000920/2022-2023 | 1928/PD | 22/12/2022 | Repairing and Renovation of R.C.C. Old and New Elevated Reservoir including Pump House and other allied works under Kashipur W/S Scheme of Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 5.03 | BP-2024-25-442 | 29/09/2024 | VCH/000558/2024-2025 |
11 | Purulia Division | BILL/00823/2024-2025 | 28/09/2024 | SUBRATA SINGHADEO | ORD/001470/2023-2024 | 1783/PD | 08/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewellat OHR Site of Zone - I of Raghunathpur-I Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Div | 14.86 | BP-2024-25-483 | 05/10/2024 | VCH/000638/2024-2025 |
12 | Purulia Division | BILL/01624/2023-2024 | 24/01/2024 | M.K.KAYAL & ASSOCIATES | ORD/001033/2022-2023 | 236/PD | 17/02/2023 | Continuation work for Soil Investigation work for proposed 100 cubic meter capacity Over Head Reservour of Arsha W/S Scheme under Purulia Division P.H.E dte. | 1.04 | BP-2024-25-431 | 26/09/2024 | VCH/001894/2023-2024 |
13 | Purulia Division | BILL/00438/2024-2025 | 13/07/2024 | DEBAKI RANJAN SARKAR | ORD/000267/2023-2024 | 1041/PD | 04/08/2023 | Laying of Distribution pipe line including providing functional House Hold Tap Connection (FHTC), and other allied works of Raghunathpur Water Supply Scheme (Zone-VIA) at Raghunathpur-II Block of Raghunathpur Sub Division under Purulia Division, PHE Dte.( | 156.72 | BP-2024-25-256 | 22/07/2024 | VCH/000330/2024-2025 |
14 | Purulia Division | BILL/00440/2024-2025 | 13/07/2024 | KM ENTERPRISES | ORD/000043/2023-2024 | 659/PD | 17/05/2023 | Construction of Chlorine cum Switch Room & Guard Room with sanitary and plumbing arrangement with approach road, plinth protection, surface drain, Land development etc. complete at Joypur OHR Site, of Joypur W/S Scheme under Purulia Sadar Sub-Division, of | 10.85 | BP-2024-25-254 | 22/07/2024 | VCH/000328/2024-2025 |
15 | Purulia Division | BILL/00451/2024-2025 | 15/07/2024 | CHANDRA SHEKHAR KUNDU | ORD/003683/2023-2024 | 139/RNP | 12/03/2024 | Continuation Work Order for the Work of Hiring of Ambassador Car / Bolero for the Assistant Engineer, Raghunathpur Sub-Divn, PHE Dte. (w.e.f. 01/04/2024 to 31/08/2024) | 0.39 | BP-2024-25-326 | 21/08/2024 | VCH/000419/2024-2025 |
16 | Purulia Division | BILL/00457/2024-2025 | 15/07/2024 | SSPR VALVE MANUFACTURING PVT LTD | ORD/004362/2023-2024 | 56/PD | 09/01/2024 | Emergent Supply and delivery of sluice valve, MJ collar and all types of CIDF/DI specials for repairing and maintenance of pipe line under Kalyathol & Palaskhola Piped Water Supply Scheme Raghunathpur Sub-Division under Purulia Division, PHE Dte. [Part-B | 8.55 | BP-2024-25-258 | 22/07/2024 | VCH/000340/2024-2025 |
17 | Purulia Division | BILL/00540/2024-2025 | 09/08/2024 | EQUIPMENTS AND SPARES AGENCIES | ORD/000089/2022-2023 | 674/PD | 25/04/2022 | Water supply Tap Connection Arrangement for 40 nos School upto 200 Students, within Manbazar-I Block (Part-B) of Purulia District under Purulia Division, PHE Dte. | 37.51 | BP-2024-25-315 | 16/08/2024 | VCH/000388/2024-2025 |
18 | Purulia Division | BILL/00543/2024-2025 | 13/08/2024 | SAANVI CONSTRUCTION | ORD/001360/2023-2024 | 1729/PD | 04/12/2023 | Construction of Switch Room Cum Chlorin Room at Zone-VI B (Babugram) OHR Site of Raghunathpur W/S Scheme (German Project) within Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 4.78 | BP-2024-25-333 | 23/08/2024 | VCH/000426/2024-2025 |
19 | Purulia Division | BILL/00547/2024-2025 | 13/08/2024 | KANJILAL AND CO. | ORD/003528/2023-2024 | 354/PD | 04/03/2024 | Construction of Boundary wall & Sinking of T/well at Puncha ,Zone-III under Purulia W/S Scheme under Purulia Sadar Sub Division under Purulia Division, PHE Dte. | 2.10 | BP-2024-25-355 | 09/09/2024 | VCH/000469/2024-2025 |
20 | Purulia Division | BILL/00548/2024-2025 | 13/08/2024 | BOSE CONSTRUCTION | ORD/001043/2022-2023 | 275/PD | 27/02/2023 | Construction of RCC clear water reservoir (CWR) of capacity 500 Cum with other allied works at Boosting Station under Raghunathpur W/S Scheme (German Project) of Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 9.41 | BP-2024-25-323 | 21/08/2024 | VCH/000416/2024-2025 |
21 | Purulia Division | BILL/00551/2024-2025 | 13/08/2024 | ANUP KUMAR SAHA | ORD/000762/2023-2024 | 1368/PD | 14/09/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 150 CUM and staging height 20 mtr as per approved drawing (No: PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other a | 19.53 | BP-2024-25-321 | 21/08/2024 | VCH/000414/2024-2025 |
22 | Purulia Division | BILL/00552/2024-2025 | 13/08/2024 | BABA LOKNATH ENTERPRISE | ORD/000285/2023-2024 | 1143/PD | 17/08/2023 | Construction of boundary wall at Zone III H/W (OHR) site of Santuri block and sinking of 1 (one) no. Tubewell under surface Based Piped W/S Scheme Purulia Piped W/S Scheme (Northern Sector) under Raghunathpur Sub Division under Purulia Division PHE Dte. | 18.50 | BP-2024-25-332 | 22/08/2024 | VCH/000425/2024-2025 |
23 | Purulia Division | BILL/00566/2024-2025 | 22/08/2024 | DEBANJAN SEAL | ORD/001690/2023-2024 | 1866/PD | 21/12/2023 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM) and JAL SAPNA at different habitation and extention of distribution pipe line of Panradda (Zone-I) W/S Scheme of Purulia Sadar Sub_Division under Purulia Div | 10.21 | BP-2024-25-341 | 28/08/2024 | VCH/000447/2024-2025 |
24 | Purulia Division | BILL/00705/2024-2025 | 09/09/2024 | EFFLUENT & WATER TRETMENT ENGINEERS PVT LTD | ORD/000542/2023-2024 | 1339/PD | 08/09/2023 | Survey, Investigation, Planning, Designing (aesthetically), Construction and Commissioning of a Conventional WATER TREATMENT PLANT and rising main of capacity 650 KLD as per BIS/CPHEEO Manual consisting of all Civi | 49.63 | BP-2024-25-376 | 15/09/2024 | VCH/000497/2024-2025 |
25 | Purulia Division | BILL/00725/2024-2025 | 13/09/2024 | NANIGOPAL DEY | ORD/001456/2023-2024 | 1773/PD | 08/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewellat OHR Site of Zone - VII of Kashipur Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Divisio | 9.89 | BP-2024-25-390 | 18/09/2024 | VCH/000505/2024-2025 |
26 | Purulia Division | BILL/00580/2024-2025 | 23/08/2024 | BANERJEE CONSTRUCTION | ORD/001053/2022-2023 | 285/PD | 27/02/2023 | Laying of parallel distribution pipeline to provide FHTC at Supudih Mouza of Bandwan Water Supply Scheme under Purulia Division, PHE Dte . | 9.85 | BP-2024-25-346 | 29/08/2024 | VCH/000443/2024-2025 |
27 | Purulia Division | BILL/00754/2024-2025 | 19/09/2024 | WPIL LIMITED | ORD/001820/2023-2024 | 53/PD | 09/01/2024 | Design, Surveying,Engineering, Supplying and Construction, Erection, Installation, Testing,Commissioning, of Fixed type Intake Jetty with Pump house, Construction of Sub-station; Raw Water Raising Main Bank Protection, 40 MLD (Minimum) capacity Water Trea | 241.35 | BP-2024-25-405 | 22/09/2024 | VCH/000512/2024-2025 |
28 | Purulia Division | BILL/00755/2024-2025 | 21/09/2024 | MAHARSHI BANERJEE | ORD/000330/2024-2025 | 1355/PD | 25/07/2024 | Sinking of 1(One) nostubewell, laying DI pipe , filling and surface dressing at OHR Site of Zone - I of Kashipur Block under Keliathol-Palashkola W/S Scheme of Raghunathpur Sub-Division under Purulia Division, P.H.E. Dte. | 6.17 | BP-2024-25-415 | 25/09/2024 | VCH/000533/2024-2025 |
29 | Purulia Division | BILL/00767/2024-2025 | 21/09/2024 | M/S CHAKRABORTY CONSTRUCTION | ORD/000348/2024-2025 | 1378/PD | 25/07/2024 | Making bypass arrangement & other allied works at lagda OHR site of Lagda W/S Scheme under Purulia Division, PHE Dte. | 3.25 | BP-2024-25-413 | 25/09/2024 | VCH/000531/2024-2025 |
30 | Purulia Division | BILL/00786/2024-2025 | 26/09/2024 | SOUVIK MANDAL | ORD/001477/2023-2024 | 1788/PD | 08/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewellat OHR Site of Zone - VI of Raghunathpur-I Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Di | 16.46 | BP-2024-25-438 | 29/09/2024 | VCH/000554/2024-2025 |
31 | Purulia Division | BILL/00884/2024-2025 | 01/10/2024 | BHAGABAN DAS KUMAR | ORD/000228/2024-2025 | 1062/PD | 07/06/2024 | Laying DI Rising Main in new alignment from Pump house to OHR and making Inter Connection Arrangement with Distribution System for Joypur W/S Scheme of Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | 2.54 | BP-2024-25-492 | 05/10/2024 | VCH/000644/2024-2025 |
32 | Purulia Division | BILL/00892/2024-2025 | 01/10/2024 | JAYANTA KUMAR MONDAL | ORD/003978/2023-2024 | 523/PD | 16/03/2024 | Laying of HDPE pipe line (75mm & 63mm) and supplying of DI specials with additional Functional Household Tap Connection (FHTC) of distribution system (Zone-I) under Sarbari W/S scheme within Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 23.86 | BP-2024-25-489 | 05/10/2024 | VCH/000641/2024-2025 |
33 | Purulia Division | BILL/00904/2024-2025 | 02/10/2024 | ANUP KUMAR SAHA | ORD/000008/2019-2020 | 1087/PD | 29/05/2019 | Survey, investigation, design and Laying Clear Water Rising Main including 3 month's Trial run followed by 3 month's Operation and Maintenance for Panradda Piped Water Supply Scheme in Balarampur Block, Purulia Division, PHE Dte. | 72.77 | BP-2024-25-472 | 04/10/2024 | VCH/000628/2024-2025 |
34 | Purulia Division | BILL/00932/2024-2025 | 03/10/2024 | SADHAN GORAIN | ORD/000238/2024-2025 | 1086/PD | 07/06/2024 | Repering& renovation of 4 (Four) Nos I.E Plant under Raghunathpur W/S Scheme of Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 11.24 | BP-2024-25-499 | 06/10/2024 | VCH/000651/2024-2025 |
35 | Purulia Division | BILL/00933/2024-2025 | 03/10/2024 | BANERJEE CONSTRUCTION | ORD/001377/2023-2024 | 1734/PD | 04/12/2023 | Repairing of Boundary walls, Supplying and fitting of Mark -II Hand Pump along with concrete platform at the low yield Big Dia DTH Tubewell or Construction of concrete cover at the dry big dia DTH Tubewells sinked at various Schools & AWCs of . Barabazar | 3.76 | BP-2024-25-505 | 06/10/2024 | VCH/000656/2024-2025 |
36 | Purulia Division | BILL/00937/2024-2025 | 03/10/2024 | BISWAJIT MAJI | ORD/000438/2024-2025 | 1501/PD | 27/08/2024 | Sinking of 1(One) no 200 mm dia DTH rigbored tubewell at OHR Sites of Zone - II ( Fusrabad) of Para Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Division under Purulia Division, P.H | 5.38 | BP-2024-25-498 | 05/10/2024 | VCH/000582/2024-2025 |
37 | Purulia Division | BILL/00940/2024-2025 | 21/10/2024 | M/S SAYAK BHATTACHARYA | ORD/000061/2023-2024 | 1055/PD | 08/08/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - I of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part - B, Mouza - | 72.67 | BP-2024-25-517 | 23/10/2024 | VCH/000668/2024-2025 |
38 | Purulia Division | BILL/00945/2024-2025 | 28/10/2024 | GAJA ENGINEERING PRIVATE LIMITED | ORD/000897/2023-2024 | 1563/PD | 26/10/2023 | Design, Surveying, Engineering, Supplying, Construction, Erection, Installation, Testing And Commissioning Of Fixed Type Intake Jetty With Pump House, Construction Of Subs Stations; Raw Water Rising Main, Bank Protection, 158 MLD (Minimum) Capacity Water | 1,193.57 | BP-2024-25-519 | 29/10/2024 | VCH/000670/2024-2025 |
39 | Purulia Division | BILL/00946/2024-2025 | 30/10/2024 | ANUP KUMAR SAHA | ORD/000797/2023-2024 | 1430/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoir including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the p | 100.69 | BP-2024-25-525 | 13/11/2024 | VCH/000700/2024-2025 |
40 | Purulia Division | BILL/00320/2024-2025 | 11/06/2024 | BHAGABAN DAS KUMAR | ORD/000290/2021-2022 | 1592/PD | 17/12/2021 | Providing Functional Household Tap Connection (FHTC)(leftout household) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at Misirdih village of Chatu Hansa G.P. under command area of Satra Water Supply Scheme at Arsha Block under Purulia Sadar | 0.09 | BP-2024-25-225 | 10/07/2024 | VCH/000292/2024-2025 |
41 | Purulia Division | BILL/00403/2024-2025 | 25/06/2024 | SUJIT SAHANA | ORD/000838/2023-2024 | 1426/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoirs (Torch type with solid raft) of capacity 250 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other | 66.85 | BP-2024-25-218 | 10/07/2024 | VCH/000255/2024-2025 |
42 | Purulia Division | BILL/00407/2024-2025 | 04/07/2024 | BHUTNATH MISHRA | ORD/001462/2023-2024 | 1777/PD | 08/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewellat OHR Site of Zone - XI of Kashipur Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Division | 16.73 | BP-2024-25-227 | 11/07/2024 | VCH/000253/2024-2025 |
43 | Purulia Division | BILL/00414/2024-2025 | 04/07/2024 | RABIN CHANDRA CHAIL | ORD/001007/2022-2023 | 174/PD | 07/02/2023 | Laying Distribution pipe line including providing Functional Household Tap Connection (FHTC) and other allied works of Raghunathpur WaterSupply Scheme (Zone-I B) of Raghunathpur Sub Division under Purulia Division, PHE Dte. [Part-II | 10.73 | BP-2024-25-237 | 13/07/2024 | VCH/000302/2024-2025 |
44 | Purulia Division | BILL/00417/2024-2025 | 05/07/2024 | ASHOK KUMAR CHATTERJEE | ORD/000338/2021-2022 | 54/PD | 13/01/2022 | Construction of Switch Room Cum Chlorine Room of Lachhyara Pipe Water Supply Scheme of Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 4.70 | BP-2024-25-232 | 11/07/2024 | VCH/000299/2024-2025 |
45 | Purulia Division | BILL/00419/2024-2025 | 06/07/2024 | MOUSUMI BANERJEE | ORD/001350/2023-2024 | 1724/PD | 04/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewell at Zone - IV of Raghunathpur-II Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Division unde | 9.94 | BP-2024-25-229 | 10/07/2024 | VCH/000251/2024-2025 |
46 | Purulia Division | BILL/00487/2024-2025 | 29/07/2024 | CHATTERJEE CONSTRUCTION | ORD/000869/2023-2024 | 1282/PD | 31/08/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 300 CUM and staging height 20 mtr as per approved drawing ( No: PCI-I/OHR/3/2012)Including soil testing with other allied works for Zone-III of Santuri Bloc | 22.18 | BP-2024-25-279 | 02/08/2024 | VCH/000361/2024-2025 |
47 | Purulia Division | BILL/00494/2024-2025 | 29/07/2024 | PRINCE INDUSTRIES ( INDIA) | ORD/000922/2023-2024 | 1595/PD | 31/10/2023 | Construction and commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the | 66.85 | BP-2024-25-286 | 02/08/2024 | VCH/000367/2024-2025 |
48 | Purulia Division | BILL/00496/2024-2025 | 29/07/2024 | JAHANGIR ANSARI | ORD/003524/2023-2024 | 351/PD | 04/03/2024 | Construction of Boundary wall & Sinking of T/well at Jhalda-II,Zone-VI under Purulia W/S Scheme under Purulia Sadar Sub Division under Purulia Division, PHE Dte. | 18.94 | BP-2024-25-287 | 06/08/2024 | VCH/000366/2024-2025 |
49 | Purulia Division | BILL/00514/2024-2025 | 05/08/2024 | LEO CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. | ORD/000303/2022-2023 | 836/PD | 19/05/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at different habitation and extention of distribution pipe line for Augmentation of (Zone-I) Manbazar W/S Scheme of Purulia Sadar Sub_Division | 3.94 | BP-2024-25-296 | 12/08/2024 | VCH/000395/2024-2025 |
50 | Purulia Division | BILL/00519/2024-2025 | 05/08/2024 | MAHARSHI BANERJEE | ORD/000070/2023-2024 | 701/PD | 22/05/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire at Rudra Mouza, JL No.-10, Plot No.68 at OHR site under Keliyathole-Palashkola W/S Scheme (Zone-I) of Raghunathpur Sub-Division under Purulia Division, P.H.E. Dte. | 4.75 | BP-2024-25-303 | 13/08/2024 | VCH/000376/2024-2025 |
51 | Purulia Division | BILL/00523/2024-2025 | 07/08/2024 | ANUP KUMAR SAHA | ORD/000797/2023-2024 | 1430/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoir including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the p | 102.94 | BP-2024-25-289 | 09/08/2024 | VCH/000373/2024-2025 |
52 | Purulia Division | BILL/00537/2024-2025 | 09/08/2024 | BASANTA KUMAR SINGHADEO | ORD/000901/2022-2023 | 1893/PD | 15/12/2022 | Providing functional Household Tap Connection (FHTC) including Other allied works under Keliathole Palaskola W/S Scheme (Zone-I & III) under Raghunathpur Sub-Division, P.H.E. | 25.80 | BP-2024-25-307 | 14/08/2024 | VCH/000380/2024-2025 |
53 | Purulia Division | BILL/00538/2024-2025 | 09/08/2024 | ANGEL LABOUR CONTRACT & CONSTRUCTION CO OPERATIVE SOCIETY LTD | ORD/000047/2023-2024 | 671/PD | 17/05/2023 | Shifting and laying of HDPE distribution main pipeline from Burudi more to Dharampur village end due to widening of PWD road at Manbazar-2 block under Manbazar-II Water Supply Scheme Under Purulia Division ,PHE Dte | 24.46 | BP-2024-25-316 | 16/08/2024 | VCH/000389/2024-2025 |
54 | Purulia Division | BILL/00671/2024-2025 | 05/09/2024 | NANIGOPAL DEY | ORD/000987/2022-2023 | 99/PD | 20/01/2023 | Laying of Distribution System including supply of materials including providing House Hold Tap Connection (FHTC) and other allied works for Aug. of Dubra Water Supply Scheme within Raghunathpur Sub-Division under Purulia Division, PHE Dte. [Part-A] | 24.77 | BP-2024-25-363 | 12/09/2024 | VCH/000487/2024-2025 |
55 | Purulia Division | BILL/00676/2024-2025 | 05/09/2024 | KHITISH CHANDRA PATHAK | ORD/001195/2022-2023 | 467/PD | 28/03/2023 | New Sinking of 4 (Four) Nos 200 mm dia river bed vertical tubewell alongwith necessary 100 mm dia GI collecting line in connection with FHTC from River bed Tubewell to common manifold chamber at river bank (Damodar River) at Balitora under Balitora W/S | 2.65 | BP-2024-25-359 | 12/09/2024 | VCH/000474/2024-2025 |
56 | Purulia Division | BILL/00792/2024-2025 | 26/09/2024 | M/S KARUNAMOYEE CONSTRUCTION | ORD/000137/2024-2025 | 908/PD | 07/05/2024 | Connecting line with manifold at two nos Intake to Iron Elevation Plant of Para Piped Water Supply Scheme of Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 8.74 | BP-2024-25-446 | 29/09/2024 | VCH/000562/2024-2025 |
57 | Purulia Division | BILL/00804/2024-2025 | 27/09/2024 | KOUSHIK CHATTERJEE | ORD/000421/2021-2022 | 312/PD | 25/02/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at different habitation and extention of distribution pipe line under command area of Barabazar Water Supply Scheme of Barabazar Block under Pu | 58.74 | BP-2024-25-453 | 03/10/2024 | VCH/000590/2024-2025 |
58 | Purulia Division | BILL/00818/2024-2025 | 28/09/2024 | SUBHAS CHANDRA MAHATO | ORD/003533/2023-2024 | 357/PD | 04/03/2024 | Construction of Boundary wall & Sinking of T/well at Purulia-II ,Zone-IX under Purulia W/S Scheme under Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | 3.38 | BP-2024-25-466 | 04/10/2024 | VCH/000622/2024-2025 |
59 | Purulia Division | BILL/00829/2024-2025 | 28/09/2024 | PROGRESSIVE ENGINEERS CO OPERATIVE SOCIETY LIMITED | ORD/000874/2023-2024 | 1524/PD | 16/10/2023 | Construction of Intake well with laying of horizontal strainer including allied works at the bank of Kansai river at Namopindra village of Bongabari W/S scheme under Purulia Sadar Sub-Division, Purulia Division, PHE Dte. | 25.22 | BP-2024-25-477 | 05/10/2024 | VCH/000632/2024-2025 |
60 | Purulia Division | BILL/00845/2024-2025 | 28/09/2024 | ARUNALOY SCIENTIFIC HOUSE | ORD/000104/2023-2024 | 865/PD | 30/06/2023 | Operation & Maintenance and water testing in the laboratory at Santuri Sub-District Water testing Laboratory under RWS purulia Sub-Division PHE Dte. (w.e.f.01.07.2023 to 30.06.2024). | 2.03 | BP-2024-25-478 | 05/10/2024 | VCH/000633/2024-2025 |
61 | Purulia Division | BILL/00846/2024-2025 | 29/09/2024 | ARUNALOY SCIENTIFIC HOUSE | ORD/000097/2023-2024 | 859/PD | 30/06/2023 | Operation & Maintenance and water testing in the laboratory at Dubra Sub-District Laboratory under RWS purulia Sub-Division PHE Dte. . (w.e.f.01.07.2023 to 30.06.2024). | 2.01 | BP-2024-25-480 | 05/10/2024 | VCH/000635/2024-2025 |
62 | Purulia Division | BILL/00856/2024-2025 | 29/09/2024 | PURNA CHANDRA TEWARI | ORD/003454/2023-2024 | 323/PD | 01/03/2024 | Construction of Guard Room with sanitary and plumbing arrangment with approach road, plinth protection, surface drain etc. complete at Balarampur Zone-I for Augmentation of Balarampur W/S Scheme under Purulia Sadar Sub-Division, under Purulia Division, | 3.37 | BP-2024-25-470 | 04/10/2024 | VCH/000626/2024-2025 |
63 | Purulia Division | BILL/00429/2024-2025 | 10/07/2024 | GLAMOUROOMS UNEMPLOYED CO-OPERATIVE SOCIETY LTD. | ORD/000832/2022-2023 | 1724/PD | 22/11/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at Palashkola and Gopalpur Mouza of Pindra G.P. under command area of Bongabari Water Supply Scheme at Purulia-II Block under Purulia Sadar Sub- | 11.73 | BP-2024-25-241 | 22/07/2024 | VCH/000315/2024-2025 |
64 | Purulia Division | BILL/00435/2024-2025 | 13/07/2024 | TOTAL INFRA | ORD/002299/2023-2024 | 192/PD | 02/02/2024 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 2(Two) nos tubewellat OHR Sites of Zone - I & II of Hura Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Divisi | 13.23 | BP-2024-25-247 | 22/07/2024 | VCH/000322/2024-2025 |
65 | Purulia Division | BILL/00456/2024-2025 | 15/07/2024 | ROY CONSTRUCTION | ORD/000124/2024-2025 | 892/PD | 07/05/2024 | Construction of main drain at Baghmundi WTP Site under Piped Water Supply Scheme from Marble Lake under Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | 2.03 | BP-2024-25-250 | 22/07/2024 | VCH/000325/2024-2025 |
66 | Purulia Division | BILL/00460/2024-2025 | 15/07/2024 | KM ENTERPRISES | ORD/000899/2023-2024 | 1567/PD | 26/10/2023 | Construction and Commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 150 CUM and staging height 20 mtr as per approved drawing (No: PC-I/OHR/3/2012) including Laying Distribution Pipe Lines and providing FHTCs including other | 22.11 | BP-2024-25-253 | 22/07/2024 | VCH/000327/2024-2025 |
67 | Purulia Division | BILL/00544/2024-2025 | 13/08/2024 | SATWICK ENTERPRISE | ORD/001638/2023-2024 | 1838/PD | 12/12/2023 | Civil & Electrical Part related to NABL Recognition of Manbaazar-II Sub-District Laboratory as per ISO/IEC 17025:2017 Related to Support Activities Under Jal Jeevan Mission. | 1.60 | BP-2024-25-387 | 17/09/2024 | VCH/000520/2024-2025 |
68 | Purulia Division | BILL/00561/2024-2025 | 22/08/2024 | S. S. ENTERPRISE | ORD/001448/2023-2024 | 1807/PD | 08/12/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - II of Neturia Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -C, Mouza - | 2.00 | BP-2024-25-343 | 29/08/2024 | VCH/000449/2024-2025 |
69 | Purulia Division | BILL/00572/2024-2025 | 23/08/2024 | IKBAL CONSTRUCTION | ORD/000878/2022-2023 | 1869/PD | 13/12/2022 | Water supply Tap Connection Arrangement for 6 nos AWC within PURULIA-II Block (Part-J,L,M,N,N,O) from newly sinked tubewell by mechanical division of Purulia District under Purulia Division, PHE Dte. | 18.66 | BP-2024-25-336 | 28/08/2024 | VCH/000457/2024-2025 |
70 | Purulia Division | BILL/00699/2024-2025 | 06/09/2024 | M/S CONTRACTORS SYNDICATE | ORD/003485/2023-2024 | 360/PD | 04/03/2024 | Construction of Boundary wall & Sinking of T/well at Bongabari (Purulia-II) under Bongabari W/S Scheme under Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | 5.52 | BP-2024-25-373 | 13/09/2024 | VCH/000494/2024-2025 |
71 | Purulia Division | BILL/00710/2024-2025 | 10/09/2024 | ANUP KUMAR SAHA CIVIL CONTRACTORS PRIVATE LIMITED | ORD/001870/2023-2024 | 95/PD | 15/01/2024 | Construction of Boundary wall at Arsha Zone-2 OHR Site and Making Bypass Arrangement at OHR Site under Arsha W/S Scheme under Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | 22.63 | BP-2024-25-370 | 13/09/2024 | VCH/000493/2024-2025 |
72 | Purulia Division | BILL/00721/2024-2025 | 12/09/2024 | RAJ BROTHERS | ORD/000895/2023-2024 | 1560/PD | 18/10/2023 | Construction and Commissioning of RCC Over Head Reservoir ( Torch type with solid raft ) of capacity 150 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe Line and providing FHTC including other | 53.20 | BP-2024-25-385 | 17/09/2024 | VCH/000501/2024-2025 |
73 | Purulia Division | BILL/00736/2024-2025 | 19/09/2024 | EXECUTIVE ENGINEER, PURULIA DIVISION PWD DTE. | null | 1008/PD | 03/08/2024 | Sl ii) Restoration of Road after laying of drinking water pipe line under Jal Jeevan Mission for Kashipur WS Scheme along Hura-Kashipur-Adra-Raghunathpur Road under Purulia Division PWD in the district of Purulia in Year 2023-2024. Estimate Amount: Rs.1, | 57.29 | BP-2024-25-408 | 22/09/2024 | VCH/000516/2024-2025 |
74 | Purulia Division | BILL/00763/2024-2025 | 21/09/2024 | SWAPAN MANDAL | ORD/000918/2023-2024 | 1592/PD | 31/10/2023 | Construction and Commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 200 CUM and staging height 20 mtr as per approved drawing (No: PC-I/OHR/3/2012) including Laying Distribution Pipe Lines and providing FHTCs including other | 41.46 | BP-2024-25-417 | 25/09/2024 | VCH/000535/2024-2025 |
75 | Purulia Division | BILL/00773/2024-2025 | 21/09/2024 | ASHOK KUMAR CHATTERJEE | ORD/001197/2022-2023 | 471/PD | 28/03/2023 | Laying Distribution pipe line including providing Functional Household Tap Connection (FHTC), and other allied works of Raghunathpur Water Supply Scheme (Zone-I A/I) of Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 6.07 | BP-2024-25-416 | 25/09/2024 | VCH/000534/2024-2025 |
76 | Purulia Division | BILL/00774/2024-2025 | 21/09/2024 | MANIRUL ISLAM SK | ORD/000555/2023-2024 | 1337/PD | 08/09/2023 | Construction of Rcc Over Head Reservoir (Torch type with solid raft)of capacity 150 cum and staging heght 20 mtr and laying of Distribution System including pipe carrying structure all complete including providing House Hold Tap Connection (FHTC)and other | 56.81 | BP-2024-25-433 | 27/09/2024 | VCH/000549/2024-2025 |
77 | Purulia Division | BILL/00899/2024-2025 | 02/10/2024 | SADHAN GORAIN | ORD/000107/2023-2024 | 869/PD | 30/06/2023 | Sinking of 3 nos New 200 mm dia horizontal tube-well at Rangamati Kansai river bed, laying of 100mm dia GI pipe collecting line from RBT to comon manifold to Mitigate Draught Like Situtation at Rangamatia river bank of Kansai Arsha & its adjoining mouza | 7.06 | BP-2024-25-513 | 06/10/2024 | VCH/000665/2024-2025 |
78 | Purulia Division | BILL/00900/2024-2025 | 02/10/2024 | TUMPA GORAIN | ORD/000448/2024-2025 | 1510/PD | 27/08/2024 | Laying HDPE distribution pipeline to cover the left out habitation of Ajodhya, Bagandih & Chatni mouza at Ajodhya Under Marble Lake W/S Scheme under Purulia Division, PHE Dte. | 22.42 | BP-2024-25-484 | 05/10/2024 | VCH/000639/2024-2025 |
79 | Purulia Division | BILL/00939/2024-2025 | 04/10/2024 | SANTANU BANERJEE | ORD/000920/2023-2024 | 1593/PD | 31/10/2023 | Construction and Commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity of 350 CUM and staging height 20 mtr as per approved drawing (No:PC-I/OHR/3/2012) including Laying Distribution Pipe Line and providing FHTC including other | 136.14 | BP-2024-25-518 | 23/10/2024 | VCH/000669/2024-2025 |
80 | Purulia Division | BILL/00411/2024-2025 | 04/07/2024 | NIBHAS SINHA | ORD/001622/2023-2024 | 1832/PD | 12/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire at Rangadanga High School , OHR Campus under Ramchandrapur W/S Scheme of Raghunathpur Sub-Division under Purulia Division, P.H.E. Dte. (Total length of Boundary Wall 175 mtr.) | 15.47 | BP-2024-25-231 | 11/07/2024 | VCH/000298/2024-2025 |
81 | Purulia Division | BILL/00421/2024-2025 | 08/07/2024 | KOUSHIK CHATTERJEE | ORD/001209/2022-2023 | 493/PD | 31/03/2023 | Making Interconnection and Bypass arrangemet of Rising Main and Distribution Pipeline For Newly Constructed OHR at Barabazar OHR Site of Aug. Barabazar W/S Scheme of Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | 2.55 | BP-2024-25-228 | 10/07/2024 | VCH/000296/2024-2025 |
82 | Purulia Division | BILL/00425/2024-2025 | 09/07/2024 | KRISHNA CONSTRUCTION AND ORDER SUPPLIER | ORD/001848/2023-2024 | 80/PD | 15/01/2024 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 2(Two) nos tubewellat OHR Sites of Zone - VII & VIII of Para Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Div | 15.14 | BP-2024-25-243 | 22/07/2024 | VCH/000318/2024-2025 |
83 | Purulia Division | BILL/00475/2024-2025 | 22/07/2024 | KOUSHIK CHATTERJEE | ORD/000091/2022-2023 | 673/PD | 25/04/2022 | Water supply Tap Connection Arrangement for 38 nos School upto 200 Students, within Manbazar-II Block (Part-B) of Purulia District under Purulia Division, PHE Dte. | 7.83 | BP-2024-25-268 | 27/07/2024 | VCH/000345/2024-2025 |
84 | Purulia Division | BILL/00477/2024-2025 | 22/07/2024 | RABIN CHANDRA CHAIL | ORD/000179/2023-2024 | 995/PD | 26/07/2023 | Laying of HDPE pipe (PE-100, PN-10) for collecting line of riverbed Intake Well (for 1 & 2) at Narayangarh under Arrah W/S Scheme of Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 5.59 | BP-2024-25-282 | 01/08/2024 | VCH/000401/2024-2025 |
85 | Purulia Division | BILL/00489/2024-2025 | 29/07/2024 | BOSE CONSTRUCTION | ORD/000002/2022-2023 | 538/PD | 01/04/2022 | Construction of Office Cum Godown at Ist Floor of Ajodhya Camp Office under Marble Lake & Its Adjoing Area W/S Scheme of Purulia Sadar Sub-Division, PHE Dte. | 12.84 | BP-2024-25-280 | 02/08/2024 | VCH/000403/2024-2025 |
86 | Purulia Division | BILL/00510/2024-2025 | 05/08/2024 | ASHOKE ADHIKARY | ORD/004345/2023-2024 | 662_PD | 17/05/2023 | Construction of meter room, panel room, undercut pump house & surface drain with other allied works at Puncha OHR Site (Bahadurpur) for Augmentation of Lagda W/S Scheme under Purulia Sadar Sub-Division, under Purulia Division, PHE Dte. | 8.72 | BP-2024-25-291 | 09/08/2024 | VCH/000399/2024-2025 |
87 | Purulia Division | BILL/00527/2024-2025 | 07/08/2024 | SOUVIK MANDAL | ORD/000861/2023-2024 | 1501/PD | 12/10/2023 | Trial Run of Panradda Zone-2 (Except Electro Mechanical Component) of all distribution system,sluice valve ,FHTC etc under Purulia Division ,P.H.E Dte(For the Period of 92 days) w.e.f of 01.11.2023 to 31.01.2024] | 14.66 | BP-2024-25-301 | 13/08/2024 | VCH/000374/2024-2025 |
88 | Purulia Division | BILL/00534/2024-2025 | 09/08/2024 | CHATTERJEE CONSTRUCTION | ORD/000262/2023-2024 | 1083/PD | 10/08/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - III of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -G , Mouza | 85.86 | BP-2024-25-309 | 14/08/2024 | VCH/000382/2024-2025 |
89 | Purulia Division | BILL/00677/2024-2025 | 05/09/2024 | SUPRIYA MAHANTI MISHRA | ORD/000655/2023-2024 | 1348/PD | 13/09/2023 | Operation & Maintenance and water testing in the laboratory at Hura Sub District Laboratory under under RWS Purulia Sub Division PHE Dte.. (w.e.f.01.10.2023 to 31.08.2024). | 5.30 | BP-2024-25-386 | 17/09/2024 | VCH/000502/2024-2025 |
90 | Purulia Division | BILL/00793/2024-2025 | 26/09/2024 | CHATTERJEE CONSTRUCTION | ORD/000452/2024-2025 | 1513/PD | 27/08/2024 | Fencing work with concrete pillars for 15 Nos vested land for Northern & Southern Sector water supply scheme Under Purulia W/S Scheme (Northern Sector) under Purulia Division, PHE Dte. | 5.86 | BP-2024-25-441 | 29/09/2024 | VCH/000557/2024-2025 |
91 | Purulia Division | BILL/00799/2024-2025 | 26/09/2024 | CHATTERJEE CONSTRUCTION | ORD/000062/2023-2024 | 1054/PD | 08/08/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - I of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part - D, Mouza - | 6.44 | BP-2024-25-444 | 29/09/2024 | VCH/000560/2024-2025 |
92 | Purulia Division | BILL/00813/2024-2025 | 28/09/2024 | VIVEKANANDA CONSTRUCTION | ORD/003465/2023-2024 | 334/PD | 01/03/2024 | Construction of Boundary wall & Sinking of T/well at Jhalda-II,Zone-VII under Purulia W/S Scheme under Purulia Sadar Sub Division under Purulia Division, PHE Dte. | 13.04 | BP-2024-25-462 | 03/10/2024 | VCH/000576/2024-2025 |
93 | Purulia Division | BILL/00820/2024-2025 | 28/09/2024 | ANIL GORAI | ORD/000459/2021-2022 | 421/PD | 17/03/2022 | Construction of RCC clear water reservoir (CWR) of capacity 100 Cum with other allied works of Baghmundi W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE Dte. | 2.16 | BP-2024-25-491 | 05/10/2024 | VCH/000643/2024-2025 |
94 | Purulia Division | BILL/00844/2024-2025 | 28/09/2024 | SOUHARDYA BUSINESS LINE | ORD/000146/2022-2023 | 758/PD | 02/05/2022 | Water supply Tap Connection Arrangement for 6 nos AWC within Purulia-I Block (Part-G) of Purulia District under Purulia Division, PHE Dte. | 4.06 | BP-2024-25-454 | 03/10/2024 | VCH/000592/2024-2025 |
95 | Purulia Division | BILL/00848/2024-2025 | 29/09/2024 | ARUNALOY SCIENTIFIC HOUSE | ORD/001267/2023-2024 | 1697/PD | 29/11/2023 | Continuation order for the work of "Supply of Laboratory reagent/media/consumables required for routine water testing of different laboratories under Purulia Division, PHE Dte. ( For 2 months)" | 18.27 | BP-2024-25-481 | 05/10/2024 | VCH/000636/2024-2025 |
96 | Purulia Division | BILL/00854/2024-2025 | 29/09/2024 | JAYANTA KUMAR MONDAL | ORD/003977/2023-2024 | 522/PD | 16/03/2024 | Laying of HDPE pipe line (75mm & 63mm) with additional Functional Household Tap Connection (FHTC) of distribution system (Zone-I) under Sarbari W/S Scheme within Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 25.57 | BP-2024-25-465 | 03/10/2024 | VCH/000621/2024-2025 |
97 | Purulia Division | BILL/00859/2024-2025 | 29/09/2024 | RANJIB GHATAK | ORD/000894/2023-2024 | 1557/PD | 18/10/2023 | Construction and Commissioning of RCC Over Head Reservoir ( Torch type with solid raft ) of capacity 200 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe Line and providing FHTC including other | 93.24 | BP-2024-25-475 | 05/10/2024 | VCH/000583/2024-2025 |
98 | Purulia Division | BILL/00371/2024-2025 | 19/06/2024 | KM ENTERPRISES | ORD/000314/2022-2023 | 847/PD | 23/05/2022 | Construction of pump house for accommodating centrifugal pump for pumping of water including panel room & chlorination room at Joypur OHR site of Joypur W/S Scheme under Purulia Sadar Sub-Division, Purulia Division, PHE Dte. | 8.96 | BP-2024-25-233 | 11/07/2024 | VCH/000258/2024-2025 |
99 | Purulia Division | BILL/00459/2024-2025 | 15/07/2024 | VINCI CONSTRUCTION | ORD/001356/2023-2024 | 1726/PD | 04/12/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - IV of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -G , Mouza - | 5.76 | BP-2024-25-255 | 22/07/2024 | VCH/000329/2024-2025 |
100 | Purulia Division | BILL/00542/2024-2025 | 13/08/2024 | JULI ENTERPRISE | ORD/002303/2023-2024 | 193/PD | 02/02/2024 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 2(Two) nos tubewellat OHR Sites of Zone - III & IV of Hura Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Divis | 9.17 | BP-2024-25-324 | 21/08/2024 | VCH/000417/2024-2025 |
101 | Purulia Division | BILL/00549/2024-2025 | 13/08/2024 | ANUP KUMAR SAHA | ORD/000763/2023-2024 | 1369/PD | 14/09/2023 | Construction and commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the | 62.72 | BP-2024-25-320 | 21/08/2024 | VCH/000413/2024-2025 |
102 | Purulia Division | BILL/00554/2024-2025 | 14/08/2024 | GOUTAM CHAKRABORTY | ORD/000141/2024-2025 | 924/PD | 07/05/2024 | Left out HDPE Distribution main Pipe line from Hatuara OHR site to existing distribution main of Bongabari W/S scheme under Purulia Sadar Sub-Division, of Purulia Division, PHE Dte. | 56.34 | BP-2024-25-328 | 21/08/2024 | VCH/000422/2024-2025 |
103 | Purulia Division | BILL/00567/2024-2025 | 22/08/2024 | TOTAL INFRA | ORD/002299/2023-2024 | 192/PD | 02/02/2024 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 2(Two) nos tubewellat OHR Sites of Zone - I & II of Hura Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Divisi | 6.32 | BP-2024-25-335 | 28/08/2024 | VCH/000456/2024-2025 |
104 | Purulia Division | BILL/00698/2024-2025 | 06/09/2024 | SIDDHARTHA SANKAR SARKAR | ORD/001052/2022-2023 | 284/PD | 27/02/2023 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at Bongabari Village including extention of distribution pipe line (Gap Portion) of Raghabpur G.P. under command area of Bongabari Water Supply | 19.03 | BP-2024-25-368 | 13/09/2024 | VCH/000491/2024-2025 |
105 | Purulia Division | BILL/00717/2024-2025 | 12/09/2024 | RAJAT KARMAKAR | ORD/001485/2023-2024 | 1798/PD | 08/12/2023 | Laying of Collecting line from Kanshabati Riverbed to Harekishtapur Riversite Pump House under Manbazar W/S Scheme under Purulia Sadar Sub-Division under Purulia Division, PHE Dte | 23.10 | BP-2024-25-378 | 16/09/2024 | VCH/000480/2024-2025 |
106 | Purulia Division | BILL/00719/2024-2025 | 12/09/2024 | TAPAN CHANDRA | ORD/000147/2024-2025 | 918/PD | 07/05/2024 | Laying of 250 mm DI rising main from Mahara CWR to Hatuara OHR for augmentation of Bongabari W/S scheme at Purulia-II block under Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | 43.22 | BP-2024-25-383 | 17/09/2024 | VCH/000499/2024-2025 |
107 | Purulia Division | BILL/00720/2024-2025 | 12/09/2024 | KABERI DUTTA | ORD/000247/2023-2024 | 1063/PD | 08/08/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - V of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -B , Mouza - | 23.94 | BP-2024-25-381 | 16/09/2024 | VCH/000484/2024-2025 |
108 | Purulia Division | BILL/00738/2024-2025 | 19/09/2024 | LUKE ENGICON | ORD/000832/2023-2024 | 1415/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenances of Distributions , Pipe Lines (DI/HDPE), including Slice Valves & FHTCs for the | 106.05 | BP-2024-25-411 | 23/09/2024 | VCH/000529/2024-2025 |
109 | Purulia Division | BILL/00745/2024-2025 | 19/09/2024 | PURNA CHANDRA TEWARI | ORD/000171/2023-2024 | 933/PD | 19/07/2023 | Construction of Switch Room Cum Chlorin Room at Santuri OHR Site of Santuri W/S Scheme within Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 3.00 | BP-2024-25-401 | 22/09/2024 | VCH/000523/2024-2025 |
110 | Purulia Division | BILL/00883/2024-2025 | 01/10/2024 | CHINMOY SEN | ORD/001452/2023-2024 | 1770/PD | 08/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewellat OHR Site of Zone - IV of Kashipur Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Division | 17.36 | BP-2024-25-514 | 06/10/2024 | VCH/000661/2024-2025 |
111 | Purulia Division | BILL/00905/2024-2025 | 02/10/2024 | ASHOKE KUMAR CHATTERJEE | ORD/001332/2022-2023 | 104/PD | 20/01/2023 | Construction of RCC Over Head reservoir (OHR) capacity 300 cum for Aug. of Dubra Water Supply Scheme (Northern Sector) within Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 50.77 | BP-2024-25-487 | 05/10/2024 | VCH/000649/2024-2025 |
112 | Purulia Division | BILL/00906/2024-2025 | 02/10/2024 | JYOTY SOLAR POWER | ORD/000212/2021-2022 | 1418/PD | 25/11/2021 | Installation of Stand-Alone Community Purification Plant (CPP) with provision of Tube Well, Solar Power Operated Pumping Machinery and Treatment Unit for removal of Fluoride in the left out Fluoride affected habitations as per IMIS Report (F-18 & C17C) 4 | 7.02 | BP-2024-25-510 | 06/10/2024 | VCH/000662/2024-2025 |
113 | Purulia Division | BILL/00908/2024-2025 | 02/10/2024 | S & P ENTERPRISE | ORD/001606/2023-2024 | 1761/PD | 07/12/2023 | Construction and Commissioning of RCC Over Head Reservoir(s) including Laying Distribution Pipe Line(s) and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe Line (DI/HDPE), including Sluice Valves & FHTCs for t | 243.05 | BP-2024-25-493 | 05/10/2024 | VCH/000581/2024-2025 |
114 | Purulia Division | BILL/00909/2024-2025 | 02/10/2024 | DEBAKI RANJAN SARKAR | ORD/000909/2023-2024 | 1584/PD | 30/10/2023 | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the | 99.43 | BP-2024-25-512 | 06/10/2024 | VCH/000664/2024-2025 |
115 | Purulia Division | BILL/00928/2024-2025 | 03/10/2024 | ALOK KUMAR CHAKRABORTY | ORD/000378/2024-2025 | 1359/PD | 25/07/2024 | Repering & Renovation of connecting line at Kasai River of Maguria Lalpur & including providing House Hold Tap Connection (FHTC) of two no school (Amliatora Pry School -1no, Daldali Girls High School-2nos) and other allied works under Maguria Lalpur W/S a | 2.53 | BP-2024-25-495 | 05/10/2024 | VCH/000646/2024-2025 |
116 | Purulia Division | BILL/00938/2024-2025 | 03/10/2024 | SIMA ENTERPRISE | ORD/001865/2023-2024 | 91/PD | 15/01/2024 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 150 CUM and staging height 20 mtr as per approved drawing (No:PC-I/OHR/3/2012) with allied works for Zone-I of Neturia Block under Purulia Piped Water Suppl | 19.84 | BP-2024-25-504 | 06/10/2024 | VCH/000584/2024-2025 |
117 | Purulia Division | BILL/00314/2024-2025 | 11/06/2024 | BHAGABAN DAS KUMAR | ORD/000276/2021-2022 | 1551/PD | 15/12/2021 | Construction of pump house for accommodating centrifugal pump for pumping of water including panel room & chlorination room from Chitmu Pump House to distribution area through distribution main of Chitmu W/S Scheme under Purulia Sadar Sub-Division, Puruli | 14.98 | BP-2024-25-224 | 10/07/2024 | VCH/000288/2024-2025 |
118 | Purulia Division | BILL/00396/2024-2025 | 24/06/2024 | M/S ANAND SINGH | ORD/001578/2023-2024 | 1820/PD | 12/12/2023 | Construction and Commissioning of RCC Over Head Reservoir(s) including Laying Distribution Pipe Line(s) and providing FHTCs including other allied works & Operation & Maintenance of Distributions , Pipe Line (DI/HDPE), including Sluice Valves & FHTCs for | 234.01 | BP-2024-25-211 | 01/07/2024 | VCH/000224/2024-2025 |
119 | Purulia Division | BILL/00397/2024-2025 | 25/06/2024 | SUBRATA SINGHADEO | ORD/003989/2023-2024 | 518/PD | 16/03/2024 | Sinking of 1(One) Nos. 200 mm dia DTH rigbored tubewell with other allied works at Boosting Pump Station (Seleta Mouza) of Raghunathpur W/S Scheme (German Project) of Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 3.71 | BP-2024-25-212 | 02/07/2024 | VCH/000225/2024-2025 |
120 | Purulia Division | BILL/00400/2024-2025 | 25/06/2024 | SAHADEV HALDER | ORD/001480/2023-2024 | 1791/PD | 08/12/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 150 CUM and staging height 20 mtr as per approved drawing (No:PC-I/OHR/3/2012)with allied works for purulia water supply scheme.(Location:-Block-Purulia-1 | 29.62 | BP-2024-25-217 | 09/07/2024 | VCH/000249/2024-2025 |
121 | Purulia Division | BILL/00404/2024-2025 | 25/06/2024 | S. S. ENTERPRISE | ORD/001448/2023-2024 | 1807/PD | 08/12/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - II of Neturia Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -C, Mouza - | 16.57 | BP-2024-25-235 | 12/07/2024 | VCH/000250/2024-2025 |
122 | Purulia Division | BILL/00406/2024-2025 | 04/07/2024 | COMPUTER MEDIA | ORD/000924/2023-2024 | 476/A/23 | 31/08/2023 | Operation & Maintenance and water testing in the laboratory at Raghunathpur W.T.P. Sub District laboratory under RWS Purulia Sub-Division PHE Dte.(w.e.f.01.09.2023 to 31.12.2023) | 0.50 | BP-2024-25-230 | 11/07/2024 | VCH/000297/2024-2025 |
123 | Purulia Division | BILL/00476/2024-2025 | 22/07/2024 | MUNNA AGROTECH ENTERPRISE | ORD/000813/2022-2023 | 1705/PD | 22/11/2022 | Water supply Tap Connection Arrangement for 9 nos AWC within Puncha Block (Part-K) & 2 nos AWC within Puncha Block (Part-L) of Purulia District under Purulia Division, PHE Dte. (Phase-III) | 14.31 | BP-2024-25-270 | 29/07/2024 | VCH/000349/2024-2025 |
124 | Purulia Division | BILL/00478/2024-2025 | 22/07/2024 | SOUHARDYA BUSINESS LINE | ORD/000152/2022-2023 | 766/PD | 02/05/2022 | Water supply Tap Connection Arrangement for 9 nos AWC within Purulia-II Block (Part-E) of Purulia District under Purulia Division, PHE Dte. | 16.05 | BP-2024-25-266 | 29/07/2024 | VCH/000346/2024-2025 |
125 | Purulia Division | BILL/00499/2024-2025 | 29/07/2024 | SUMIT KUMAR CHAKRABORTY | ORD/001849/2023-2024 | 81/PD | 15/01/2024 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 2(Two) nos tubewellat OHR Sites of Zone - XV & XVI of Para Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Divi | 15.76 | BP-2024-25-285 | 02/08/2024 | VCH/000362/2024-2025 |
126 | Purulia Division | BILL/00526/2024-2025 | 07/08/2024 | MANATOSH SINGH | ORD/000656/2023-2024 | 1349/PD | 13/09/2023 | Operation & Maintenance and water testing in the laboratory af Raghunathpur Sub-District Laboratory under RWS purulia Sub-Division PHE Dte. (w.e.f.01.10.2023 to 31.08.2024). | 3.04 | BP-2024-25-305 | 13/08/2024 | VCH/000378/2024-2025 |
127 | Purulia Division | BILL/00533/2024-2025 | 09/08/2024 | NANIGOPAL DEY | ORD/000150/2022-2023 | 762/PD | 02/05/2022 | Water supply Tap Connection Arrangement for 9 no AWC within Hura Block (Part-F) of Purulia District under Purulia Division, PHE Dte. | 29.46 | BP-2024-25-310 | 14/08/2024 | VCH/000383/2024-2025 |
128 | Purulia Division | BILL/00539/2024-2025 | 09/08/2024 | M/S SAYAK BHATTACHARYA | ORD/000223/2024-2025 | 1098/PD | 07/06/2024 | Repairing of DI Rising Main & Sinking of 4(Four ) Nos. 200 mm dia DTH rigboredtubewell with 1 H.P. Submersible Pumping Machinary with allied works at Anara Girls' High School, Para S.N. High School, Dubra High School & Anara S.E. Railway Colony High Sc | 22.52 | BP-2024-25-308 | 14/08/2024 | VCH/000381/2024-2025 |
129 | Purulia Division | BILL/00673/2024-2025 | 05/09/2024 | SANTANU BANERJEE | ORD/000410/2022-2023 | 937/PD | 16/06/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at different habitation and extention of distribution pipe line under command area of Bandwan Water Supply Scheme of Bandwan Block under Puru | 18.75 | BP-2024-25-367 | 13/09/2024 | VCH/000490/2024-2025 |
130 | Purulia Division | BILL/00674/2024-2025 | 05/09/2024 | JAYANTA KUMAR MONDAL | ORD/000809/2023-2024 | 1416/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenances of Distributions , Pipe Lines (DI/HDPE), including Slice Valves & FHTCs for the | 208.97 | BP-2024-25-361 | 12/09/2024 | VCH/000476/2024-2025 |
131 | Purulia Division | BILL/00675/2024-2025 | 05/09/2024 | HIRAK KUMAR SAO | ORD/000631/2022-2023 | 1399/PD | 01/09/2022 | Supplying & laying of HDPE pipe and laying of DI pipe line for Distribution System of Sirkabad W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE Dte. (Mouza Covered-Bhelaidih,Gandhabazar,Aharrah)) | 2.82 | BP-2024-25-364 | 12/09/2024 | VCH/000488/2024-2025 |
132 | Purulia Division | BILL/00789/2024-2025 | 26/09/2024 | AMIT PATHAK | ORD/000281/2023-2024 | 1138/PD | 17/08/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 200 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012), Laying of Distribution Pipe Line with allied works for Zone- VII of Santuri | 18.87 | BP-2024-25-435 | 29/09/2024 | VCH/000551/2024-2025 |
133 | Purulia Division | BILL/00790/2024-2025 | 26/09/2024 | CHANCHAL MISHRA | ORD/000151/2024-2025 | 907/PD | 07/05/2024 | Laying of distribution pipe line & Restoration work by cleaning and chowkage clearance of distribution Main & including providing House Hold Tap Connection (FHTC) two no (Adivasi Hostel) and other allied works at Daldali village under Kashipur Piped water | 2.61 | BP-2024-25-451 | 03/10/2024 | VCH/000588/2024-2025 |
134 | Purulia Division | BILL/00805/2024-2025 | 27/09/2024 | MANATOSH SINGH | ORD/000258/2021-2022 | 1531/PD | 13/12/2021 | Repairing and Renovation of R.C.C. Elevated Reservoir of capacity 185 Cum (Intze Type) including other allied works at OHR site of Baghmundi W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE Dte. | 4.27 | BP-2024-25-476 | 05/10/2024 | VCH/000631/2024-2025 |
135 | Purulia Division | BILL/00843/2024-2025 | 28/09/2024 | ARUNALOY SCIENTIFIC HOUSE | ORD/000096/2023-2024 | 858/PD | 30/06/2023 | Operation & Maintenance and water testing in the laboratory at Cheliyama Sub-District Laboratory under RWS purulia Sub-Division PHE Dte. (w.e.f.01.07.2023 to 30.06.2024). | 2.00 | BP-2024-25-479 | 05/10/2024 | VCH/000634/2024-2025 |
136 | Purulia Division | BILL/01615/2023-2024 | 24/01/2024 | M.K.KAYAL & ASSOCIATES | ORD/001001/2022-2023 | 110/A/PD | 20/01/2023 | Continuation work for Soil Investigation work for proposed WTP at Manbazar-II Block within within Purulia Sadar Sub-Division of Purulia Division P.H.E Dte. | 1.10 | BP-2024-25-432 | 26/09/2024 | VCH/001895/2023-2024 |
137 | Purulia Division | BILL/00374/2024-2025 | 19/06/2024 | TRINITY CONSTRUCTION | ORD/000899/2022-2023 | 1838/PD | 12/12/2022 | Repairing, renovation of Boundary Wall at Joypur OHR site of Joypur W/S Scheme Under Purulia Sadar Sub-Division, Purulia Division, P.H.E. Dte. | 8.67 | BP-2024-25-219 | 10/07/2024 | VCH/000257/2024-2025 |
138 | Purulia Division | BILL/00461/2024-2025 | 16/07/2024 | NANIGOPAL DEY | ORD/000529/2022-2023 | 1059/PD | 08/07/2022 | Supplying & laying of HDPE pipe and laying of DI pipe line for Distribution System of Kotshila W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE Dte. (Mouza Name-Chitarpur) | 17.48 | BP-2024-25-259 | 23/07/2024 | VCH/000342/2024-2025 |
139 | Purulia Division | BILL/00471/2024-2025 | 19/07/2024 | NIBHAS SINHA | ORD/000803/2023-2024 | 1428/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the | 83.39 | BP-2024-25-271 | 29/07/2024 | VCH/000350/2024-2025 |
140 | Purulia Division | BILL/00546/2024-2025 | 13/08/2024 | PARTHA PRATIM CHHATAIT | ORD/000525/2022-2023 | 1043/PD | 07/07/2022 | Supplying & laying of HDPE pipe and laying of DI pipe line for Distribution System under augmentation of Kotshila W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE Dte. (Mouza Name-Murulahar ) | 23.33 | BP-2024-25-325 | 21/08/2024 | VCH/000418/2024-2025 |
141 | Purulia Division | BILL/00553/2024-2025 | 14/08/2024 | GAJA ENGINEERING PRIVATE LIMITED | ORD/000897/2023-2024 | 1563/PD | 26/10/2023 | Design, Surveying, Engineering, Supplying, Construction, Erection, Installation, Testing And Commissioning Of Fixed Type Intake Jetty With Pump House, Construction Of Subs Stations; Raw Water Rising Main, Bank Protection, 158 MLD (Minimum) Capacity Water | 843.30 | BP-2024-25-329 | 21/08/2024 | VCH/000427/2024-2025 |
142 | Purulia Division | BILL/00555/2024-2025 | 14/08/2024 | PREMNATH MITRA | ORD/000016/2022-2023 | 578/PD | 12/04/2022 | Water supply Tap Connection Arrangement for 47 nos School upto 200 Students, 5 nos School for 201-500 Students, 1 no School for 501-800 Students and 1 no School above 800 Students within Manbazar-II Block (Part-A) of Purulia District under Purulia Divisi | 59.05 | BP-2024-25-331 | 22/08/2024 | VCH/000424/2024-2025 |
143 | Purulia Division | BILL/00579/2024-2025 | 23/08/2024 | EXECUTIVE ENGINEER, PURULIA DIVISION PWD DTE. | null | 924/PWD | 19/06/2024 | Restoration of Road after laying of drinking after pipe line under JAL Jeevan Mission for W/S Scheme along Raghunathpur Chalunia Road, in the District of Purulia under Purulia Division PWD Dte. during the year 2024-2025. (Memo No.924/PWD dt.19.06.2024) (N | 47.28 | BP-2024-25-340 | 28/08/2024 | VCH/000446/2024-2025 |
144 | Purulia Division | BILL/00712/2024-2025 | 10/09/2024 | SAIBAL SARKAR | ORD/000169/2023-2024 | 940/PD | 19/07/2023 | Repairing and Renovation of High lift pump house & Sub station building including other allied works at WTP site in connection with Jal Jeevan Mission (JJM) for Augmentation of Balarampur W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE | 5.77 | BP-2024-25-384 | 17/09/2024 | VCH/000500/2024-2025 |
145 | Purulia Division | BILL/00714/2024-2025 | 11/09/2024 | KHITISH CHANDRA PATHAK | ORD/003979/2023-2024 | 524/PD | 16/03/2024 | Supply fitting fixing D.I Specials for 200 MM dia D.I Rising Main under Sarbari W/S Scheme under Raghunathpur Sub-Division under Purulia Division P.H.E Dte. | 3.32 | BP-2024-25-380 | 16/09/2024 | VCH/000498/2024-2025 |
146 | Purulia Division | BILL/00734/2024-2025 | 19/09/2024 | CHANDRA SHEKHAR KUNDU | ORD/000844/2023-2024 | 466/RNP | 10/10/2023 | Continuous work order for the work of Hiring of Ambassador Car / Bolero for the Assistant Engineer, Raghunathpur Sub-Divn, PHE Dte. (w.e.f. 01/11/2023 to 31/03/2024) | 0.40 | BP-2024-25-524 | 13/11/2024 | VCH/000698/2024-2025 |
147 | Purulia Division | BILL/00735/2024-2025 | 19/09/2024 | CHANDRA SHEKHAR KUNDU | ORD/000844/2023-2024 | 466/RNP | 10/10/2023 | Continuous work order for the work of Hiring of Ambassador Car / Bolero for the Assistant Engineer, Raghunathpur Sub-Divn, PHE Dte. (w.e.f. 01/11/2023 to 31/03/2024) | 0.39 | BP-2024-25-524 | 13/11/2024 | VCH/000699/2024-2025 |
148 | Purulia Division | BILL/00582/2024-2025 | 23/08/2024 | ANADI MAHATO | ORD/001036/2022-2023 | 324/PD | 09/03/2023 | Repairing and Renovation of Boundary wall & centry room including other allied works at WTP site in connection with Jal Jeevan Mission (JJM) for Augmentation of Balarampur W/S Scheme of Purulia Sadar Sub-Division under Purulia Division PHE Dte. | 3.02 | BP-2024-25-344 | 29/08/2024 | VCH/000450/2024-2025 |
149 | Purulia Division | BILL/00594/2024-2025 | 28/08/2024 | SUBHAS CHANDRA MAHATO | ORD/001825/2023-2024 | 63/PD | 10/01/2024 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 2(Two) nos tubewellat OHR Sites of Zone - V & VI of Hura Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Divisi | 4.71 | BP-2024-25-352 | 06/09/2024 | VCH/000466/2024-2025 |
150 | Purulia Division | BILL/00605/2024-2025 | 28/08/2024 | BHAGABAN DAS KUMAR | ORD/000123/2024-2025 | 890/PD | 07/05/2024 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and) at Gurrabera habitation of Mouza-Ritudih (JL-62) under command area of Joypur Water Supply Scheme of Jhalda-II Block under Purulia Sadar Sub-Division unde | 3.24 | BP-2024-25-350 | 06/09/2024 | VCH/000465/2024-2025 |
151 | Purulia Division | BILL/00743/2024-2025 | 19/09/2024 | SEKH IRFAN | ORD/000316/2022-2023 | 848/PD | 23/05/2022 | Repairing, renovation & restoration of Pump house & store cum Guard room at Deolghata Pump house campus of Joypur W/S Scheme Under Purulia Sadar Sub-Division, Purulia Division, P.H.E. Dte. | 4.11 | BP-2024-25-410 | 22/09/2024 | VCH/000518/2024-2025 |
152 | Purulia Division | BILL/00748/2024-2025 | 19/09/2024 | BISWAJIT MAJI | ORD/001471/2023-2024 | 1784/PD | 08/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewellat OHR Site of Zone - II of Raghunathpur-I Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Di | 3.10 | BP-2024-25-400 | 22/09/2024 | VCH/000524/2024-2025 |
153 | Purulia Division | BILL/00749/2024-2025 | 19/09/2024 | M/S KARUNAMOYEE CONSTRUCTION | ORD/000211/2024-2025 | 1244/PD | 04/07/2024 | New Sinking of 2 (Two) Nos 200 mm dia river bed vertical tubewell (T/W No.- 4 & 5) along with necessary 100 mm dia GI collecting line from Riverbed Tubewell to common manifold chamber at river bank (Damodar River) at Chinakurighat of Parbeliya W/S Scheme | 3.68 | BP-2024-25-409 | 22/09/2024 | VCH/000517/2024-2025 |
154 | Purulia Division | BILL/00750/2024-2025 | 19/09/2024 | MADHU SUDAN RAKSHIT | ORD/000252/2023-2024 | 1065/PD | 08/08/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - V of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -G , Mouza - | 40.91 | BP-2024-25-399 | 22/09/2024 | VCH/000525/2024-2025 |
155 | Purulia Division | BILL/00765/2024-2025 | 21/09/2024 | M/S KARUNAMOYEE CONSTRUCTION | ORD/000348/2021-2022 | 98/PD | 18/01/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at different habitation of Sidpur mouza (Jl. No.154) and replacement/ extention of distribution pipe line under augmentation of Hutmura Water | 18.12 | BP-2024-25-423 | 25/09/2024 | VCH/000541/2024-2025 |
156 | Purulia Division | BILL/00769/2024-2025 | 21/09/2024 | KHAN ENTERPRISE | ORD/000779/2023-2024 | 1423/PD | 29/09/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 350 CUM and staging height 20 mtr as per approved drawing (No: PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other a | 100.02 | BP-2024-25-430 | 26/09/2024 | VCH/000544/2024-2025 |
157 | Purulia Division | BILL/00770/2024-2025 | 21/09/2024 | NIBHAS SINHA | ORD/000803/2023-2024 | 1428/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the | 61.71 | BP-2024-25-418 | 25/09/2024 | VCH/000536/2024-2025 |
158 | Purulia Division | BILL/00782/2024-2025 | 23/09/2024 | ASHOK KUMAR CHATTERJEE | ORD/000176/2022-2023 | 793/PD | 05/05/2022 | Construction of RCC Over Head Reservoir (Intze type with solid raft ) of capacity 200 cum and staging height 20 mtr. with including supply of all labour & materials for Saltora -Hijli W/S Scheme within Raghunathpur Sub-Division of Purulia Division P.H.E | 14.84 | BP-2024-25-427 | 26/09/2024 | VCH/000547/2024-2025 |
159 | Purulia Division | BILL/00784/2024-2025 | 23/09/2024 | SINGHA ENTERPRISE | ORD/000818/2022-2023 | 1718/PD | 22/11/2022 | Acceptance cum Work Order for "Water supply Tap Connection Arrangement for 11 nos AWC within Manbazar-I Block (Part-E) of Purulia District under Purulia Division, PHE Dte.(Phase-III)" | 24.54 | BP-2024-25-429 | 26/09/2024 | VCH/000548/2024-2025 |
160 | Purulia Division | BILL/00944/2024-2025 | 25/10/2024 | SOUTH EASTERN RAILWAY, RANCHI DIVISION | null | WL0703IB052410202411113832563388047XX | 24/10/2024 | Indian Railways Miscellaneous collection against Merchant Reference no.WL0703IB052410202411113832563388047XX DT.24-10-2024. | 5.04 | BP-2024-25-521 | 29/10/2024 | VCH/000673/2024-2025 |
161 | Purulia Division | BILL/00398/2024-2025 | 25/06/2024 | KHITISH CHANDRA PATHAK | ORD/000365/2022-2023 | 868/PD | 23/05/2022 | Supplying, laying different dia HDPE pipe including Functional House Hold Tap Connection (FHTC) for Distribution System (Zone-II) of Sarbari W/S Scheme under Raghunathpur Sub-Division under Purulia Division, PHE Dte. (Mouza-Neturia, Pathardiha, Kuthibari, | 20.77 | BP-2024-25-214 | 02/07/2024 | VCH/000227/2024-2025 |
162 | Purulia Division | BILL/00427/2024-2025 | 09/07/2024 | ARUNALOY SCIENTIFIC HOUSE | ORD/000441/2022-2023 | 299/PR | 07/06/2022 | Operation & Maintenance and water testing in the laboratory at Dubra Sub-District Laboratory under RWS purulia Sub-Division PHE Dte.(w.e.f.01.07.2022 to 30.06.2023). SL NO.04 | 1.10 | BP-2024-25-313 | 14/08/2024 | VCH/000386/2024-2025 |
163 | Purulia Division | BILL/00515/2024-2025 | 05/08/2024 | SHYAMAL KUMAR DEY | ORD/000012/2023-2024 | 540/PD | 12/04/2023 | Construction of meter room, panel room, undercut pump house & surface drain with other allied works at Balarampur_Zone-I OHR site for Augmentation of Balarampur W/S Scheme under Purulia Sadar Sub-Division, under Purulia Division, PHE Dte. | 2.86 | BP-2024-25-293 | 12/08/2024 | VCH/000398/2024-2025 |
164 | Purulia Division | BILL/00524/2024-2025 | 07/08/2024 | MS D.PALIT AND CO. | ORD/000783/2023-2024 | 1420/PD | 29/09/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 250 CUM and staging height 20 mtr as per approved drawing (No: PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other a | 140.63 | BP-2024-25-290 | 09/08/2024 | VCH/000400/2024-2025 |
165 | Purulia Division | BILL/00525/2024-2025 | 07/08/2024 | SARKAR ENTERPRISE | ORD/003955/2023-2024 | 497/PD | 16/03/2024 | Cleaning & Fencing at Ajodhya Pump House Site under Purulia Sadar Sub-Division under Purulia Division, PHE Dte.(Under Lagda W/S Scheme) | 0.96 | BP-2024-25-294 | 12/08/2024 | VCH/000397/2024-2025 |
166 | Purulia Division | BILL/00529/2024-2025 | 09/08/2024 | SUBHAS CHANDRA MAHATO | ORD/000242/2023-2024 | 1058/PD | 08/08/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - VI of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -B , Mouza - | 19.44 | BP-2024-25-311 | 14/08/2024 | VCH/000384/2024-2025 |
167 | Purulia Division | BILL/00626/2024-2025 | 03/09/2024 | DEBAKI RANJAN SARKAR | ORD/001062/2022-2023 | 295/PD | 27/02/2023 | Laying of Main line and Parallel line under command area of Bandwan Water Supply Scheme of Bandwan Block under Purulia Sadar Sub-Division under Purulia Division, PHE Dte (Bandwan Mouza) | 23.48 | BP-2024-25-354 | 09/09/2024 | VCH/000468/2024-2025 |
168 | Purulia Division | BILL/00680/2024-2025 | 05/09/2024 | SUDHANSHU OJHA | ORD/001446/2023-2024 | 1764/PD | 07/12/2023 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jiban Mission (JJM) and Jal Swapna at different habitation and extension of distribution pipe line of Panradda (Zone-II) W/S Scheme of Purulia Sadar Sub Division under Purulia Div | 1.61 | BP-2024-25-357 | 12/09/2024 | VCH/000473/2024-2025 |
169 | Purulia Division | BILL/00692/2024-2025 | 06/09/2024 | GOUTAM CHAKRABORTY | ORD/000347/2024-2025 | 1377/PD | 25/07/2024 | Making arrangement of interconnection at distribution pipeline with newly laid distribution pipeline & installation of sluice valves on pipeline at jiudaru mouza under Kotshila W/S at Purulia Water Supply scheme (Northern Sector) under Purulia Division,P | 11.85 | BP-2024-25-371 | 13/09/2024 | VCH/000482/2024-2025 |
170 | Purulia Division | BILL/00693/2024-2025 | 06/09/2024 | M/S ANAND SINGH | ORD/001578/2023-2024 | 1820/PD | 12/12/2023 | Construction and Commissioning of RCC Over Head Reservoir(s) including Laying Distribution Pipe Line(s) and providing FHTCs including other allied works & Operation & Maintenance of Distributions , Pipe Line (DI/HDPE), including Sluice Valves & FHTCs for | 485.98 | BP-2024-25-365 | 12/09/2024 | VCH/000478/2024-2025 |
171 | Purulia Division | BILL/00794/2024-2025 | 26/09/2024 | SUBRATA SINGHADEO | ORD/000379/2024-2025 | 1402/PD | 25/07/2024 | Construction of Substation Building at Boosting station (Seleta mouza) under Raghunathpur water supply scheme and Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 22.39 | BP-2024-25-434 | 29/09/2024 | VCH/000550/2024-2025 |
172 | Purulia Division | BILL/00801/2024-2025 | 26/09/2024 | MITHU BUILDERS | ORD/001886/2023-2024 | 104/PD | 15/01/2024 | Laying of Distribution Pipeline from Zone IV B OHR site to Ekunja More and other allied works for Aug. of Raghunathpur Water Supply Scheme (Zone - IV B) within Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 21.74 | BP-2024-25-436 | 29/09/2024 | VCH/000552/2024-2025 |
173 | Purulia Division | BILL/00802/2024-2025 | 26/09/2024 | MADHU SUDAN RAKSHIT | ORD/000258/2024-2025 | 1195/PD | 26/06/2024 | Supplying , fitting and fixing Cast Iron heavy type spiral stiar case at Ramchandrapur under Ramchandrapur W/S Scheme of Raghunathpur Sub Division under Purulia Division, PHE Dte. | 2.69 | BP-2024-25-443 | 29/09/2024 | VCH/000559/2024-2025 |
174 | Purulia Division | BILL/00811/2024-2025 | 27/09/2024 | AMIT PATHAK | ORD/000677/2023-2024 | 1361/PD | 13/09/2023 | Civil, Electrical & Sanitary plumbing works related to NABL Recognition of PARA Sub-District Laboratory as per ISO/IEC 17025:2017 Related to Support Activities Under Jal Jeevan Mission. | 7.18 | BP-2024-25-461 | 03/10/2024 | VCH/000619/2024-2025 |
175 | Purulia Division | BILL/00819/2024-2025 | 28/09/2024 | MS D.PALIT AND CO. | ORD/000777/2023-2024 | 1419/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoir (Torch Type With solid raft) of capacity 150 CUM and staging height 20 mtr as per approve drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other al | 39.01 | BP-2024-25-450 | 03/10/2024 | VCH/000587/2024-2025 |
176 | Purulia Division | BILL/00839/2024-2025 | 28/09/2024 | BOSE CONSTRUCTION | ORD/000440/2024-2025 | 1503/PD | 27/08/2024 | New sinking of 2(Two ) nos. 200 mm dia river bed tubewell (Horizontal) at Kansabati river alongwith laying of 100 mm dia G.I. collecting line with other allied works of Joypur W/S Scheme of Purulia Sadar Sub-Division, under Purulia Division PHE Dte. | 9.67 | BP-2024-25-474 | 05/10/2024 | VCH/000630/2024-2025 |
177 | Purulia Division | BILL/00852/2024-2025 | 29/09/2024 | SOUMITRA CHAKRABORTY | ORD/000200/2024-2025 | 1028/PD | 04/06/2024 | Laying Distribution Pipe line and other allied work for Zone-II of Purulia-I block for Bhul Mouza under Purulia Water Supply Scheme (Northern Sector) under Purulia Divn. PHE Dte. (Sl No. 02) | 52.44 | BP-2024-25-463 | 03/10/2024 | VCH/000579/2024-2025 |
178 | Purulia Division | BILL/00372/2024-2025 | 19/06/2024 | IKBAL CONSTRUCTION | ORD/000679/2023-2024 | 1362/PD | 13/09/2023 | Supplying laying fitting fixing of HDPE pipe & FHTC Connection Near Amlatora more to Amlatora last matha & to increase pressure of Retrofitting works for creation of 'FHTC (Functional House Hold Tap Connection') in connection with Jal Jeevan Mission (JJM) | 8.95 | BP-2024-25-264 | 26/07/2024 | VCH/000343/2024-2025 |
179 | Purulia Division | BILL/00433/2024-2025 | 13/07/2024 | KOUSHIK CHATTERJEE | ORD/000780/2023-2024 | 1418/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoir (Torch Type With solid raft) of capacity 150 CUM and staging height 20 mtr as per approve drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other al | 22.53 | BP-2024-25-245 | 22/07/2024 | VCH/000320/2024-2025 |
180 | Purulia Division | BILL/00434/2024-2025 | 13/07/2024 | NANIGOPAL DEY | ORD/001014/2022-2023 | 181/PD | 07/02/2023 | Laying of parallel line under command area of Kotshila Water Supply Scheme of Kotshila Block under Purulia Sadar Sub-Division under Purulia Division, PHE Dte (Chitarpur Mouza) | 1.87 | BP-2024-25-251 | 22/07/2024 | VCH/000326/2024-2025 |
181 | Purulia Division | BILL/00455/2024-2025 | 15/07/2024 | BISWAJIT MAJI | ORD/001867/2023-2024 | 92/PD | 15/01/2024 | Laying Distribution Pipe line including FHTC and other allied work for Zone-I of Neturia Block at Mouza-Pochhara under Purulia Water Supply Scheme (Northern Sector) Under Purulia Division ,PHEDte.(Part-B) | 10.65 | BP-2024-25-249 | 22/07/2024 | VCH/000324/2024-2025 |
182 | Purulia Division | BILL/00467/2024-2025 | 19/07/2024 | KHITISH CHANDRA PATHAK | ORD/003980/2023-2024 | 525/PD | 16/03/2024 | Laying of different dia HDPE Pipe line and Road crossing for additional work at Sarbori distribution line (Zone-II) under Sarbari W/S Scheme of Raghunathpur Sub-Division under Purulia Division PHE Dte. | 12.46 | BP-2024-25-269 | 29/07/2024 | VCH/000348/2024-2025 |
183 | Purulia Division | BILL/00545/2024-2025 | 13/08/2024 | ESSAR CONSTRUCTION | ORD/001383/2023-2024 | 1738/PD | 04/12/2023 | Repairing of Boundary walls, Supplying and fitting of Mark -II Hand Pump along with concrete platform at the low yield Big Dia DTH Tubewell or Construction of concrete cover at the dry big dia DTH Tubewellssinked at various Schools & AWCs of . Puncha& | 6.03 | BP-2024-25-327 | 21/08/2024 | VCH/000421/2024-2025 |
184 | Purulia Division | BILL/00571/2024-2025 | 23/08/2024 | ASHOK KUMAR CHATTERJEE | ORD/001197/2022-2023 | 471/PD | 28/03/2023 | Laying Distribution pipe line including providing Functional Household Tap Connection (FHTC), and other allied works of Raghunathpur Water Supply Scheme (Zone-I A/I) of Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 54.05 | BP-2024-25-339 | 28/08/2024 | VCH/000445/2024-2025 |
185 | Purulia Division | BILL/00711/2024-2025 | 10/09/2024 | MOONLIGHT HOUSE | ORD/000315/2022-2023 | 843/PD | 23/05/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at different habitation of Mouza-Chitahi (Jl-105) & Mouza-Ghaghri (Jl-106) and replacement/ extention of distribution pipe line under command a | 8.18 | BP-2024-25-377 | 15/09/2024 | VCH/000485/2024-2025 |
186 | Purulia Division | BILL/00716/2024-2025 | 12/09/2024 | ANUP KUMAR SAHA | ORD/000914/2023-2024 | 1579/PD | 30/10/2023 | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the | 69.96 | BP-2024-25-379 | 16/09/2024 | VCH/000486/2024-2025 |
187 | Purulia Division | BILL/00723/2024-2025 | 13/09/2024 | KOUSHIK CHATTERJEE | ORD/000780/2023-2024 | 1418/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoir (Torch Type With solid raft) of capacity 150 CUM and staging height 20 mtr as per approve drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other al | 48.41 | BP-2024-25-389 | 18/09/2024 | VCH/000504/2024-2025 |
188 | Purulia Division | BILL/00726/2024-2025 | 13/09/2024 | MS GORAIN CONCERN | ORD/001620/2023-2024 | 1830/PD | 12/12/2023 | Pushing of 600mm dia MS pipe and 100 mm dia MS water carrier pipe by hydraulic jacking method across Purulia to Jhalda Road for laying Distribution Main for Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission at 04 | 24.36 | BP-2024-25-392 | 18/09/2024 | VCH/000506/2024-2025 |
189 | Purulia Division | BILL/00599/2024-2025 | 28/08/2024 | EQUIPMENTS AND SPARES AGENCIES | ORD/000551/2022-2023 | 676/PD | 25/04/2022 | Water supply Tap Connection Arrangement for 46 nos School upto 200 Students, 7 nos School for 201-500 Students, 1 no School for 501-800 Students and 1 no School above 800 Students within Manbazar-I Block (Part-A) of Purulia District under Purulia Division | 30.60 | BP-2024-25-349 | 06/09/2024 | VCH/000464/2024-2025 |
190 | Purulia Division | BILL/00753/2024-2025 | 19/09/2024 | GAJA ENGINEERING PRIVATE LIMITED | ORD/000897/2023-2024 | 1563/PD | 26/10/2023 | Design, Surveying, Engineering, Supplying, Construction, Erection, Installation, Testing And Commissioning Of Fixed Type Intake Jetty With Pump House, Construction Of Subs Stations; Raw Water Rising Main, Bank Protection, 158 MLD (Minimum) Capacity Water | 893.34 | BP-2024-25-404 | 22/09/2024 | VCH/000521/2024-2025 |
191 | Purulia Division | BILL/00898/2024-2025 | 02/10/2024 | SUBODH PRAMANIK | ORD/000479/2024-2025 | 1500/PD | 27/08/2024 | Laying of Loop Line for the distribution System at different command area of Patuara, Ramjibanpur, Bhomorbera,Lawadih etc of Satra under Marble Lake W/S Scheme Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | 20.75 | BP-2024-25-482 | 05/10/2024 | VCH/000637/2024-2025 |
192 | Purulia Division | BILL/00907/2024-2025 | 02/10/2024 | JYOTY SOLAR POWER | ORD/000297/2021-2022 | 1588/PD | 17/12/2021 | Installation of Stand-Alone Community Purification Plant (CPP) with provision of Tube Well, Solar Power Operated Pumping Machinery and Treatment Unit for removal of Fluoride in the left out Fluoride affected habitations as per IMIS Report (F-18 & C17C) 4 | 7.30 | BP-2024-25-511 | 06/10/2024 | VCH/000663/2024-2025 |
193 | Purulia Division | BILL/00930/2024-2025 | 03/10/2024 | SANDIP KUMAR DUBEY | ORD/000131/2024-2025 | 897/PD | 07/05/2024 | Repairing of DI Rising Main, construction of RCC Clear water reservoir (CWR) of capacity 150 Cum, New Boundary wall (Lenth=62 mtr) and 01 No. Sinking of RBT Tubewell (200X165 mm dia) and other allied works at Zone-VIII OHR campus of Raghunathpur W/S Schem | 18.95 | BP-2024-25-496 | 05/10/2024 | VCH/000647/2024-2025 |
194 | Purulia Division | BILL/00942/2024-2025 | 25/10/2024 | LABORATORY STAFFS | null | 1220-F(P2)/FA/Q/2M/493/12 | 07/03/2024 | Ad-hoc Bonus 2023-24 bill payment for the Laboratory 52 nos. @ Rs.6000/- staffs. | 3.12 | BP-2024-25-522 | 29/10/2024 | VCH/000679/2024-2025 |
195 | Purulia Division | BILL/00405/2024-2025 | 01/07/2024 | M/S ANAND SINGH | ORD/001599/2023-2024 | 1821/PD | 12/12/2023 | Construction and Commissioning of RCC Over Head Reservoir(s) including Laying Distribution Pipe Line(s) and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe Line (DI/HDPE), including Sluice Valves & FHTCs for t | 413.24 | BP-2024-25-216 | 08/07/2024 | VCH/000254/2024-2025 |
196 | Purulia Division | BILL/00409/2024-2025 | 04/07/2024 | MD AAMIR KHAN | ORD/000922/2022-2023 | 1889/PD | 15/12/2022 | Construction and Commissioning of RCC Over Head Reservoir (Intze type with solid raft) of capacity 400 cum and staging height 20 mtr. with including supply of all labour & materials for Sarbari W/S Scheme within Raghunathpur Sub-Division of Purulia Divis | 54.77 | BP-2024-25-244 | 22/07/2024 | VCH/000319/2024-2025 |
197 | Purulia Division | BILL/00423/2024-2025 | 09/07/2024 | ROY CONSTRUCTION | ORD/000127/2024-2025 | 895/PD | 07/05/2024 | Laying of DI rising main including bypass arrangement & other allied works & construction of boundary wall at Baghmundi WTP Site in Purulia Water Supply Scheme (Northern Sector) under Purulia Division, PHE Dte. | 25.72 | BP-2024-25-238 | 16/07/2024 | VCH/000303/2024-2025 |
198 | Purulia Division | BILL/00479/2024-2025 | 22/07/2024 | ANUP KUMAR SAHA CIVIL CONTRACTORS PRIVATE LIMITED | ORD/003455/2023-2024 | 317/PD | 01/03/2024 | Supply & delivery of spreading and levelling Filter media at Rapid Gravity sand filter beds after removal of existing not functioning filter media at Laxmanpur WTP under Purulia Division,P.H.E.Dte. | 15.83 | BP-2024-25-267 | 29/07/2024 | VCH/000347/2024-2025 |
199 | Purulia Division | BILL/00488/2024-2025 | 29/07/2024 | MOLLA ENTERPRISE | ORD/000992/2023-2024 | 1633/PD | 08/11/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - II of Neturia Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -B, Mouza - | 36.69 | BP-2024-25-288 | 06/08/2024 | VCH/000364/2024-2025 |
200 | Purulia Division | BILL/00495/2024-2025 | 29/07/2024 | M/S RAJ KUMAR KHAN | ORD/000034/2023-2024 | 584/PD | 20/04/2023 | Laying of Distribution System including pipe carrying structure all complete including cost of materials including providing Functional Household Tap Connection (FHTC) and other allied works for Aug. Work of Raghunathpur Water Supply Scheme (German Assist | 58.30 | BP-2024-25-276 | 02/08/2024 | VCH/000405/2024-2025 |
201 | Purulia Division | BILL/00521/2024-2025 | 05/08/2024 | SAIBAL SARKAR | ORD/001339/2023-2024 | 1722/PD | 04/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewell at Zone - II of Raghunathpur-II Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Division unde | 11.30 | BP-2024-25-299 | 13/08/2024 | VCH/000392/2024-2025 |
202 | Purulia Division | BILL/00531/2024-2025 | 09/08/2024 | ANUDIP SAHA | ORD/000100/2023-2024 | 862/PD | 30/06/2023 | Operation & Maintenance and water testing in the laboratory at Kashipur Sub District Laboratory under under RWS Purulia Sub Division PHE Dte. (w.e.f.01.07.2023 to 30.06.2024). | 3.54 | BP-2024-25-312 | 14/08/2024 | VCH/000385/2024-2025 |
203 | Purulia Division | BILL/00627/2024-2025 | 03/09/2024 | SABYASACHI MISHRA | ORD/003972/2023-2024 | 516/PD | 16/03/2024 | Laying of parallel line under command area of Kotshila Water Supply Scheme of Kotshila Block under Purulia Sadar Sub-Division under Purulia Division, PHE Dte (Chayadih Mouza) (Under Lagda W/S Scheme) | 6.05 | BP-2024-25-348 | 06/09/2024 | VCH/000463/2024-2025 |
204 | Purulia Division | BILL/00697/2024-2025 | 06/09/2024 | SUMIT KUMAR MITRA | ORD/003521/2023-2024 | 349/PD | 04/03/2024 | Construction of Boundary wall & Sinking of T/well at Jhalda-II,Zone-III under Purulia W/S Scheme under Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | 7.39 | BP-2024-25-391 | 18/09/2024 | VCH/000528/2024-2025 |
205 | Purulia Division | BILL/00795/2024-2025 | 26/09/2024 | BOSE CONSTRUCTION | ORD/000082/2022-2023 | 633/PD | 22/04/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at different habitation and extention of distribution pipe line under command area of Bandwan Water Supply Scheme of Bandwan Block under Puru | 38.34 | BP-2024-25-448 | 03/10/2024 | VCH/000586/2024-2025 |
206 | Purulia Division | BILL/00806/2024-2025 | 27/09/2024 | SUBODH PRAMANIK | ORD/000339/2024-2025 | 1365/PD | 25/07/2024 | Repairing of damage pipe line including House Connection arrangement for the works related to JICA Assisted West Bengal Pipped Water Supply Project(Purulia) of Satra Water Supply Scheme under Arsha Block. | 5.46 | BP-2024-25-457 | 03/10/2024 | VCH/000595/2024-2025 |
207 | Purulia Division | BILL/00815/2024-2025 | 28/09/2024 | MAHARSHI BANERJEE | ORD/000492/2024-2025 | 1707/PD | 05/09/2024 | Laying of Distribution line and Road Crossing and Construction of Sluice valve Chamber and other allied works for Kashipur under Kalyathol & Palaskhola W/S Scheme in connection with FHTC connection under Jal Jeevan Mission (JJM) Programme of Raghunathpur | 28.04 | BP-2024-25-467 | 04/10/2024 | VCH/000623/2024-2025 |
208 | Purulia Division | BILL/00821/2024-2025 | 28/09/2024 | M/S ANAND SINGH | ORD/001599/2023-2024 | 1821/PD | 12/12/2023 | Construction and Commissioning of RCC Over Head Reservoir(s) including Laying Distribution Pipe Line(s) and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe Line (DI/HDPE), including Sluice Valves & FHTCs for t | 248.68 | BP-2024-25-449 | 03/10/2024 | VCH/000577/2024-2025 |
209 | Purulia Division | BILL/00832/2024-2025 | 28/09/2024 | KHITISH CHANDRA PATHAK | ORD/000235/2024-2025 | 1075/PD | 07/06/2024 | Laying of HDPE Pipe (PE-100, PN-10) for collecting line of riverbed tubewell (for 1, 2, 3 & 4) under Raghunathpur W/S Scheme of Raghunathpur Sub-Division, under Purulia Division, PHE Dte. | 4.36 | BP-2024-25-485 | 05/10/2024 | VCH/000650/2024-2025 |
210 | Purulia Division | BILL/00836/2024-2025 | 28/09/2024 | SUJIT SAHANA | ORD/000836/2023-2024 | 1425/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoirs (Torch type with solid raft) of capacity 200 CUM and staging height 20 mtr as per approve drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other | 60.38 | BP-2024-25-468 | 04/10/2024 | VCH/000624/2024-2025 |
211 | Purulia Division | BILL/00851/2024-2025 | 29/09/2024 | M/S SB CONSTRUCTION | ORD/000148/2024-2025 | 919/PD | 07/05/2024 | Laying of DI pipe along with interconnection arrangement at OHR site & Construction of Boundary wall & pathway & Sinking of Tubewell at Purulia-I (Zone-V) under Purulia W/S Scheme (southern sector) of Purulia Division, PHE Dte. | 24.53 | BP-2024-25-458 | 03/10/2024 | VCH/000596/2024-2025 |
212 | Purulia Division | BILL/02107/2023-2024 | 21/03/2024 | PARTHA PRATIM CHHATAIT | ORD/000751/2022-2023 | 1251/PD | 30/08/2022 | Water supply Tap Connection Arrangement for 50 nos school upto 200 students within Kashipur Block (Part - C) of Purulia District under Purulia Division, PHE Dte. | 51.38 | BP-2024-25-222 | 10/07/2024 | VCH/001847/2023-2024 |
213 | Purulia Division | BILL/00462/2024-2025 | 16/07/2024 | BHAGABANDAS KUMAR | ORD/003523/2023-2024 | 350/PD | 04/03/2024 | Construction of Boundary wall & Sinking of T/well at Jhalda-II,Zone-VIII under Purulia W/S Scheme under Purulia Sadar Sub Division-under Purulia Division, PHE Dte. | 17.62 | BP-2024-25-260 | 23/07/2024 | VCH/000341/2024-2025 |
214 | Purulia Division | BILL/00465/2024-2025 | 19/07/2024 | MAA TARA CONSTRUCTION | ORD/000284/2023-2024 | 1141/PD | 17/08/2023 | Construction of boundary wall at Zone I H/W (OHR) site of Santuri block and sinking of 1 (one) no. Tubewell under surface Based Piped W/S Scheme Purulia Piped W/S Scheme (Northern Sector) under Raghunathpur Sub Division under Purulia Division PHE Dte. | 17.77 | BP-2024-25-273 | 29/07/2024 | VCH/000352/2024-2025 |
215 | Purulia Division | BILL/00466/2024-2025 | 19/07/2024 | PRIYATOSH MUKHERJEE | ORD/001864/2023-2024 | 90/PD | 15/01/2024 | Left Out Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at different habitation of Mouza-Rahardaga (Jl-64) & Mouza-Mirdi (Jl-102) and extension of Parallal distribution pipe line under command area of | 31.85 | BP-2024-25-272 | 29/07/2024 | VCH/000351/2024-2025 |
216 | Purulia Division | BILL/00558/2024-2025 | 20/08/2024 | SOUMITRA CHAKRABORTY | ORD/003969/2023-2024 | 513/PD | 16/03/2024 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM) and JAL SAPNA at different habitation and Laying of Branch distribution Pipeline of Kotshila W/S Scheme of Purulia Sadar Sub_Division under Purulia Divisio | 1.58 | BP-2024-25-330 | 22/08/2024 | VCH/000423/2024-2025 |
217 | Purulia Division | BILL/00568/2024-2025 | 22/08/2024 | CHOUDHURY STONE CRUSHING | ORD/003531/2023-2024 | 356/PD | 04/03/2024 | Construction of Boundary wall & Sinking of T/well at Purulia-II ,Zone-I under Purulia W/S Scheme under Purulia Sadar Sub Division under Purulia Division, PHE Dte. | 13.42 | BP-2024-25-347 | 06/09/2024 | VCH/000462/2024-2025 |
218 | Purulia Division | BILL/00573/2024-2025 | 23/08/2024 | PRAVAT SARKAR | ORD/000432/2021-2022 | 379/PD | 11/03/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at different habitation and extention of distribution pipe line under command area of Barabazar Water Supply Scheme of Barabazar Block under Pur | 12.90 | BP-2024-25-342 | 28/08/2024 | VCH/000448/2024-2025 |
219 | Purulia Division | BILL/00574/2024-2025 | 23/08/2024 | SOUMITRA CHAKRABORTY | ORD/000528/2022-2023 | 1058/PD | 08/07/2022 | Supplying & laying of HDPE Pipe line for Distribution System of Kotshila W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE Dte. (Mouza Name-Tiraldih or Goaladih) | 8.50 | BP-2024-25-337 | 28/08/2024 | VCH/000455/2024-2025 |
220 | Purulia Division | BILL/00724/2024-2025 | 13/09/2024 | NATIONAL PROJECTS CONSTRUCTION CORPORATION LIMITED | ORD/001600/2023-2024 | 41/PD | 08/01/2024 | Construction and Commissioning of RCC Over Head Reservoir(s) including Laying Distribution Pipe Line(s) and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe Line (DI/HDPE), including Sluice Valves & FHTCs for t | 132.14 | BP-2024-25-393 | 19/09/2024 | VCH/000507/2024-2025 |
221 | Purulia Division | BILL/00752/2024-2025 | 19/09/2024 | BASANTA KUMAR SINGHADEO | ORD/001044/2022-2023 | 276/PD | 27/02/2023 | Construction of Pump House (10 X 7 mtr) at Boosting Station under Raghunathpur W/S Scheme (German Project) of Raghunathpur Sub-Divn under Purulia Division, P.H.E. Dte. | 11.51 | BP-2024-25-398 | 22/09/2024 | VCH/000526/2024-2025 |
222 | Purulia Division | BILL/00768/2024-2025 | 21/09/2024 | AMIT PATHAK | ORD/000439/2024-2025 | 1502/PD | 27/08/2024 | Sinking of 1 (one) No. 200 mm dia DTH rigbored tubewell of Raghunathpur Water Supply Scheme (German Assisted) (Zone -V B)(Nanduka) within Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 4.55 | BP-2024-25-412 | 25/09/2024 | VCH/000530/2024-2025 |
223 | Purulia Division | BILL/00772/2024-2025 | 21/09/2024 | KM ENTERPRISES | ORD/000899/2023-2024 | 1567/PD | 26/10/2023 | Construction and Commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 150 CUM and staging height 20 mtr as per approved drawing (No: PC-I/OHR/3/2012) including Laying Distribution Pipe Lines and providing FHTCs including other | 69.19 | BP-2024-25-428 | 26/09/2024 | VCH/000543/2024-2025 |
224 | Purulia Division | BILL/00783/2024-2025 | 23/09/2024 | RABIN CHANDRA CHAIL | ORD/000804/2023-2024 | 1422/PD | 29/09/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 100 CUM and staging height 20 mtr as per approve drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other al | 22.43 | BP-2024-25-426 | 26/09/2024 | VCH/000546/2024-2025 |
225 | Purulia Division | BILL/00863/2024-2025 | 29/09/2024 | SINGHA ENTERPRISE | ORD/004055/2023-2024 | 526/PD | 16/03/2024 | Providing necessary water supply arrangement within school with connection from new Big-Dia D.T.H. Tube Well (200mm x 165mm) considering 200mt Dept and GI pipe of adequate dia and PVC pipes (medium duty confirming to the ASTMD-1785) and length where nece | 19.94 | BP-2024-25-494 | 05/10/2024 | VCH/000645/2024-2025 |
226 | Purulia Division | BILL/00890/2024-2025 | 01/10/2024 | M/S. S.P CONSTRUCTION | ORD/000100/2022-2023 | 635/PD | 22/04/2022 | roviding Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM) and JAL SAPNA at different habitation and extention of distribution pipe line of Panradda (Zone-V) W/S Scheme of Purulia Sadar Sub_Division under Purulia Divi | 8.12 | BP-2024-25-500 | 06/10/2024 | VCH/000652/2024-2025 |
227 | Purulia Division | BILL/00896/2024-2025 | 01/10/2024 | ASHOKE KUMAR CHATTERJEE | ORD/000893/2023-2024 | 1559/PD | 18/10/2023 | Construction and Commissioning of RCC Over Head Reservoir ( Torch type with solid raft ) of capacity 250 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe Line and providing FHTC including other | 31.40 | BP-2024-25-488 | 05/10/2024 | VCH/000580/2024-2025 |
228 | Purulia Division | BILL/00408/2024-2025 | 04/07/2024 | ANUP KUMAR SAHA | ORD/000269/2023-2024 | 1090/PD | 10/08/2023 | Survey, Investigation, Planning, Designing (aesthetically), Construction and Commissioning of a Conventional WATER TREATMENT PLANT and rising main of capacity 1521 KLD as per BIS/CPHEEO Manual consisting of all Civ | 32.00 | BP-2024-25-220 | 10/07/2024 | VCH/000274/2024-2025 |
229 | Purulia Division | BILL/00412/2024-2025 | 04/07/2024 | SADHAN GORAIN | ORD/003966/2023-2024 | 509/PD | 16/03/2024 | Laying of 250 mm dia MS Pipe and Road Crossing and Construction of PCC Approach Road at OHR site for Sindri-Chas W/S Scheme in connection with FHTC connection under Jal Jeevan Mission (JJM) Programme of Purulia Sadar Sub-Division under Purulia Division, | 22.82 | BP-2024-25-226 | 10/07/2024 | VCH/000259/2024-2025 |
230 | Purulia Division | BILL/00426/2024-2025 | 09/07/2024 | KHITISH CHANDRA PATHAK | ORD/003964/2023-2024 | 507/PD | 16/03/2024 | Road Crossing of rising main by jack pushing at Panchyet Road under Sarbari W/S Scheme of Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 8.85 | BP-2024-25-242 | 22/07/2024 | VCH/000316/2024-2025 |
231 | Purulia Division | BILL/00474/2024-2025 | 22/07/2024 | GAJA ENGINEERING PRIVATE LIMITED | ORD/000897/2023-2024 | 1563/PD | 26/10/2023 | Design, Surveying, Engineering, Supplying, Construction, Erection, Installation, Testing And Commissioning Of Fixed Type Intake Jetty With Pump House, Construction Of Subs Stations; Raw Water Rising Main, Bank Protection, 158 MLD (Minimum) Capacity Water | 826.97 | BP-2024-25-265 | 27/07/2024 | VCH/000344/2024-2025 |
232 | Purulia Division | BILL/00516/2024-2025 | 05/08/2024 | SADHAN GORAIN | ORD/000089/2023-2024 | 819/PD | 26/06/2023 | Repairing and Renovation of R.C.C. Elevated Reservoir of capacity 800 Cum (Intze Type) including bypass arrangement & other allied works in connection with Jal Jeevan Mission (JJM) for Augmentation of Zone-II of Balarampur W/S Scheme of Purulia Sadar Sub_ | 17.83 | BP-2024-25-295 | 12/08/2024 | VCH/000396/2024-2025 |
233 | Purulia Division | BILL/00517/2024-2025 | 05/08/2024 | M/S KHAN ENTERPRISE | ORD/001463/2023-2024 | 1778/PD | 08/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewellat OHR Site of Zone - XII of Kashipur Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Divisio | 14.38 | BP-2024-25-300 | 13/08/2024 | VCH/000391/2024-2025 |
234 | Purulia Division | BILL/00520/2024-2025 | 05/08/2024 | KM ENTERPRISES | ORD/001869/2023-2024 | 93/PD | 15/01/2024 | Construction of Office Cum Godown at PHE Campus Under Keliathole Palashkola w/s Scheme within Raghunathpur Sub-Division under Purulia Division, PHE Dte. | 25.44 | BP-2024-25-304 | 13/08/2024 | VCH/000377/2024-2025 |
235 | Purulia Division | BILL/00528/2024-2025 | 07/08/2024 | ARUNALOY SCIENTIFIC HOUSE | ORD/000444/2022-2023 | 302/PR | 23/06/2022 | Operation & Maintenance and water testing in the laboratory of Santuri Sub-District Water testing Laboratory under RWS purulia Sub-Division PHE Dte.(w.e.f.01.07.2022 to 30.06.2023). SL NO.07 | 1.10 | BP-2024-25-314 | 14/08/2024 | VCH/000387/2024-2025 |
236 | Purulia Division | BILL/00535/2024-2025 | 09/08/2024 | M/S ANAND SINGH | ORD/001599/2023-2024 | 1821/PD | 12/12/2023 | Construction and Commissioning of RCC Over Head Reservoir(s) including Laying Distribution Pipe Line(s) and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe Line (DI/HDPE), including Sluice Valves & FHTCs for t | 414.06 | BP-2024-25-306 | 14/08/2024 | VCH/000379/2024-2025 |
237 | Purulia Division | BILL/00679/2024-2025 | 05/09/2024 | MOONLIGHT HOUSE | ORD/000009/2023-2024 | 537/PD | 12/04/2023 | Laying of Loop Pipe Line for distribution System under command area Zone-I at different habitation For Providing Functional Household Tap Connection (FHTC) in connection under Jal Jeevan Mission (JJM and JAL SAPNA) of Manbazar II Block (part) Wat | 18.23 | BP-2024-25-369 | 13/09/2024 | VCH/000492/2024-2025 |
238 | Purulia Division | BILL/00798/2024-2025 | 26/09/2024 | MS D.PALIT AND CO. | ORD/001214/2022-2023 | 503/PD | 31/03/2023 | Laying of Loop Pipe Line for distribution System under command area Zone-II at different habitation For Providing Functional Household Tap Connection (FHTC) in connection under Jal Jeevan Mission (JJM and JAL SAPNA) of Manbazar II Block (part) Wa | 30.58 | BP-2024-25-473 | 04/10/2024 | VCH/000629/2024-2025 |
239 | Purulia Division | BILL/00814/2024-2025 | 28/09/2024 | SADHAN GORAIN | ORD/000400/2021-2022 | 217/PD | 08/02/2022 | Providing FHTC in connection with JJM & JAL SAPNA at different habitation and extension of distribution pipeline under command area of augmentation of Lagda W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE Dte. (Part-B : Water Supply | 26.43 | BP-2024-25-464 | 03/10/2024 | VCH/000620/2024-2025 |
240 | Purulia Division | BILL/00850/2024-2025 | 29/09/2024 | ASHOK KUMAR CHATTERJEE | ORD/000078/2023-2024 | 768/PD | 08/06/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire at Gobag Mouza, JL No.-58, Plot No.-620 under Neturia Block at OHR site under Raghunathpur W/S Scheme (German Project) of Raghunathpur Sub-Division under Purulia Division, P.H.E. Dte. | 7.72 | BP-2024-25-471 | 04/10/2024 | VCH/000627/2024-2025 |
241 | Purulia Division | BILL/00853/2024-2025 | 29/09/2024 | M/S SAYAK BHATTACHARYA | ORD/000333/2024-2025 | 1358/PD | 25/07/2024 | Supply and installtion of Pressure Shell / Pressure filter (Size- 3000 mm dia X 1800 mm) and laying of HDPE distribution pipe line at Bathanbari under Ramchandrapur W/S Scheme of Raghunathpur Sub-Division under Purulia Division, PHE Dte.(SM Code-SM/15039 | 34.30 | BP-2024-25-452 | 03/10/2024 | VCH/000589/2024-2025 |
242 | Purulia Division | BILL/00958/2024-2025 | 11/11/2024 | SOUTH EASTERN RAILWAY, RANCHI DIVISION | null | WL0703IB051111202412201575410323XX | 11/11/2024 | Indian Railways Miscellaneous collection against Merchant Reference no.WL0703IB051111202412201575410323XX DT.11-11-2024. | 1.06 | BP-2024-25-529 | 14/11/2024 | VCH/000704/2024-2025 |
243 | Purulia Division | BILL/00961/2024-2025 | 12/11/2024 | EXECUTIVE ENGINEER, PURULIA DIVISION PWD DTE. | null | 1536/PWD | 27/09/2024 | Restoration of Road after laying of drinking after pipe line under JAL Jeevan Mission for W/S Scheme along Raghunathpur Chalunia Road, in the District of Purulia under Purulia Division PWD Dte. during the year 2024-2025. (Memo No.1536/PWD dt.27.09.2024) ( | 47.28 | BP-2024-25-530 | 14/11/2024 | VCH/000705/2024-2025 |
244 | Purulia Division | BILL/00432/2024-2025 | 13/07/2024 | GLAMOUROOMS UNEMPLOYED CO-OPERATIVE SOCIETY LTD. | ORD/000621/2022-2023 | 1392/PD | 01/09/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at Hatuara Village of Raghabpur G.P. under command area of Bongabari Water Supply Scheme at Purulia-II Block under Purulia Sadar Sub-Division u | 16.53 | BP-2024-25-248 | 22/07/2024 | VCH/000323/2024-2025 |
245 | Purulia Division | BILL/00454/2024-2025 | 15/07/2024 | MS GORAIN CONCERN | ORD/001620/2023-2024 | 1830/PD | 12/12/2023 | Pushing of 600mm dia MS pipe and 100 mm dia MS water carrier pipe by hydraulic jacking method across Purulia to Jhalda Road for laying Distribution Main for Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission at 04 | 17.03 | BP-2024-25-246 | 22/07/2024 | VCH/000321/2024-2025 |
246 | Purulia Division | BILL/00458/2024-2025 | 15/07/2024 | SSPR VALVE MANUFACTURING PVT LTD | ORD/004361/2023-2024 | 55/PD | 09/01/2024 | Emergent Supply and delivery of sluice valve, MJ collar and all types of CIDF/DI specials for repairing and maintenance of pipe line under Kalyathol & Palaskhola Piped Water Supply Scheme of Raghunathpur Sub-Division under Purulia Division, PHE Dte. [Part | 8.10 | BP-2024-25-257 | 22/07/2024 | VCH/000339/2024-2025 |
247 | Purulia Division | BILL/00578/2024-2025 | 23/08/2024 | MANATOSH SINGH | ORD/000523/2022-2023 | 1039/PD | 07/07/2022 | Supplying & laying of HDPE pipe and laying of DI pipe line for Distribution System under augmentation of Kotshila W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE Dte. (Mouza Name-Timangda) | 11.06 | BP-2024-25-345 | 29/08/2024 | VCH/000451/2024-2025 |
248 | Purulia Division | BILL/00707/2024-2025 | 09/09/2024 | EFFLUENT & WATER TRETMENT ENGINEERS PVT LTD | ORD/000539/2023-2024 | 1340/PD | 08/09/2023 | Survey, Investigation, Planning, Designing (aesthetically), Construction and Commissioning of a Conventional WATER TREATMENT PLANT and rising main of capacity 712 KLD as per BIS/CPHEEO Manual consisting of all Civi | 52.18 | BP-2024-25-374 | 15/09/2024 | VCH/000495/2024-2025 |
249 | Purulia Division | BILL/00713/2024-2025 | 10/09/2024 | VIVEKANANDA CONSTRUCTION | ORD/001630/2023-2024 | 1837/PD | 12/12/2023 | Civil & Electrical Part related to NABL Recognition of Baghmundi Sub-District Laboratory as per ISO/IEC 17025:2017 Related to Support Activities Under Jal Jeevan Mission. | 5.71 | BP-2024-25-394 | 19/09/2024 | VCH/000508/2024-2025 |
250 | Purulia Division | BILL/00746/2024-2025 | 19/09/2024 | SUBRATA SINGHADEO | ORD/000245/2023-2024 | 1061/PD | 08/08/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - VI of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -E, Mouza - | 8.68 | BP-2024-25-397 | 22/09/2024 | VCH/000527/2024-2025 |
251 | Purulia Division | BILL/00751/2024-2025 | 19/09/2024 | CHATTERJEE CONSTRUCTION | ORD/000142/2024-2025 | 912/PD | 07/05/2024 | Sinking of 1(One) nos tube well, Withdrawing and relaying of DI Pipe, Earth filling and surface dressing Near Northern Sector Head work site under Purulia Piped w/s Scheme of Raghunathpur Sub-Division under Purulia Division, P.H.E. Dte. | 7.44 | BP-2024-25-403 | 22/09/2024 | VCH/000513/2024-2025 |
252 | Purulia Division | BILL/00756/2024-2025 | 21/09/2024 | SANTANU BANERJEE | ORD/000633/2022-2023 | 1401/PD | 01/09/2022 | Construction of RCC elevated reservoir of capacity 150 cum under Keliathole Palaskola W/S Scheme (Zone-I) of Raghunathpur Sub-Division under Purulia Division, P.H.E. Dte. | 18.09 | BP-2024-25-421 | 25/09/2024 | VCH/000539/2024-2025 |
253 | Purulia Division | BILL/00764/2024-2025 | 21/09/2024 | M/S SAYAK BHATTACHARYA | ORD/001451/2023-2024 | 1769/PD | 08/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewellat OHR Site of Zone - III of Kashipur Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Divisio | 21.95 | BP-2024-25-414 | 25/09/2024 | VCH/000532/2024-2025 |
254 | Purulia Division | BILL/00860/2024-2025 | 29/09/2024 | PRINCE INDUSTRIES ( INDIA) | ORD/000922/2023-2024 | 1595/PD | 31/10/2023 | Construction and commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the | 158.49 | BP-2024-25-501 | 06/10/2024 | VCH/000653/2024-2025 |
255 | Purulia Division | BILL/00893/2024-2025 | 01/10/2024 | MITHU BUILDERS | ORD/001104/2022-2023 | 270/PD | 24/02/2023 | Construction of RCC Over Head Reservoir (Torch type with solid raft) of capacity 150 cum and staging height 20 mtr and laying of Distribution System including pipe carrying structure all complete including providing House Hold Tap Connection (FHTC) and ot | 22.39 | BP-2024-25-507 | 06/10/2024 | VCH/000658/2024-2025 |
256 | Purulia Division | BILL/00895/2024-2025 | 01/10/2024 | SUJIT CHAKRABORTY | ORD/001049/2022-2023 | 281/PD | 27/02/2023 | Construction of Boundary wall with other allied works at river site pump house under Augmentation of Ramnagar W/S Scheme under Purulia Sadar Sub_ Division, PHE Dte. | 4.18 | BP-2024-25-509 | 06/10/2024 | VCH/000660/2024-2025 |
257 | Purulia Division | BILL/00902/2024-2025 | 02/10/2024 | BHAGABANDAS KUMAR | ORD/000273/2021-2022 | 1549/PD | 15/12/2021 | Construction of RCC clear water reservoir (CWR) of capacity 100 Cum with other allied works at Chitmu W/S Scheme under Purulia Sadar Sub-Division, PHE Dte. | 1.86 | BP-2024-25-508 | 06/10/2024 | VCH/000659/2024-2025 |
258 | Purulia Division | BILL/00910/2024-2025 | 02/10/2024 | M/S RAJ KUMAR KHAN | ORD/001334/2023-2024 | 1717/PD | 04/12/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 350 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) with allied works for purulia water supply scheme.(Location:-Block-Purulia - | 19.44 | BP-2024-25-490 | 05/10/2024 | VCH/000642/2024-2025 |
259 | Purulia Division | BILL/00931/2024-2025 | 03/10/2024 | SUBODH PRAMANIK | ORD/000538/2022-2023 | 1055/PD | 08/07/2022 | Supplying & laying of HDPE pipe and laying of DI pipe line for Distribution System of Kotshila W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE Dte. (Mouza Name-Banahatu) Zone-ii | 6.79 | BP-2024-25-497 | 05/10/2024 | VCH/000648/2024-2025 |
260 | Purulia Division | BILL/00936/2024-2025 | 03/10/2024 | FIDERE MARINE SERVICES PVT LTD | ORD/000154/2022-2023 | 755/PD | 02/05/2022 | Water supply Tap Connection Arrangement for 9 nos AWC within Purulia-I Block (Part-D) of Purulia District under Purulia Division, PHE Dte. | 13.24 | BP-2024-25-506 | 06/10/2024 | VCH/000657/2024-2025 |
261 | Purulia Division | BILL/00941/2024-2025 | 21/10/2024 | M/S SAYAK BHATTACHARYA | ORD/000261/2023-2024 | 1082/PD | 10/08/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - III of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -F , Mouza | 70.22 | BP-2024-25-516 | 23/10/2024 | VCH/000667/2024-2025 |
262 | Purulia Division | BILL/00943/2024-2025 | 25/10/2024 | SOUTH EASTERN RAILWAY, RANCHI DIVISION | null | WL0703IB052410202411410689904167XX | 24/10/2024 | Indian Railways Miscellaneous collection against Merchant Reference no.WL0703IB052410202411410689904167XX DT.24-10-2024. | 5.93 | BP-2024-25-520 | 29/10/2024 | VCH/000672/2024-2025 |
263 | Purulia Division | BILL/00312/2024-2025 | 11/06/2024 | AMAL KUMAR MUKHERJEE | ORD/000624/2022-2023 | 1394/PD | 01/09/2022 | Extension of PVC pipe line in distribution system for Stand Post at different School & ICDS Centre of Joypur Block to supply drinking water of command area of Joypur Water Supply Scheme under Purulia Sadar Sub-Division of Purulia Division, PHE Dte. | 0.62 | BP-2024-25-221 | 10/07/2024 | VCH/000256/2024-2025 |
264 | Purulia Division | BILL/00399/2024-2025 | 25/06/2024 | AMIT PATHAK | ORD/000135/2024-2025 | 905/PD | 07/05/2024 | Land development by earth filling with carried earth , Concrete road & Sinking of 1 (one) No. 200 mm dia DTH rigbored tubewell with other allied works of Raghunathpur Water Supply Scheme (German Assisted) (Zone -V B) within Raghunathpur Sub-Division unde | 16.49 | BP-2024-25-215 | 02/07/2024 | VCH/000228/2024-2025 |
265 | Purulia Division | BILL/00416/2024-2025 | 05/07/2024 | RAKSHIT ENTERPRISE | ORD/000884/2023-2024 | 1534/PD | 16/10/2023 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM) and JAL SAPNA at different habitation and laying of Branch distribution pipe line of Panradda (Zone-VII) W/S Scheme of Purulia Sadar Sub_Division under Puruli | 4.24 | BP-2024-25-234 | 11/07/2024 | VCH/000300/2024-2025 |
266 | Purulia Division | BILL/00422/2024-2025 | 09/07/2024 | MS D.PALIT AND CO. | ORD/000781/2023-2024 | 1421/PD | 29/09/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 350 CUM and staging height 20 mtr as per approved drawing (No: PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other | 119.57 | BP-2024-25-239 | 16/07/2024 | VCH/000304/2024-2025 |
267 | Purulia Division | BILL/00491/2024-2025 | 29/07/2024 | SADHAN GORAIN | ORD/000013/2023-2024 | 541/PD | 12/04/2023 | Construction of meter room, panel room, undercut pump house & surface drain with other allied works at Balarampur_Zone-II (Berma) OHR site for Augmentation of Balarampur W/S Scheme under Purulia Sadar Sub-Division, under Purulia Division, PHE Dte. | 10.46 | BP-2024-25-284 | 02/08/2024 | VCH/000368/2024-2025 |
268 | Purulia Division | BILL/00492/2024-2025 | 29/07/2024 | MOUSUMI BANERJEE | ORD/001350/2023-2024 | 1724/PD | 04/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewell at Zone - IV of Raghunathpur-II Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Division unde | 4.27 | BP-2024-25-277 | 02/08/2024 | VCH/000365/2024-2025 |
269 | Purulia Division | BILL/00493/2024-2025 | 29/07/2024 | BABA LOKNATH ENTERPRISE | ORD/000994/2023-2024 | 1634/PD | 08/11/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - II of Neturia Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -D, Mouza - | 37.40 | BP-2024-25-283 | 02/08/2024 | VCH/000363/2024-2025 |
270 | Purulia Division | BILL/00497/2024-2025 | 29/07/2024 | ROY CONSTRUCTION | ORD/003459/2023-2024 | 333/PD | 01/03/2024 | Construction of WBSEDCL Room of Bandwan W/S Scheme and and Other allied works under Purulia Sadar Sub-Division, under Purulia Division, PHE Dte. | 3.88 | BP-2024-25-275 | 02/08/2024 | VCH/000406/2024-2025 |
271 | Purulia Division | BILL/00498/2024-2025 | 29/07/2024 | MS CHANDI CHARAN ROY | ORD/001106/2022-2023 | 354/PD | 14/03/2023 | Construction of Over Head Reservoir (OHR) of 500 Cum Capacity, Staging Height 25 mtr. at Birgiri Mouza of Bangabari W/S Scheme under Purulia Sadar Sub-Division of Purulia Division, P.H.E Dte. (SL - 2) | 35.69 | BP-2024-25-281 | 02/08/2024 | VCH/000402/2024-2025 |
272 | Purulia Division | BILL/00511/2024-2025 | 05/08/2024 | SOUVIK MANDAL | ORD/003971/2023-2024 | 515/PD | 16/03/2024 | Laying of parallel line under command area of Kotshila Water Supply Scheme of Kotshila Block under Purulia Sadar Sub-Division under Purulia Division, PHE Dte (Uparbatri Mouza) (Under Lagda W/S Scheme) | 5.15 | BP-2024-25-302 | 13/08/2024 | VCH/000375/2024-2025 |
273 | Purulia Division | BILL/00513/2024-2025 | 05/08/2024 | CHANDAN CHATTERJEE | ORD/000251/2023-2024 | 1064/PD | 08/08/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - V of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -F , Mouza - | 5.93 | BP-2024-25-292 | 12/08/2024 | VCH/000372/2024-2025 |
274 | Purulia Division | BILL/00518/2024-2025 | 05/08/2024 | PRINCE INDUSTRIES ( INDIA) | ORD/000919/2023-2024 | 1596/PD | 31/10/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 200 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other a | 22.31 | BP-2024-25-298 | 13/08/2024 | VCH/000393/2024-2025 |
275 | Purulia Division | BILL/00678/2024-2025 | 05/09/2024 | KOUSHIK CHATTERJEE | ORD/000098/2023-2024 | 860/PD | 30/06/2023 | Operation & Maintenance and water testing in the laboratory at Jhalda-I Sub District Laboratory under under RWS Purulia Sub Division PHE Dte. (w.e.f.01.07.2023 to 30.06.2024). | 2.36 | BP-2024-25-358 | 12/09/2024 | VCH/000519/2024-2025 |
276 | Purulia Division | BILL/00796/2024-2025 | 26/09/2024 | GANGULY ENTERPRISES | ORD/003483/2023-2024 | 361/PD | 04/03/2024 | Construction of Boundary wall & Sinking of T/well at Mahara Tolapathardih(Purulia-II) under Bongabari W/S Scheme under Purulia Sadar Sub-Division under Purulia Division, PHE Dte. | 19.90 | BP-2024-25-437 | 29/09/2024 | VCH/000553/2024-2025 |
277 | Purulia Division | BILL/00797/2024-2025 | 26/09/2024 | KANAILAL PAL | ORD/000997/2022-2023 | 110/PD | 20/01/2023 | Construction of Boundary wall at Kachahatu Pump House Site under Kotshila W/S Scheme under Purulia Sadar Sub Division under Purulia Division, PHE Dte. | 14.91 | BP-2024-25-439 | 29/09/2024 | VCH/000555/2024-2025 |
278 | Purulia Division | BILL/00810/2024-2025 | 27/09/2024 | ROY CONSTRUCTION | ORD/000413/2021-2022 | 334/PD | 28/02/2022 | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at different habitation and extention of distribution pipe line under command area of Bandwan Water Supply Scheme of Bandwan Block under Puru | 5.22 | BP-2024-25-459 | 03/10/2024 | VCH/000618/2024-2025 |
279 | Purulia Division | BILL/00817/2024-2025 | 28/09/2024 | SOUVIK MANDAL | ORD/000346/2024-2025 | 1376/PD | 25/07/2024 | New sinking of 2(Two) nos 200mm dia riverbed tube wells (Horizontal) at river bed of Kansai along with laying of 100 mm dia GI connecting line of Puncha W/S at Purulia Water Supply Scheme (Northern Sector) under Purulia Division, PHE Dte. | 6.43 | BP-2024-25-503 | 06/10/2024 | VCH/000655/2024-2025 |
280 | Purulia Division | BILL/00824/2024-2025 | 28/09/2024 | HANNAN BUILDERS PRIVATE LIMITED | ORD/000834/2023-2024 | 1432/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenances of Distributions , Pipe Lines (DI/HDPE), including Sluice Valves & FHTCs for th | 218.91 | BP-2024-25-460 | 03/10/2024 | VCH/000578/2024-2025 |
281 | Purulia Division | BILL/00838/2024-2025 | 28/09/2024 | SABYASACHI MISHRA | ORD/000132/2024-2025 | 898/PD | 07/05/2024 | Laying of Distribution System of pipe line at Kakdiha village is a rest portion of Part-E including providing House Hold Tap Connection (FHTC) and other allied works for Aug. Kalyathol & Palaskhola Piped Water Supply Scheme within Raghunathpur Sub-Divisio | 14.18 | BP-2024-25-456 | 03/10/2024 | VCH/000594/2024-2025 |
282 | Purulia Division | BILL/00855/2024-2025 | 29/09/2024 | ALOK KUMAR CHAKRABORTY | ORD/000460/2024-2025 | 1519/PD | 27/08/2024 | Supplying laying fitting fixing of different dia pipe line & FHTC connection repairing (Damage of Old different dia pipe line & FHTC connection due to widening of road & Drain of PWD Roads from Doldoli more to Mourandih more &Karandih village ) in connec | 16.02 | BP-2024-25-455 | 03/10/2024 | VCH/000593/2024-2025 |
283 | Purulia Division | BILL/00947/2024-2025 | 30/10/2024 | ANUP KUMAR SAHA | ORD/000914/2023-2024 | 1579/PD | 30/10/2023 | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenance of Distributions, Pipe lines (DI/HDPE), including Sluice Valves & FHTCs for the | 64.74 | BP-2024-25-526 | 13/11/2024 | VCH/000701/2024-2025 |
284 | Purulia Division | BILL/00957/2024-2025 | 11/11/2024 | SOUTH EASTERN RAILWAY, RANCHI DIVISION | null | WL0703IB050611202404020185125751XX | 06/11/2024 | Indian Railways Miscellaneous collection against Merchant Reference no.WL0703IB050611202404020185125751XX DT.06-11-2024. | 1.06 | BP-2024-25-527 | 14/11/2024 | VCH/000702/2024-2025 |
285 | Purulia Division | BILL/00959/2024-2025 | 11/11/2024 | SOUTH EASTERN RAILWAY, RANCHI DIVISION | null | WL0703IB051111202412211573995764XX | 11/11/2024 | Indian Railways Miscellaneous collection against Merchant Reference no.WL0703IB051111202412211573995764XX DT.11-11-2024. | 1.06 | BP-2024-25-528 | 14/11/2024 | VCH/000703/2024-2025 |
286 | Purulia Division | BILL/02518/2023-2024 | 28/03/2024 | PREMNATH MITRA | ORD/000218/2022-2023 | 770/PD | 02/05/2022 | Water supply Tap Connection Arrangement for 41 nos School upto 200 Students, 4 nos School for 201-500 Students, 1 no School for 501-800 Students and 1 no School above 800 Students within RAGHUNATHPUR-1 BLOCK (Part-A) of Purulia District under Purulia Div | 19.99 | BP-2024-25-252 | 22/07/2024 | VCH/001850/2023-2024 |
287 | Purulia Division | BILL/00452/2024-2025 | 15/07/2024 | CHANDRA SHEKHAR KUNDU | ORD/003683/2023-2024 | 139/RNP | 12/03/2024 | Continuation Work Order for the Work of Hiring of Ambassador Car / Bolero for the Assistant Engineer, Raghunathpur Sub-Divn, PHE Dte. (w.e.f. 01/04/2024 to 31/08/2024) | 0.39 | BP-2024-25-326 | 21/08/2024 | VCH/000420/2024-2025 |
288 | Purulia Division | BILL/00550/2024-2025 | 13/08/2024 | AMIT PATHAK | ORD/000885/2023-2024 | 1535/PD | 16/10/2023 | Laying Distribution Pipe line and providing Functional Household Tap Connection (FHTC), including other allied work for Zone - IV of Santuri Block under Purulia Pipe Water Supply Scheme (Northern Sector) Under Purulia Division ,PHE Dte. [Part -A, Mouza - | 35.79 | BP-2024-25-322 | 21/08/2024 | VCH/000415/2024-2025 |
289 | Purulia Division | BILL/00575/2024-2025 | 23/08/2024 | SOUVIK MANDAL | ORD/000871/2023-2024 | 1521/PD | 16/10/2023 | Construction of Intake well with laying of horizontal strainer including allied works at the bank of Kansai river near Samsan Ghat at Puncha under Bongabari W/S Scheme of Purulia Sadar Sub- Division, Purulia Division, PHE Dte. | 29.80 | BP-2024-25-338 | 28/08/2024 | VCH/000444/2024-2025 |
290 | Purulia Division | BILL/00708/2024-2025 | 09/09/2024 | EFFLUENT & WATER TRETMENT ENGINEERS PVT LTD | ORD/000546/2023-2024 | 1338/PD | 08/09/2023 | Survey, Investigation, Planning, Designing (aesthetically), Construction and Commissioning of a Conventional WATER TREATMENT PLANT and rising main of capacity 421 KLD as per BIS/CPHEEO Manual consisting of all Civi | 45.58 | BP-2024-25-375 | 15/09/2024 | VCH/000496/2024-2025 |
291 | Purulia Division | BILL/00709/2024-2025 | 10/09/2024 | SHYAM KUMAR | ORD/000833/2023-2024 | 1417/PD | 29/09/2023 | Construction and Commissioning of RCC Over Head Reservoirs including Laying Distribution Pipe Lines and providing FHTCs including other allied works & Operation & Maintenances of Distributions , Pipe Lines (DI/HDPE), including Sluice Valves & FHTCs for th | 83.74 | BP-2024-25-372 | 13/09/2024 | VCH/000483/2024-2025 |
292 | Purulia Division | BILL/00718/2024-2025 | 12/09/2024 | WPIL LIMITED | ORD/001824/2023-2024 | 74/PD | 10/01/2024 | Design, Surveying, Engineering, Supplying and Construction, Erection, Installation, Testing and Commissioning of 9 Nos of Boosting Station, Pump house , Sub-station Building, Clear Water Raising Main upto 30 Nos of Delivery Point (Existing) & 145 Nos of O | 336.51 | BP-2024-25-382 | 17/09/2024 | VCH/000479/2024-2025 |
293 | Purulia Division | BILL/00727/2024-2025 | 13/09/2024 | SUBODH PRAMANIK | ORD/000206/2024-2025 | 1064/PD | 07/06/2024 | Sinking of 3 nos New 200 mm dia horizontal tube-well and laying of 100mm dia GI pipe collecting main from RBT to common manifold at river side of Satra Head Works site of Purulia water supply scheme (Northern Sector) under Purulia Division, P.H.E. Dte. | 17.96 | BP-2024-25-388 | 18/09/2024 | VCH/000503/2024-2025 |
294 | Purulia Division | BILL/00590/2024-2025 | 28/08/2024 | HIRAK KUMAR SAO | ORD/003546/2023-2024 | 329/PD | 01/03/2024 | Laying of DI pipeline and Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM and JAL SAPNA) at different habitation and other allied works of Sirkabad W/S Scheme of Purulia Sadar Sub-Division under Purulia Div | 7.08 | BP-2024-25-366 | 12/09/2024 | VCH/000489/2024-2025 |
295 | Purulia Division | BILL/00604/2024-2025 | 28/08/2024 | TUSHAR KANTI GORAI | ORD/000099/2023-2024 | 861/Pd | 30/06/2023 | Operation & Maintenance and water testing in the laboratory at Joypur Sub-District water testing Laboratory under RWS purulia Sub-Division PHE Dte. . (w.e.f.01.07.2023 to 30.06.2024). | 2.24 | BP-2024-25-353 | 06/09/2024 | VCH/000467/2024-2025 |
296 | Purulia Division | BILL/00739/2024-2025 | 19/09/2024 | JAL PRAVAHIKA PVT. LTD. | ORD/000271/2023-2024 | 1099/PD | 14/08/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 250 CUM and staging height 20 mtr as per approved drawing ( No:PC-I/OHR/3/2012) including Laying Distribution pipe line and providing FHTC including other | 92.19 | BP-2024-25-407 | 22/09/2024 | VCH/000515/2024-2025 |
297 | Purulia Division | BILL/00742/2024-2025 | 19/09/2024 | NANIGOPAL DEY | ORD/000819/2022-2023 | 1719/PD | 22/11/2022 | Acceptance cum Work Order for "Water supply Tap Connection Arrangement for 9 nos AWC within Manbazar-I Block (Part-N) of Purulia District under Purulia Division, PHE Dte.(Phase-IV)" | 4.13 | BP-2024-25-402 | 22/09/2024 | VCH/000522/2024-2025 |
298 | Purulia Division | BILL/00747/2024-2025 | 19/09/2024 | ASHOK KUMAR CHATTERJEE | ORD/000635/2022-2023 | 1403/PD | 01/09/2022 | Functional Household Tap Connection (FHTC) including other allied works of Sutaboi Water Supply Scheme under zone-I & zone-ii at Kashipur Block of Raghunathpur Sub Division under Purulia Division, PHE Dte. | 5.31 | BP-2024-25-406 | 22/09/2024 | VCH/000511/2024-2025 |
299 | Purulia Division | BILL/00757/2024-2025 | 21/09/2024 | GLAMOUROOMS UNEMPLOYED CO-OPERATIVE SOCIETY LTD. | ORD/000328/2021-2022 | 36/PD | 07/01/2022 | Providing FHTC & Supplying & laying different dia HDPE pipe line of distribution linewith allied works from OHR (zone-1) site to Mathorgoria village More & Balitora bauripara end to bramhan para of Balitora village under zone-I of Balitora W/S Scheme of | 21.20 | BP-2024-25-425 | 26/09/2024 | VCH/000545/2024-2025 |
300 | Purulia Division | BILL/00758/2024-2025 | 21/09/2024 | KOUSHIK CHATTERJEE | ORD/001011/2022-2023 | 178/PD | 07/02/2023 | Construction of RCC common manifold camber and Laying of 100 mm dia GI collecting line from riverbed tube-well to common manifold (remaining portion) & laying of 200 mm dia MS collecting main from manifold to CWR and at Lagda river bank of Kansai in conne | 12.09 | BP-2024-25-419 | 25/09/2024 | VCH/000537/2024-2025 |
301 | Purulia Division | BILL/00766/2024-2025 | 21/09/2024 | BBC ENTERPRISE | ORD/000902/2023-2024 | 1565/PD | 26/10/2023 | Construction and Commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 350 CUM and staging height 20 mtr as per approved drawing (No:PC-I/OHR/3/2012) including Laying Distribution Pipe Lines and providing FHTCs including other | 41.66 | BP-2024-25-422 | 25/09/2024 | VCH/000540/2024-2025 |
302 | Purulia Division | BILL/00771/2024-2025 | 21/09/2024 | PRINCE INDUSTRIES ( INDIA) | ORD/001476/2023-2024 | 1787/PD | 08/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewellat OHR Site of Zone - V of Raghunathpur-I Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Div | 18.24 | BP-2024-25-424 | 25/09/2024 | VCH/000542/2024-2025 |
303 | Purulia Division | BILL/00775/2024-2025 | 21/09/2024 | SADHAN GORAIN | ORD/000013/2018-2019 | 64/PD | 21/06/2019 | Construction of RCC Elevated Reservoir Capacity 200 cum (Intze Type).staging height 20mtr. including supplying & laying of HDPE pipe and laying of DI pipe line for Distribution system under Zone-VI of panradda W/S scheme under purulia Division .PHE Dte.Zo | 69.04 | BP-2024-25-420 | 25/09/2024 | VCH/000538/2024-2025 |
304 | Purulia Division | BILL/00787/2024-2025 | 26/09/2024 | S.PATHAK & CO. | ORD/001338/2023-2024 | 1721/PD | 04/12/2023 | Construction of Boundary wall, RCC Pillar, gate, Barbed wire & Sinking of 1(one) no tubewell at Zone - I of Raghunathpur-II Block under Surface Water Based Piped Water Supply Scheme for Purulia District (Northern Sector) of Raghunathpur Sub-Division unde | 16.58 | BP-2024-25-440 | 29/09/2024 | VCH/000556/2024-2025 |
305 | Purulia Division | BILL/00861/2024-2025 | 29/09/2024 | PRINCE INDUSTRIES ( INDIA) | ORD/000916/2023-2024 | 1597/PD | 31/10/2023 | Construction and Commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 400 CUM and staging height 20 mtr as per approved drawing (No: PC-I/OHR/3/2012) including Laying Distribution Pipe Lines and providing FHTCs including other | 51.30 | BP-2024-25-502 | 06/10/2024 | VCH/000654/2024-2025 |
306 | Purulia Division | BILL/00862/2024-2025 | 29/09/2024 | SAMAN KUMAR MAHATO | ORD/000764/2023-2024 | 1370/PD | 14/09/2023 | Construction and commissioning of RCC Over Head Reservoir (Torch type with solid raft) of capacity 100 CUM and staging height 20 mtr as per approved drawing (No: PC-I/OHR/3/2012) including Laying Distribution Pipe line and providing FHTC including other a | 44.71 | BP-2024-25-469 | 04/10/2024 | VCH/000625/2024-2025 |
307 | Purulia Division | BILL/00891/2024-2025 | 01/10/2024 | ROY CONSTRUCTION | ORD/001128/2022-2023 | 377/PD | 15/03/2023 | Repairing and Renovation of Pump house cum switch room including other allied works at Boludi OHR site in connection with Jal Jeevan Mission (JJM) for Augmentation of Manbazar W/S Scheme of Purulia Sadar Sub_Division under Purulia Division PHE Dte. | 1.07 | BP-2024-25-486 | 05/10/2024 | VCH/000640/2024-2025 |
Total | 13,680.08 |