Sl No. District
As per Census (2011)
Scheme
Parent Scheme as per PHED-MIS
Child Scheme
Retrofitting/ Augmentation Scheme under Parent Scheme as per PHED-MIS
No. of Villages
Villages covered under this Retrofitting/ Augmentation Scheme as per PHED-MIS
Total Households
Household information of the Covered Villages as entered by the Divisions
FHTCs
Approved FHTC Count considered under the Village Modified after appropriation in YDU as per PHED-MIS
Cost
Approved Implementation Cost Modified after appropriation in YDU considered under the Schemes as per PHED-MIS
AAFS Status
Status of Administrative and Financial Approval as per PHED-MIS
AAFS No. Tender Status
Status of Tender Invitation as per PHED Tender Module
WO Status
Status of Work Order Issuance as per PHED-MIS
3 10 6,398 5,962 321.51  
1 ALIPURDUAR PATLAKHAWA WATER SUPPLY SCHEME (SM/00151) F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Patlakhawa Piped Water Supply Scheme (Phase-2) (SM/07061) 2 1,689 1,581 93.85 Yes GO2021002759PH Yes Yes
2 ALIPURDUAR PATLAKHAWA WATER SUPPLY SCHEME (SM/00151) F.H.T.C Under Jaldhara/Jalswapna including retrofitting of existing distribution System under the command area of Patlakhawa Piped Water Supply Scheme (Phase-1) (SM/07060) 3 1,510 1,400 86.77 Yes GO2021002762PH Yes Yes
3 ALIPURDUAR PATLAKHAWA WATER SUPPLY SCHEME (SM/00151) AUGMENTATION OF PATLAKHAWA WATER SUPPLY SCHEME (SM/11401) 5 3,199 2,981 140.89 Yes GO2223004639PH Yes Yes
Total 10 6,398 5,962 321.51